Plan Review Stops For Permit 20121329 |
Review Stop |
AD |
ADDRESSING |
Rev No |
1 |
Status |
P |
Date |
2020-12-30 |
|
|
Cont ID |
|
Sent By |
cpuell |
Date |
2020-12-30 |
Time |
11:42 |
Rev Time |
0.00 |
Received By |
cpuell |
Date |
2020-12-30 |
Time |
11:42 |
Sent To |
|
|
Notes |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
P |
Date |
2021-02-17 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2021-02-17 |
Time |
07:56 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2021-02-16 |
Time |
17:20 |
Sent To |
|
|
Notes |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
F |
Date |
2021-01-13 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2021-01-13 |
Time |
09:01 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2021-01-12 |
Time |
15:10 |
Sent To |
|
|
Notes |
2021-01-13 09:01:25 | SFR ADDITION | | REVIEWED BY ROGER MCPHERSON | | 561-805-6716 | | [email protected] | | CODE USED FOR REVIEW - 2017 FBC WITH WPB CHAPTER 1 | | AMENDMENTS | | | | CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107 | | 1) PLEASE PROVIDE COMPLETE MIAMI DADE OR FLORIDA STATE | | PRODUCT APPROVAL FOR THE NEW EXTERIOR WINDOWS AND | | DOORS. REVIEWED AND MARKED APPROVED BY THE BUILDING | | DESIGNER OF RECORD. | | 2) THE SLIDING GLASS DOOR SHOWN ON DRAWING A-2 SHOWS A | | WIDTH OF 30" ON THE DOOR SCHEDULE - IS THIS CORRECT? | | 3) WINDOW AND DOOR PRODUCT APPROVALS MAY BE DEFERRED | | SUBMITTALS BY LISTING ITEMS TO BE DEFERRED ON THE | | CONSTRUCTION DOCUMENTS - 107.3.4.1 DEFERRED SUBMITTALS. | | FOR THE PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS | | ARE DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE | | NOT SUBMITTED AT THE TIME OF THE APPLICATION AND THAT | | ARE TO BE SUBMITTED TO THE BUILDING OFFICIAL WITHIN A | | SPECIFIED PERIOD. DEFERRAL OF ANY SUBMITTAL ITEMS SHALL | | HAVE THE PRIOR APPROVAL OF THE BUILDING OFFICIAL. THE | | REGISTERED DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE | | SHALL LIST THE DEFERRED SUBMITTALS ON THE CONSTRUCTION | | DOCUMENTS FOR REVIEW BY THE BUILDING OFFICIAL. | | DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE | | SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN | | RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD | | THEM TO THE BUILDING OFFICIAL WITH A NOTATION | | INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE | | BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO | | THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL | | ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED | | SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING | | OFFICIAL. |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
P |
Date |
2021-01-12 |
|
|
Cont ID |
|
Sent By |
cthroop |
Date |
2021-01-12 |
Time |
09:29 |
Rev Time |
0.00 |
Received By |
cthroop |
Date |
2021-01-12 |
Time |
09:07 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2021-02-17 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2021-02-17 |
Time |
08:04 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2021-01-28 |
Time |
07:46 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2021-01-27 |
|
|
Cont ID |
|
Sent By |
lmarchan |
Date |
2021-01-27 |
Time |
15:55 |
Rev Time |
0.00 |
Received By |
lmarchan |
Date |
2020-12-30 |
Time |
11:42 |
Sent To |
|
|
Notes |
|
|
Review Stop |
IMPACT |
COUNTY IMPACT FEES |
Rev No |
2 |
Status |
P |
Date |
2021-02-03 |
|
|
Cont ID |
|
Sent By |
lmarchan |
Date |
2021-02-03 |
Time |
08:28 |
Rev Time |
0.00 |
Received By |
lmarchan |
Date |
2021-01-29 |
Time |
07:46 |
Sent To |
|
|
