Plan Review Stops For Permit 21091098 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
P |
Date |
2021-09-26 |
|
|
Cont ID |
|
Sent By |
cthroop |
Date |
2021-09-26 |
Time |
08:14 |
Rev Time |
0.00 |
Received By |
cthroop |
Date |
2021-09-24 |
Time |
13:21 |
Sent To |
|
|
Notes |
2021-09-26 08:15:39 | COPY OF APPROVED VARIANCE FROM THE CONSTRUCTION BOARD | | OF ADJUSTMENT AND APPEALS HAS BEEN SUBMITTED. CT |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2021-09-26 |
|
|
Cont ID |
|
Sent By |
cthroop |
Date |
2021-09-26 |
Time |
07:27 |
Rev Time |
0.00 |
Received By |
cthroop |
Date |
2021-09-23 |
Time |
15:45 |
Sent To |
|
|
Notes |
|
|
Review Stop |
NFIP |
NFIP REVIEW ACTIVITY |
Rev No |
1 |
Status |
P |
Date |
2021-09-26 |
|
|
Cont ID |
|
Sent By |
cthroop |
Date |
2021-09-26 |
Time |
08:14 |
Rev Time |
0.00 |
Received By |
cthroop |
Date |
2021-09-24 |
Time |
13:21 |
Sent To |
|
|
Notes |
2021-09-26 07:27:02 | COPY OF APPROVED VARIANCE FROM THE CONSTRUCTION BOARD | | OF ADJUSTMENT AND APPEALS HAS BEEN SUBMITTED. CT |
|
|
|