Plan Review Stops For Permit 21100660 |
Review Stop |
AD |
ADDRESSING |
Rev No |
1 |
Status |
P |
Date |
2022-04-11 |
|
|
Cont ID |
|
Sent By |
cpuell |
Date |
2022-04-11 |
Time |
08:57 |
Rev Time |
0.00 |
Received By |
cpuell |
Date |
2022-04-11 |
Time |
08:57 |
Sent To |
|
|
Notes |
2022-04-11 08:57:36 | ADDRESS APPROPRIATE FOR PROJECT, DATABASES UPDATED. |
|
|
Review Stop |
ASBESTOS |
CONFIRM RPT SENT TO PBC HEALTH |
Rev No |
4 |
Status |
P |
Date |
2022-03-08 |
|
|
Cont ID |
|
Sent By |
aoliver |
Date |
2022-03-08 |
Time |
09:47 |
Rev Time |
0.00 |
Received By |
aoliver |
Date |
2022-03-08 |
Time |
09:47 |
Sent To |
|
|
Notes |
|
|
Review Stop |
ASBESTOS |
CONFIRM RPT SENT TO PBC HEALTH |
Rev No |
3 |
Status |
F |
Date |
2022-02-11 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2022-02-11 |
Time |
08:01 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2022-02-11 |
Time |
08:01 |
Sent To |
|
|
Notes |
2022-02-11 08:16:00 | PLEASE PROVIDE A SIGNED ACKNOWLEDGEMENT FROM THE | | CONTRACTOR, ON LETTERHEAD, STATING THAT THE | | INSTRUCTIONS ON THE WEBSITE OF ASBESTOS PROGRAM | | COORDINATOR, FLORIDA DEPARTMENT OF HEALTH PALM BEACH | | COUNTY WILL BE FOLLOWED, AND THAT NOTIFICATION WILL BE | | GIVEN TIMELY. | | | | ADDITIONAL INFORMATION REGARDING ASBESTOS REQUIREMENTS | | CAN BE FOUND ON THEIR WEBSITE: | | | | HTTP://PALMBEACH.FLORIDAHEALTH.GOV/PROGRAMS-AND-SERVICE | | S/ENVIRONMENTAL-HEALTH/AIR-QUALITY/ASBESTOS-DEMOLITION- | | RENOVATION.HTML | | |
|
|
Review Stop |
ASBESTOS |
CONFIRM RPT SENT TO PBC HEALTH |
Rev No |
2 |
Status |
F |
Date |
2022-01-06 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2022-01-06 |
Time |
08:34 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2022-01-06 |
Time |
08:34 |
Sent To |
|
|
Notes |
2022-01-06 08:35:41 | AN ASBESTOS REPORT IS NOT REQUIRED - | | | | PLEASE PROVIDE A SIGNED ACKNOWLEDGEMENT FROM THE | | CONTRACTOR, ON LETTERHEAD, STATING THAT THE | | INSTRUCTIONS ON THE WEBSITE OF ASBESTOS PROGRAM | | COORDINATOR, FLORIDA DEPARTMENT OF HEALTH PALM BEACH | | COUNTY WILL BE FOLLOWED, AND THAT NOTIFICATION WILL BE | | GIVEN TIMELY. | | | | ADDITIONAL INFORMATION REGARDING ASBESTOS REQUIREMENTS | | CAN BE FOUND ON THEIR WEBSITE: | | | | HTTP://PALMBEACH.FLORIDAHEALTH.GOV/PROGRAMS-AND-SERVICE | | S/ENVIRONMENTAL-HEALTH/AIR-QUALITY/ASBESTOS-DEMOLITION- | | RENOVATION.HTML | | |
|
|
Review Stop |
ASBESTOS |
CONFIRM RPT SENT TO PBC HEALTH |
Rev No |
1 |
Status |
F |
Date |
2021-11-30 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2021-11-30 |
Time |
16:33 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2021-11-30 |
Time |
16:15 |
Sent To |
|
|
Notes |
2021-11-30 16:34:58 | PLEASE PROVIDE A SIGNED ACKNOWLEDGEMENT FROM THE | | CONTRACTOR, ON LETTERHEAD, STATING THAT THE | | INSTRUCTIONS ON THE WEBSITE OF ASBESTOS PROGRAM | | COORDINATOR, FLORIDA DEPARTMENT OF HEALTH PALM BEACH | | COUNTY WILL BE FOLLOWED, AND THAT NOTIFICATION WILL BE | | GIVEN TIMELY. | | | | ADDITIONAL INFORMATION REGARDING ASBESTOS REQUIREMENTS | | CAN BE FOUND ON THEIR WEBSITE: | | | | HTTP://PALMBEACH.FLORIDAHEALTH.GOV/PROGRAMS-AND-SERVICE | | S/ENVIRONMENTAL-HEALTH/AIR-QUALITY/ASBESTOS-DEMOLITION- | | RENOVATION.HTML | | |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
