Plan Review Details - Permit 21031571
Plan Review Stops For Permit 21031571
Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 1 Status N Date 2021-03-30 Cont ID  
Sent By shill Date 2021-03-30 Time 15:17 Rev Time 0.00
Received By shill Date 2021-03-30 Time 15:17 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 2 Status P Date 2021-10-26 Cont ID  
Sent By cthroop Date 2021-10-26 Time 16:43 Rev Time 0.00
Received By cthroop Date 2021-10-26 Time 08:01 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status F Date 2021-05-03 Cont ID  
Sent By lcrespo Date 2021-05-03 Time 16:18 Rev Time 0.00
Received By lcrespo Date 2021-05-03 Time 16:19 Sent To  
Notes
2021-05-03 16:19:0505/03/21 1ST GAS REVIEW**DENIED** WITH COMMENTS
  
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME, AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1. PLEASE HAVE A SIGNATURE ON THE ISOMETRIC DRAWING OF
 THE PERSON DESIGNING THE SYSTEM, NOT IN ACCORDANCE WITH
 FLORIDA ADMINISTRATIVE CODE 61G15-23.001, FLORIDA
 STATUTE 471 PER THE WPB AMENDMENTS TO THE FBC SEC.
 107.1 GENERAL.
  
 2. SUBMIT MANUFACTURER'S SPECIFICATION
 SHEETS/INSTALLATION MANUAL FOR THE FIRE PIT TO VERIFY
 COMPLIANCE WITH 2020 FBC RES. SEC. G2408.1.
  
 3. GAS APPLIANCES SHALL BE LISTED AND LABELED. THE
 INSTALLATION MANUALS FOR ALL GAS APPLIANCES/EQUIPMENT
 SHALL BE ONSITE AT THE TIME OF INSPECTION PER THE 2020
 FBC RES. SEC. G2413.2 AND G2404.3.
  
 4. THE ORIGINAL GAS PLAN WAS SUBMITTED BY AN ARCHITECT,
 AND THE REVISION IS SUBMITTED BY A GAS CONTRACTOR. IF
 THE GAS CONTRACTOR IS TAKING OVER PLEASE HAVE
 ADMINISTRATIVE DOCUMENTATION PROVIDED FOR THE CHANGE
 PER THE WPB AMENDMENTS TO THE FBC SEC. 107.2.1
 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
 5. PLEASE PROVIDE A GAS RISER DIAGRAM PER THE WPB
 AMENDMENTS TO THE FBC SEC. 107.3.5.3 (13) RESIDENTIAL
 GAS.
  
 WHEN RESUBMITTING PLANS, PLEASE INDICATE THE REVISION &
 REMOVE ANY VOIDED SHEETS & REPLACE ANY NECESSARY PAGES.
 A TRANSMITTAL LETTER LISTING THE ORIGINAL REVIEW
 COMMENT NUMBER, WITH A DESCRIPTION OF THE REVISION
 MADE, IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE
 THE CHANGES CAN BE FOUND WILL HELP EXPEDITE YOUR
 PERMIT. THANK YOU FOR YOUR ANTICIPATED COOPERATION.
  
 HTTPS://CODES.ICCSAFE.ORG/CODES/FLORIDA
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2021-10-27 Cont ID  
Sent By lmarchan Date 2021-10-27 Time 16:52 Rev Time 0.00
Received By lmarchan Date 2021-10-07 Time 16:04 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2021-05-03 Cont ID  
Sent By lcrespo Date 2021-05-03 Time 16:19 Rev Time 0.00
Received By lcrespo Date 2021-05-03 Time 11:12 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2021-04-22 Cont ID  
Sent By shill Date 2021-04-22 Time 11:33 Rev Time 0.00
Received By shill Date 2021-04-13 Time 14:54 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status N Date 2021-10-26 Cont ID  
Sent By cthroop Date 2021-10-26 Time 16:43 Rev Time 0.00
Received By cthroop Date 2021-10-26 Time 08:01 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status N Date 2021-05-03 Cont ID  
Sent By lcrespo Date 2021-05-03 Time 16:19 Rev Time 0.00
Received By lcrespo Date 2021-05-03 Time 16:19 Sent To  
Notes
***NONE***

Review Stop PRIVATEPRV PRIVATE PROVIDER DOCUMENTS
Rev No 3 Status P Date 2021-10-27 Cont ID  
Sent By rgathrig Date 2021-10-27 Time 15:51 Rev Time 0.00
Received By rgathrig Date 2021-10-27 Time 15:51 Sent To  
Notes
***NONE***

Review Stop PRIVATEPRV PRIVATE PROVIDER DOCUMENTS
Rev No 2 Status P Date 2021-05-03 Cont ID  
Sent By dbattles Date 2021-05-03 Time 11:18 Rev Time 0.00
Received By dbattles Date 2021-05-03 Time 11:18 Sent To  
Notes
***NONE***

Review Stop PRIVATEPRV PRIVATE PROVIDER DOCUMENTS
Rev No 1 Status F Date 2021-04-22 Cont ID  
Sent By shill Date 2021-04-22 Time 11:29 Rev Time 0.00
Received By shill Date 2021-04-22 Time 11:29 Sent To  
Notes
2021-04-28 12:55:134/28/21 THE ORIGINAL RVEISION REQUEST HAD THE WRONG
 MASTER OF 20060773.
 THE PLANS ARE UNDER 20060772 AND IT HAS BEEN UPDATED IN
 C+
 THIS CAN BE REVISION TO MASTER 20060773 WHERE THE GAS
 PLANS WERE REVIEWED.
2021-04-22 11:30:31FS553.791, THIS PROJECT IS PRIVATE PROVIDER PLAN
 REVIEW. AFFIDAVIT OF COMPLIANCE REQUIRED PRIOR TO
 SUBMITTAL.
  
 THE MASTER PERMIT DOES NOT INCLUDE GAS, SO THIS IS NOT
 A REVISION. COORDINATE WITH [email protected] TO
 HAVE THE SUBMITTAL CHANGED TO A GAS PERMIT APPLICATION.
  
  
  
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 3 Status P Date 2021-10-26 Cont ID  
Sent By cthroop Date 2021-10-26 Time 16:44 Rev Time 0.00
Received By cthroop Date 2021-10-26 Time 08:01 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2021-05-03 Cont ID  
Sent By dbattles Date 2021-05-03 Time 11:18 Rev Time 0.00
Received By dbattles Date 2021-05-03 Time 11:18 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2021-04-22 Cont ID  
Sent By shill Date 2021-04-22 Time 11:32 Rev Time 0.00
Received By shill Date 2021-04-22 Time 11:32 Sent To  
Notes
2021-04-22 11:33:15THIS WILL BE REVIEWED AFTER AFFIDAVIT IS RECEIVED.
  