2020-12-31 09:20:57 | 12/31/20 1ST PLUMBING REVIEW**DENIED** WITH COMMENTS |
| |
| NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS |
| TIME, AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| |
| 1. SIGNED AND SEALED DRAWINGS OR |
| DIGITALLY/ELECTRONICALLY SIGNED BY THE ARCHITECT TO BE |
| USED IN ELECTRONIC PLAN REVIEW - OR - IF YOUR THEY DO |
| NOT HAVE AN ELECTRONIC OR DIGITAL SIGNATURE - PLEASE |
| DROP OFF (CITY HALL DROPBOX) THE ORIGINAL SIGNED AND |
| SEALED DOCUMENT ALONG WITH A "PLAN REVIEW REQUEST FORM" |
| EXPLAINING THE REASON FOR SUBMITTING THE DOCUMENT OR |
| DRAWINGS. THE PLAN REVIEW REQUEST FORM CAN BE OBTAINED |
| BY EMAILING [email protected] AND ASKING FOR THE FORM. |
| |
| 2. PLANS CALL OUT FOR A TOTAL OF FOUR PAGES, AND ONLY |
| TWO ARE UPLOAD. INFORMATION ABOUT THIS REVIEW MAY BE ON |
| THOSE PAGES MISSING, SO PLEASE UPLOAD SO A REVIEW CAN |
| BE COMPLETED PER THE WPB AMENDMENTS TO THE FBC SEC. |
| 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS. |
| |
| 3. SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE MAIN |
| DRAIN PER THE WPB AMENDMENTS TO FBC SEC. 107.2.1. |
| |
| 4. PLEASE SUBMIT TOTAL DYNAMIC HEAD CALCULATIONS FOR |
| THE MAXIMUM SYSTEM FLOW. THE PUMP'S MAXIMUM FLOW FROM |
| ITS PUMP CURVE IS NO LONGER ALLOWED TO BE USED IN |
| DETERMINING THE MAXIMUM SYSTEM FLOW RATE PER |
| ANSI/APSP/ICC 7 - 2013 SECS. 4.4.9, 4.4.9.1. THE 2013 |
| EDITION ADDRESSES THE FLOW RATE IN GALLONS PER MINUTE |
| (GPM). IT REQUIRES THAT THE MAXIMUM SYSTEM FLOW RATE |
| DOES NOT EXCEED THE LISTED MAXIMUM FLOW RATE OF THE |
| SUCTION OUTLET FITTING ASSEMBLY (DRAIN COVER). THE TDH |
| CALCULATIONS MUST INCLUDE ALL THE SYSTEM COMPONENTS, |
| INCLUDING SUCTION AND RETURN PIPING, FITTINGS, VALVES, |
| HEATER, FILTER, AND CHLORINATOR. ALL SYSTEM COMPONENTS |
| EXCEPT THE PUMP. HAYWARD CALCULATOR CAN PROVIDE HELP |
| WITH THE TDH. |
| |
| 5. PLEASE IDENTIFY ON THE PUMP CURVE WHICH CURVE KEY IS |
| SPECIFIC TO THE PUMP BEING INSTALLED ON THIS POOL. THIS |
| IS NEEDED TO CONFIRM THE MAXIMUM SYSTEM FLOW FROM THE |
| TDH CALCULATIONS PER THE ANSI/APSP/ICC 7 - 2013 SECS. |
| 4.4.9, 4.4.9.1. |
| |
| 6. THE PUMP SPECIFICATIONS ARE BLURRY; PLEASE SUBMIT |
| CLEAR AND LEGIBLE SPECIFICATIONS FOR THE PUMP CURVE PER |
| THE WPB AMEND. TO FBC SEC. 107.2.1. |
| |
| 7. SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE SALT |
| CHLORINATOR PER THE WPB AMENDMENTS TO FBC SEC. 107.2.1. |
| |
| 8. SHOWS A VELOCITY CHART PER ANSI/APSP -7 SEC. 4.4. |
| REFER TO THE 2013 EDITION OF APSP 7 PER THE WPB |
| AMENDMENTS TO THE FBC SEC. 107.2.1 INFORMATION ON |
| CONSTRUCTION DOCUMENTS. |
| |
| WHEN RESUBMITTING PLANS, PLEASE INDICATE THE REVISION & |
| REMOVE ANY VOIDED SHEETS & REPLACE ANY NECESSARY PAGES. |
| A TRANSMITTAL LETTER LISTING THE ORIGINAL REVIEW |
| COMMENT NUMBER, WITH A DESCRIPTION OF THE REVISION |
| MADE, IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE |
| THE CHANGES CAN BE FOUND WILL HELP TO EXPEDITE YOUR |
| PERMIT. THANK YOU FOR YOUR ANTICIPATED COOPERATION. |
| |
| HTTPS://CODES.ICCSAFE.ORG/CODES/FLORIDA |
| LUIS A. CRESPO |
| PLUMBING PLAN EXAMINER / INSPECTOR |
| EMAIL: [email protected] OFFICE: 561 805-6720 |
| |