3 |
Status |
P |
Date |
2022-02-11 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2022-02-11 |
Time |
08:17 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2022-02-11 |
Time |
08:17 |
Sent To |
|
|
Notes |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
P |
Date |
2022-01-06 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2022-01-06 |
Time |
08:31 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2022-01-06 |
Time |
08:31 |
Sent To |
|
|
Notes |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
P |
Date |
2021-11-30 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2021-11-30 |
Time |
16:35 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2021-11-30 |
Time |
16:35 |
Sent To |
|
|
Notes |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
2 |
Status |
P |
Date |
2022-02-14 |
|
|
Cont ID |
|
Sent By |
jleahy |
Date |
2022-02-14 |
Time |
11:57 |
Rev Time |
0.00 |
Received By |
jleahy |
Date |
2022-02-14 |
Time |
11:53 |
Sent To |
|
|
Notes |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
P |
Date |
2021-12-09 |
|
|
Cont ID |
|
Sent By |
jleahy |
Date |
2021-12-09 |
Time |
15:22 |
Rev Time |
0.00 |
Received By |
jleahy |
Date |
2021-12-09 |
Time |
15:19 |
Sent To |
|
|
Notes |
|
|
Review Stop |
FIRE |
FIRE DEPARTMENT |
Rev No |
3 |
Status |
P |
Date |
2022-01-25 |
|
|
Cont ID |
|
Sent By |
pleduc |
Date |
2022-01-25 |
Time |
|
Rev Time |
0.00 |
Received By |
pleduc |
Date |
2022-01-24 |
Time |
11:18 |
Sent To |
|
|
Notes |
2022-01-24 11:18:38 | FIRE PROVISO: | | | | THE FIRE SPRINKLER & FIRE ALARM SYSTEMS SHALL BE | | MAINTAINED THROUGHOUT DEMO & CONSTRUCTION PERIODS | | | | ALL FIRE SPRINKLER & FIRE ALARM WORK. INCLUDING DEMO, | | SHALL BE DONE UNDER SEPARATE PERMITS & SHOP DRAWINGS. | | | | PETER LEDUC | | FIRE MARSHAL | | 561-804-4709 | | [email protected] |
|
|
Review Stop |
FIRE |
FIRE DEPARTMENT |
Rev No |
2 |
Status |
P |
Date |
2021-12-27 |
|
|
Cont ID |
|
Sent By |
pleduc |
Date |
2021-12-27 |
Time |
|
Rev Time |
0.00 |
Received By |
pleduc |
Date |
2021-12-27 |
Time |
10:57 |
Sent To |
|
|
Notes |
2021-12-27 10:58:06 | FIRE PROVISO: | | | | THE FIRE SPRINKLER & FIRE ALARM SYSTEMS SHALL BE | | MAINTAINED THROUGHOUT DEMO & CONSTRUCTION PERIODS | | | | ALL FIRE SPRINKLER & FIRE ALARM WORK. INCLUDING DEMO, | | SHALL BE DONE UNDER SEPARATE PERMITS & SHOP DRAWINGS. | | | | PETER LEDUC | | FIRE MARSHAL | | 561-804-4709 | | [email protected] |
|
|
Review Stop |
FIRE |
FIRE DEPARTMENT |
Rev No |
1 |
Status |
P |
Date |
2021-10-26 |
|
|
Cont ID |
|
Sent By |
pleduc |
Date |
2021-10-26 |
Time |
|
Rev Time |
0.00 |
Received By |
pleduc |
Date |
2021-10-26 |
Time |
16:08 |
Sent To |
|
|
Notes |
2021-10-26 16:13:14 | FIRE PROVISO: | | | | THE FIRE SPRINKLER & FIRE ALARM SYSTEMS SHALL BE | | MAINTAINED THROUGHOUT DEMO & CONSTRUCTION PERIODS | | | | ALL FIRE SPRINKLER & FIRE ALARM WORK. INCLUDING DEMO, | | SHALL BE DONE UNDER SEPARATE PERMITS & SHOP DRAWINGS. | | | | PETER LEDUC | | FIRE MARSHAL | | 561-804-4709 | | [email protected] | | |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
6 |
Status |
N |
Date |
2022-04-01 |
|
|
Cont ID |
|
Sent By |
medwards |
Date |
2022-04-01 |
Time |