Notes |
2021-02-03 08:28:45 | RECEIPT MU-2021-4578 - $0.00 NO FEES DUE | 2021-01-29 07:47:09 | 1/29/21 EMAILED IMPACT OFFICE FOR REVIEW. LEM |
|
|
Review Stop |
IMPACT |
COUNTY IMPACT FEES |
Rev No |
1 |
Status |
F |
Date |
2021-01-13 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2021-01-13 |
Time |
09:01 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2021-01-13 |
Time |
09:01 |
Sent To |
|
|
Notes |
2021-01-13 09:02:17 | PLANS WILL BE REVIEWED BY THE PBC IMPACT FEE OFFICE | | DIGITALLY VIA PROJECTDOX UPON NOTIFICATION BY THIS | | OFFICE. NOTIFICATION MAY OCCUR WHEN PLANS ARE NEAREST | | FINAL FORM. YOU MAY COORDINATE WITH THE IMPACT FEE | | OFFICE AT (561) 233-5025 OR SIMPLY UPLOAD THE MUNICIPAL | | IMPACT FEE QUESTIONNAIRE FORM TO YOUR PROJECT AND NAME | | THE FILE MUNICIPAL IMPACT FEE QUESTIONNAIRE. THE FORM | | CAN BE FOUND AT: HTTP://DISCOVER.PBCGOV.ORG/PZB/ADMINIS | | TRATION/PDF/IMPACTFEES/FORMS/QUESTIONNAIRE.PDF | | | | UPON APPROVAL AND FEE PAYMENT, PLEASE UPLOAD THE | | RECEIPT TO YOUR PROJECT OR EMAIL IT TO | | [email protected] . | | |
|
|
Review Stop |
M |
MECHANICAL (A/C) |
Rev No |
1 |
Status |
P |
Date |
2021-01-08 |
|
|
Cont ID |
|
Sent By |
medwards |
Date |
2021-01-08 |
Time |
14:40 |
Rev Time |
0.00 |
Received By |
medwards |
Date |
2021-01-08 |
Time |
14:40 |
Sent To |
|
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
P |
Date |
2021-01-06 |
|
|
Cont ID |
|
Sent By |
lcrespo |
Date |
2021-01-06 |
Time |
15:51 |
Rev Time |
0.00 |
Received By |
lcrespo |
Date |
2021-01-06 |
Time |
06:47 |
Sent To |
|
|
Notes |
2021-01-06 06:58:16 | 01/06/21 REVIEWED FOR CODE COMPLIANCE (PLUMBING) | | | | BY REVIEWING THE PLANS / SPECIFICATIONS FOR CODE | | COMPLIANCE DOES NOT RELIEVE THE OWNER, DESIGN | | PROFESSIONAL, CONTRACTORS, OR THEIR REPRESENTATIVES | | FROM THE RESPONSIBILITY TO COMPLY WITH ALL LOCAL, | | STATE, AND NATIONAL CODES AND STANDARDS IN EFFECT AT | | THE TIME OF PERMIT ISSUANCE. OUR REVIEW IS NOT A CHECK | | OF EVERY ITEM AND DOES NOT PREVENT THIS DEPARTMENT FROM | | REQUIRING CORRECTIONS DURING CONSTRUCTION. ANY CHANGES | | / ALTERATIONS TO APPROVED PLANS SHALL BE APPROVED TO | | AVOID VOIDING OF THE PERMIT. | | | | LUIS A. CRESPO | | PLUMBING PLAN EXAMINER / INSPECTOR | | EMAIL: [email protected] OFFICE: 561 805-6720 | | |
|
|
Review Stop |
R |
ROOF PLAN REVIEW |
Rev No |
1 |
Status |
P |
Date |
2021-01-13 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2021-01-13 |
Time |
09:02 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2021-01-13 |
Time |
09:02 |
Sent To |
|
|
Notes |
|
|
Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
Rev No |
2 |
Status |
P |
Date |
2021-02-17 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2021-02-17 |
Time |
08:00 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2021-02-17 |
Time |
08:00 |
Sent To |
|
|
Notes |
|
|
Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
Rev No |
1 |
Status |
P |
Date |
2021-01-08 |
|
|
Cont ID |
|
Sent By |
medwards |
Date |
2021-01-08 |
Time |
14:42 |
Rev Time |
0.00 |
Received By |
medwards |
Date |
2021-01-08 |
Time |
14:42 |
Sent To |
|
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
P |
Date |
2021-01-26 |
|
|
Cont ID |
|
Sent By |
kalexand |
Date |
2021-01-26 |
Time |
16:05 |
Rev Time |
0.00 |
Received By |
kalexand |
Date |
2021-01-26 |
Time |
16:05 |
Sent To |
I |
|
Notes |
2021-01-26 16:42:34 | AS THE TOTAL VALUE OF THE ADDITION EXCEEDS 50% OF THE | | IMPROVEMENT VALUE OF THE STRUCTURE A LANDSCAPE PERMIT | | MUST BE SUBMITTED TO PLANNING AND ZONING DIVISION. |
|
|