09:47 |
Rev Time |
0.00 |
Received By |
medwards |
Date |
2022-03-10 |
Time |
13:31 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
5 |
Status |
F |
Date |
2022-03-10 |
|
|
Cont ID |
|
Sent By |
medwards |
Date |
2022-03-10 |
Time |
09:28 |
Rev Time |
0.00 |
Received By |
medwards |
Date |
2022-03-08 |
Time |
11:46 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
4 |
Status |
N |
Date |
2022-03-08 |
|
|
Cont ID |
|
Sent By |
medwards |
Date |
2022-03-08 |
Time |
09:47 |
Rev Time |
0.00 |
Received By |
aoliver |
Date |
2022-02-17 |
Time |
10:56 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2022-02-14 |
|
|
Cont ID |
|
Sent By |
jleahy |
Date |
2022-02-14 |
Time |
11:57 |
Rev Time |
0.00 |
Received By |
jleahy |
Date |
2022-01-21 |
Time |
08:37 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
|
|
|
Cont ID |
|
Sent By |
|
Date |
2022-01-10 |
Time |
|
Rev Time |
0.00 |
Received By |
aoliver |
Date |
2021-12-22 |
Time |
09:09 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2021-12-09 |
|
|
Cont ID |
|
Sent By |
jleahy |
Date |
2021-12-09 |
Time |
15:22 |
Rev Time |
0.00 |
Received By |
jleahy |
Date |
2021-10-15 |
Time |
09:11 |
Sent To |
|
|
Notes |
|
|
Review Stop |
IMPACT |
COUNTY IMPACT FEES |
Rev No |
2 |
Status |
P |
Date |
2022-04-13 |
|
|
Cont ID |
|
Sent By |
lmarchan |
Date |
2022-04-13 |
Time |
13:48 |
Rev Time |
0.00 |
Received By |
lmarchan |
Date |
2022-04-05 |
Time |
07:27 |
Sent To |
|
|
Notes |
2022-04-13 11:00:52 | RECEIPT MU-2022-01642 - $6137.69 PAID | 2022-04-05 07:28:12 | 4/5/22 EMAILED IMPACT OFFICE FOR REVIEW. LEM |
|
|
Review Stop |
IMPACT |
COUNTY IMPACT FEES |
Rev No |
1 |
Status |
F |
Date |
2021-11-30 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2021-11-30 |
Time |
16:35 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2021-11-30 |
Time |
16:35 |
Sent To |
|
|
Notes |
2021-11-30 16:35:49 | PLANS WILL BE REVIEWED BY THE PBC IMPACT FEE OFFICE | | DIGITALLY VIA PROJECTDOX UPON NOTIFICATION BY THIS | | OFFICE. NOTIFICATION MAY OCCUR WHEN PLANS ARE NEAREST | | FINAL FORM. YOU MAY COORDINATE WITH THE IMPACT FEE | | OFFICE AT (561) 233-5025 OR SIMPLY UPLOAD THE MUNICIPAL | | IMPACT FEE QUESTIONNAIRE FORM TO YOUR PROJECT AND NAME | | THE FILE MUNICIPAL IMPACT FEE QUESTIONNAIRE. THE FORM | | CAN BE FOUND AT: HTTP://DISCOVER.PBCGOV.ORG/PZB/ADMINIS | | TRATION/PDF/IMPACTFEES/FORMS/QUESTIONNAIRE.PDF | | | | UPON APPROVAL AND FEE PAYMENT, PLEASE UPLOAD THE | | RECEIPT TO YOUR PROJECT OR EMAIL IT TO | | [email protected] . | | |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
6 |
Status |
P |
Date |
2022-04-01 |
|
|
Cont ID |
|
Sent By |
medwards |
Date |
2022-04-01 |
Time |
09:45 |
Rev Time |
0.00 |
Received By |
medwards |
Date |
2022-04-01 |
Time |
09:45 |
Sent To |
|
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
5 |
Status |
F |
Date |
2022-03-10 |
|
|
Cont ID |
|
Sent By |
medwards |
Date |
2022-03-10 |
Time |
09:27 |
Rev Time |
0.00 |
Received By |
medwards |
Date |
2022-03-10 |
Time |
09:27 |
Sent To |
|
|
Notes |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
4 |
Status |
F |
Date |
2022-03-07 |
|
|
Cont ID |
|
Sent By |
medwards |
Date |
2022-03-07 |
Time |
15:13 |
Rev Time |
0.00 |
Received By |
medwards |
Date |
2022-03-07 |
Time |
15:13 |
Sent To |
|
|
Notes |
2022-03-07 15:16:56 | PLEASE SEE PREVIOUS COMMENTS BELOW. THE MECHANICAL | | DRAWINGS WERE SUBMITTED THIS CYCLE BUT THE VENTILATION | | FOR THIS WORK AREA, BEAUTY SALON HAS NOT BEEN | | SUBMITTED. PLEASE PROVIDE THE OUTDOOR AIR CALCULATIONS | | FOR THIS BEAUTY SALON. FBC M 403.3.1.1 AND TABLE | | 403.3.1.1. IS THER GOING TO BE ANY NAIL STATIONS IN | | THIS BEAUTY SALON? IF SO PLEASE SHOW THE EXHAUST FOR | | EACH AREA. FBC M TABLE 403.3.1.1 | | | | THE DRAWING HAS CHANGED, PLEASE PROVIDE A CODE | | COMPLIANT MECHANICAL DRAWING SHOWING THIS BEAUTY SALON | | AND THE MECHANICAL SYSTEMS ASSOCIATED WITH A BEAUTY | | SALON ALONG WITH ADDRESSING THE COMMENTS FROM THE FIRST | | CYCLE MECHANICAL PLAN REVIEW LISTED BELOW. | | | | | | PLEASE PROVIDE A MECHANICAL DRAWING SHOWING THE | | MECHANICAL WORK COVERED UNDER THIS PROJECT. I.E. MOVING | | OF SUPPLY OR RETURN REGISTERS, THE DRYER EXHAUST DUCT | | AND TERMINATION LOCATION, THE BATHROOM EXHAUST FANS. | | AND THE TERMINATION LOCATIONS. IS THERE GOING TO BE A | | HOOD ABOVE THE RANGE? IF SO WILL IT BE DUCTED TO THE | | EXTERIOR? WHAT ARE THE EXHAUST CFM'S? DOES IT REQUIRE | | MAKE UP AIR? FBC 107.2.1 | | | | | | MICHAEL EDWARDS | | MECHANICAL EXAMINER | | 401 CLEMATIS STREET | | WEST PALM BEACH FL. 33401 | | 561-805-6728 | | [email protected] | | |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
3 |
Status |
F |
Date |
2022-02-10 |
|
|
Cont ID |
|
Sent By |
medwards |
Date |
2022-02-10 |
Time |
13:54 |
Rev Time |
0.00 |
Received By |
medwards |
Date |
2022-02-10 |
Time |
13:40 |
Sent To |
|
|
Notes |
2022-02-10 13:57:43 | THE DRAWING HAS CHANGED, PLEASE PROVIDE A CODE | | COMPLIANT MECHANICAL DRAWING SHOWING THIS BEAUTY SALON | | AND THE MECHANICAL SYSTEMS ASSOCIATED WITH A BEAUTY | | SALON ALONG WITH ADDRESSING THE COMMENTS FROM THE FIRST | | CYCLE MECHANICAL PLAN REVIEW LISTED BELOW. | | | | PLEASE RESPOND TO FIRST CYCLE MECHANICAL REVIEW | | COMMENTS BELOW: | | | | PLEASE PROVIDE A MECHANICAL DRAWING SHOWING THE | | MECHANICAL WORK COVERED UNDER THIS PROJECT. I.E. MOVING | | OF SUPPLY OR RETURN REGISTERS, THE DRYER EXHAUST DUCT | | AND TERMINATION LOCATION, THE BATHROOM EXHAUST FANS. | | AND THE TERMINATION LOCATIONS. IS THERE GOING TO BE A | | HOOD ABOVE THE RANGE? IF SO WILL IT BE DUCTED TO THE | | EXTERIOR? WHAT ARE THE EXHAUST CFM'S? DOES IT REQUIRE | | MAKE UP AIR? FBC 107.2.1 | | | | | | MICHAEL EDWARDS | | MECHANICAL EXAMINER | | 401 CLEMATIS STREET | | WEST PALM BEACH FL. 33401 | | 561-805-6728 | | [email protected] | | |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
2 |
Status |
F |
Date |
2021-12-30 |
|
|
Cont ID |
|
Sent By |
medwards |
Date |
2021-12-30 |
Time |
13:53 |
Rev Time |
0.00 |
Received By |
medwards |
Date |
2021-12-30 |
Time |
13:53 |
Sent To |
|
|
Notes |
2021-12-30 13:54:40 | PLEASE RESPOND TO FIRST CYCLE MECHANICAL REVIEW | | COMMENTS BELOW: | | | | PLEASE PROVIDE A MECHANICAL DRAWING SHOWING THE | | MECHANICAL WORK COVERED UNDER THIS PROJECT. I.E. MOVING | | OF SUPPLY OR RETURN REGISTERS, THE DRYER EXHAUST DUCT | | AND TERMINATION LOCATION, THE BATHROOM EXHAUST FANS. | | AND THE TERMINATION LOCATIONS. IS THERE GOING TO BE A | | HOOD ABOVE THE RANGE? IF SO WILL IT BE DUCTED TO THE | | EXTERIOR? WHAT ARE THE EXHAUST CFM'S? DOES IT REQUIRE | | MAKE UP AIR? FBC 107.2.1 | | | | | | MICHAEL EDWARDS | | MECHANICAL EXAMINER | | 401 CLEMATIS STREET | | WEST PALM BEACH FL. 33401 | | 561-805-6728 | | [email protected] | | |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
1 |
Status |
F |
Date |
2021-11-08 |
|
|
Cont ID |
|
Sent By |
medwards |
Date |
2021-11-08 |
Time |
16:54 |
Rev Time |
0.00 |
Received By |
medwards |
Date |
2021-11-08 |
Time |
16:54 |
Sent To |
|
|
Notes |
2021-11-08 16:59:35 | PLEASE PROVIDE A MECHANICAL DRAWING SHOWING THE | | MECHANICAL WORK COVERED UNDER THIS PROJECT. I.E. MOVING | | OF SUPPLY OR RETURN REGISTERS, THE DRYER EXHAUST DUCT | | AND TERMINATION LOCATION, THE BATHROOM EXHAUST FANS. | | AND THE TERMINATION LOCATIONS. IS THERE GOING TO BE A | | HOOD ABOVE THE RANGE? IF SO WILL IT BE DUCTED TO THE | | EXTERIOR? WHAT ARE THE EXHAUST CFM'S? DOES IT REQUIRE | | MAKE UP AIR? FBC 107.2.1 | | | | | | MICHAEL EDWARDS | | MECHANICAL EXAMINER | | 401 CLEMATIS STREET | | WEST PALM BEACH FL. 33401 | | 561-805-6728 | | [email protected] | | |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
4 |
Status |
P |
Date |
2022-02-25 |
|
|
Cont ID |
|
Sent By |
ccole |
Date |
2022-02-25 |
Time |
08:44 |
Rev Time |
0.00 |
Received By |
ccole |
Date |
2022-02-25 |
Time |
08:44 |
Sent To |
|
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
3 |
Status |
F |
Date |
2022-02-04 |
|
|
Cont ID |
|
Sent By |
ccole |
Date |
2022-02-04 |
Time |
10:46 |
Rev Time |
0.00 |
Received By |
ccole |
Date |
2022-02-04 |
Time |
09:33 |
Sent To |
|
|
Notes |
2022-02-04 10:46:25 | 3RD REVIEW FBC-2020 PLUMBING | | PERMIT- 21100660 | | 2/4/2022 | | | | CODES IN EFFECT: | | FBC P- FLORIDA PLUMBING CODE 7TH EDITION 2020 | | FBC ACC- FLORIDA ACCESSIBILITY CODE 7TH EDITION 2020 | | FBC B- FLORIDA BUILDING CODE 7TH EDITION 2020 | | FBC EX- FLORIDA EXISTING BUILDING CODE 7TH EDITION 2020 | | FS- FLORIDA STATUTES | | FAC- FLORIDA ADMINISTRATIVE CODE | | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC | | FAIR HOUSING DESIGN ACT MANUAL | | | | PLAN REVIEW RESULTS: DENIED. COMMENTS FROM THE 1ST AND | | 2ND REVIEW STILL EXIST. I AM REQUESTING THAT THE | | CONTRACTOR/DESIGNER FOR THE PROJECT CONTACT ME TO GO | | OVER THE PLANS EITHER BY TELPHONE OR ZOOM CALL. PLEASE | | NOTE THE PLUMBING PLANS SHALL BE SIGNED BY A FL. | | LICENSED ENGINEER OR PLUMBING CONTRACTOR. PLUMBING | | CONTRACTOR PLANS SHALL BEAR THE PRINTED NAME, LICENSE | | NUMBER AND SIGNATURE OF THE CONTRACTOR- SEC. 107.2.1 | | WPB. | | | | 1) SHEET P1: THE SANITARY ISOMETRIC DRAWING DOES NOT | | APPEAR TO REFLECT THE ACTUAL BUILDING DRAIN LAYOUT AS | | SHOWN ON THE FLOOR PLAN. A) BASED ON THE FLOOR PLAN THE | | KITCHEN SINK DRAIN SHALL CONNECT DOWNSTREAM OF THE | | WASHING MACHINE DRAIN CONNECTION AND BE INDIVIDUALLY | | VENTED- SECS. 910 & 911 FBC P. B) THE HAIR SINK DRAINS | | SHALL CONNECT DOWNSTREAM OF THE WC AND LAV AND SHALL BE | | INDIVIDUALLY VENTED IN ACCORDANCE WITH SECS. 910 & | | 912.1 FBC P. | | | | 2) P1: THE NOTES INDICATE A STACKABLE WD, HOWEVER THE | | PLANS SHOW THE UNITS SIDE BY SIDE. PLEASE CORRECT- SEC. | | 107.2.1 WPB. | | | | 3) P2: THE 1ST REVIEW COMMENT #2 STILL PARTIALLY | | EXISTS. A) PLEASE SHOW LAVATORY KNEE AND TOE | | CLEARANCES- PAGES 7.47- 7.52 FHDA. B) PLEASE SHOW THE | | DEPTH MEASUREMENT OF THE NEW SHOWER TO BE NO LESS THAN | | 36-INCHES PER PAGE 7.58 FHDA. | | | | 4) P2: THE 1ST REVIEW COMMENT #3 REQUESTING GRAB BAR | | REINFORCEMENT LOCATIONS STILL EXISTS. PLEASE PROVIDE | | ELEVATION DRAWINGS IN ACCORDANCE WITH- | | PAGES 6.3- 6.8- WATER CLOSETS. | | PAGES 6.12- 6.13- SHOWERS | | PAGES 6.14- 6.16 REINFORCEMENT METHODS | | FOR ADDITIONAL DRAWINGS PLEASE SEE FIGURES 3 & 5 OF THE | | FAIR HOUSING ACCESSIBILITY GUIDELINES CONTAINED IN THE | | FBC ACC. | | | | 5) P2: THE HEIGHT MEASUREMENT FOR THE SHOWER SEAT IS | | NOT LEGIBLE. PLEASE REFER TO PAGE 6.13 FHDA. THE HEIGHT | | SHALL BE 17-19 INCHES FROM THE FINISHED SHOWER FLOOR. | | | | 6) THE REQUESTED WATER DISTRIBUTION RISER WAS NOT | | PROVIDED. PLEASE PROVIDE THE DRAWING WHICH SHALL | | INCLUDE THE LOCATION OF THE WATER HEATER AND HOT WATER | | PIPING PLAN- SEC. 607.1 FBC P. | | | | 7) P2: PLEASE SHOW THE CENTERLINE OF THE WATER CLOSET | | DRAIN WILL BE 18 INCHES MEASURED FROM THE ADJACENT | | FINISHED WALL- PAGE 7.43 FHDA. | | | | 8) P3: SHOW THE SHOWER PAN LINER WILL BE PITCHED ONE | | FOURTH UNIT VERTICAL IN 12 UNITS HORIZONTAL (1/4 INCH | | PER FT. OR 2% SLOPE)- SEC. 417.5.2 FBC P. | | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | RE-SUBMITTAL FORM. | | | | CHRISTOPHER L. COLE | | MECHANICAL/PLUMBING PLANS EXAMINER | | 401 CLEMATIS STREET | | WEST PALM BEACH FL 33401 | | 561-805-6719 | | [email protected] | | |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
2 |
Status |
F |
Date |
2022-01-10 |
|
|
Cont ID |
|
Sent By |
ccole |
Date |
2022-01-10 |
Time |
09:54 |
Rev Time |
0.00 |
Received By |
ccole |
Date |
2022-01-10 |
Time |
08:05 |
Sent To |
|
|
Notes |
2022-01-10 09:55:32 | 2ND REVIEW FBC-2020 PLUMBING | | PERMIT- 21100660 | | 1/10/2022 | | | | CODES IN EFFECT: | | FBC P- FLORIDA PLUMBING CODE 7TH EDITION 2020 | | FBC ACC- FLORIDA ACCESSIBILITY CODE 7TH EDITION 2020 | | FBC B- FLORIDA BUILDING CODE 7TH EDITION 2020 | | FBC EX- FLORIDA EXISTING BUILDING CODE 7TH EDITION 2020 | | FS- FLORIDA STATUTES | | FAC- FLORIDA ADMINISTRATIVE CODE | | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC | | FAIR HOUSING DESIGN ACT MANUAL | | | | PLAN REVIEW RESULTS: DENIED. | | | | 1) SHEET P1: THE SANITARY ISOMETRIC DRAWING DOES NOT | | APPEAR TO REFLECT THE ACTUAL BUILDING DRAIN LAYOUT AS | | SHOWN ON THE FLOOR PLAN. A) BASED ON THE FLOOR PLAN THE | | KITCHEN SINK DRAIN SHALL CONNECT DOWNSTREAM OF THE | | WASHING MACHINE DRAIN CONNECTION AND BE INDIVIDUALLY | | VENTED- SECS. 910 & 911 FBC P. B) THE HAIR SINK DRAINS | | SHALL CONNECT DOWNSTREAM OF THE WC AND LAV AND SHALL BE | | INDIVIDUALLY VENTED IN ACCORDANCE WITH SEC. 912.1 WET | | VENTING FBC P. | | | | 2) P1: THE NOTES INDICATE A STACKABLE WD, HOWEVER THE | | PLANS SHOW THE UNITS SIDE BY SIDE. PLEASE CORRECT- SEC. | | 107.2.1 WPB. | | | | 3) P2: THE 1ST REVIEW COMMENT #2 STILL PARTIALLY | | EXISTS. A) PLEASE SHOW LAVATORY KNEE AND TOE | | CLEARANCES- PAGES 7.47- 7.52 FHDA. B) PLEASE SHOW THE | | DEPTH MEASUREMENT OF THE NEW SHOWER TO BE NO LESS THAN | | 36-INCHES PER PAGE 7.58 FHDA. | | | | 4) P2: THE 1ST REVIEW COMMENT #3 REQUESTING GRAB BAR | | REINFORCEMENT LOCATIONS STILL EXISTS. PLEASE PROVIDE | | ELEVATION DRAWINGS IN ACCORDANCE WITH- | | PAGES 6.3- 6.8- WATER CLOSETS. | | PAGES 6.12- 6.13- SHOWERS | | PAGES 6.14- 6.16 REINFORCEMENT METHODS | | FOR ADDITIONAL DRAWINGS PLEASE SEE FIGURES 3 & 5 OF THE | | FAIR HOUSING ACCESSIBILITY GUIDELINES CONTAINED IN THE | | FBC ACC. | | | | 5) P2: THE HEIGHT MEASUREMENT FOR THE SHOWER SEAT IS | | NOT LEGIBLE. PLEASE REFER TO PAGE 6.13 FHDA. THE HEIGHT | | SHALL BE 17-19 INCHES FROM THE FINISHED SHOWER FLOOR. | | | | 6) THE REQUESTED WATER DISTRIBUTION RISER WAS NOT | | PROVIDED. PLEASE PROVIDE THE DRAWING WHICH SHALL | | INCLUDE THE LOCATION OF THE WATER HEATER AND HOT WATER | | PIPING PLAN- SEC. 607.1 FBC P. | | | | 7) P2: PLEASE SHOW THE CENTERLINE OF THE WATER CLOSET | | DRAIN WILL BE 18 INCHES MEASURED FROM THE ADJACENT | | FINISHED WALL- PAGE 7.43 FHDA. | | | | 8) P3: SHOW THE SHOWER PAN LINER WILL BE PITCHED ONE | | FOURTH UNIT VERTICAL IN 12 UNITS HORIZONTAL (1/4 INCH | | PER FT. OR 2% SLOPE)- SEC. 417.5.2 FBC P. | | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | RE-SUBMITTAL FORM. | | | | CHRISTOPHER L. COLE | | MECHANICAL/PLUMBING PLANS EXAMINER | | 401 CLEMATIS STREET | | WEST PALM BEACH FL 33401 | | 561-805-6719 | | [email protected] | | |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
F |
Date |
2021-11-15 |
|
|
Cont ID |
|
Sent By |
ccole |
Date |
2021-11-15 |
Time |
15:10 |
Rev Time |
0.00 |
Received By |
ccole |
Date |
2021-11-15 |
Time |
12:37 |
Sent To |
|
|
Notes |
2021-11-15 15:13:14 | 1ST REVIEW FBC-2020 PLUMBING | | PERMIT- 21100660 | | 11/15/2021 | | | | CODES IN EFFECT: | | FBC P- FLORIDA PLUMBING CODE 7TH EDITION 2020 | | FBC ACC- FLORIDA ACCESSIBILITY CODE 7TH EDITION 2020 | | FBC B- FLORIDA BUILDING CODE 7TH EDITION 2020 | | FBC EX- FLORIDA EXISTING BUILDING CODE 7TH EDITION 2020 | | FS- FLORIDA STATUTES | | FAC- FLORIDA ADMINISTRATIVE CODE | | WPB- WEST PALM BEACH AMENDMENTS TO THE FBC | | FAIR HOUSING DESIGN ACT MANUAL | | | | PLAN REVIEW RESULTS: DENIED. | | | | 1) SHEET A-1: PROVIDE DESIGN CRITERIA FOR THE PROJECT | | INCLUDING A LIST OF CURRENT CODES AND STANDARDS- | | SECTION 107.2.1 WPB. | | | | 2) A-1 & P-1: FAIR HOUSING ACT COMPLIANCE: TWO CITY | | PLAZA IS A MULTI-STORY CONDOMINIUM BUILDING THAT WERE | | DESIGNED AND CONSTRUCTED IN ACCORDANCE WITH THE FAIR | | HOUSING ACT DESIGN GUIDELINES. REFER TO PAGE 7 OF THE | | MANUAL WHICH REQUIRES THE GROUND FLOOR LEVEL OF UNIT | | 101 TO IN COMPLIANCE WITH THE GUIDELINES. | | A) THE DESIGN PROFESSIONAL OF RECORD SHALL INDICATE ON | | THE PLANS WHICH OF THE TWO BATHROOM TYPES IS THE BASIS | | OF DESIGN- SPECIFICATION TYPE A OR B ON THE PLANS. | | PLEASE REFER TO PAGES 7.34- 7.39 OF THE DESIGN MANUAL | | FOR EXPLANATORY INFORMATION ON SPECIFICATION A & B AND | | SHOW COMPLIANCE. | | 2) REFER TO CHAPTER 7 (REQUIREMENT 7 USABLE KITCHENS & | | USABLE BATHROOMS) AND PROVIDE ENLARGED, DIMENSIONED | | KITCHEN AND BATHROOM DRAWINGS AND DETAILS. THE PLANS | | SHALL BE IN COMPLIANCE WITH THE SECTIONS LISTED BELOW- | | PAGES 7.1- 7.6 CLEAR FLOOR SPACES FOR SINKS AND | | APPLIANCES | | PAGES 7.7- 7.11 CLEARANCES BETWEEN KITCHEN COUNTERS AND | | ALL OPPOSING ELEMENTS. | | PAGES 7.12- 7.16 REMOVABLE SINK AND APPLIANCE CABINET | | DOORS INCLUDING KNEE SPACES. | | PAGES 7.40-7.46 WATER CLOSET CLEAR FLOOR SPACES. | | PAGES 7.47- 7.52: LAVATORY AND VANITY CLEAR FLOOR AND | | KNEE AND TOE CLEARANCES. | | PAGES 7.56- 7.59: SHOWER CLEAR FLOOR SPACE AND CONTROL | | LOCATIONS INCLUDING SHOWER DIMENSIONS. | | | | 3) REFER TO CHAPTER 6 (REINFORCED WALLS FOR GRAB BARS). | | BASED ON CHAPTER 7 COMPLIANCES LISTED ABOVE, PLEASE | | PROVIDE DRAWINGS AND DETAILS SHOWING GRAB BAR | | REINFORCEMENT LOCATIONS AND INSTALLATION DETAILS. | | PAGES 6.3- 6.8- WATER CLOSETS. | | PAGES 6.12- 6.13- SHOWERS | | PAGES 6.14- 6.16 REINFORCEMENT METHODS | | | | 4) P-1: THE ISOMETRIC DRAWING DOES NOT SHOW THE | | REQUIRED VENTS FOR THE PLUMBING FIXTURES- SECTION | | 901.2.1 FBC P. | | | | 5) P-1: THE 2-INCH VERTICAL DRAIN STACK AND HORIZONTAL | | BRANCH ARE UNDERSIZED- MINIMUM 3-INCH DRAINS ARE | | REQUIRED- SECTION 406.2 FBC P. | | | | 6) P-1: PLEASE OUTLINE THE NEW DRAIN LOCATIONS ON THE | | FLOOR PLAN AND PROVIDE A SLAB REPAIR DETAIL- SECTION | | 107.2.1 WPB. | | | | 7) P-1: PROVIDE A WATER DISTRIBUTION RISER DRAWING- | | SECTION 107.3.5.1.3 WPB. PROVIDE SYMBOLS ON THE DRAWING | | TO INDICATE LOCATIONS OF REQUIRED WATER HAMMER | | ARRESTORS AND BACKFLOW PREVENTERS- SECTION 604.9 & | | 608.3 FBC P. | | | | 8) P-1 & P-2: PROVIDE A PLUMBING FIXTURE SCHEDULE | | LISTING THE MAKES AND MODELS OF THE WATER CLOSETS, | | LAVATORIES, SHOWER VALVES AND FAUCETS, KITCHEN SINK, | | DISHWASHING MACHINE, WASHING MACHINE- SECTIONS 405- 425 | | FBC P. | | | | 9) P-1 & P-2: INDICATE THE TYPE OF FINISH MATERIALS FOR | | THE FLOORS AND WALLS OF THE SHOWERS- 421.5.1 AND | | PROVIDE A SHOWER PAN DETAIL- 421.5.2 FBC P. | | | | 10) P-1: INDICATE THE TYPE OF 2X4 WOOD BACKING TO BE | | INSTALLED FOR THE GRAB BAR REINFORCEMENTS AND PROVIDE | | INSTALLATION DETAILS- SECTIONS 603.1 AND 1607.8.2 FBC | | B. | | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | RE-SUBMITTAL FORM. | | | | CHRISTOPHER L. COLE | | MECHANICAL/PLUMBING PLANS EXAMINER | | 401 CLEMATIS STREET | | WEST PALM BEACH FL 33401 | | 561-805-6719 | | [email protected] | | |
|
|
Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
Rev No |
2 |
Status |
N |
Date |
2021-12-22 |
|
|
Cont ID |
|
Sent By |
ccole |
Date |
2021-12-22 |
Time |
09:57 |
Rev Time |
0.00 |
Received By |
ccole |
Date |
2021-12-22 |
Time |
09:57 |
Sent To |
|
|
Notes |
2021-12-22 09:58:26 | CONTRACTOR DRAWINGS- DIG/SIG REVIEW NOT REQUIRED. |
|
|
Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
Rev No |
1 |
Status |
N |
Date |
2021-10-15 |
|
|
Cont ID |
|
Sent By |
mpeterso |
Date |
2021-10-15 |
Time |
10:01 |
Rev Time |
0.00 |
Received By |
mpeterso |
Date |
2021-10-15 |
Time |
10:00 |
Sent To |
|
|
Notes |
2021-10-15 10:01:48 | CONTRACTOR DRAWINGS NOT REQUIRED TO HAVE SIGNATURE | | REVEIW |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
N |
Date |
2021-10-27 |
|
|
Cont ID |
|
Sent By |
aaponte |
Date |
2021-10-27 |
Time |
10:50 |
Rev Time |
0.00 |
Received By |
ckimmerl |
Date |
2021-10-27 |
Time |
10:50 |
Sent To |
|
|
Notes |
|
|