Plan Review Details - Permit 20110342
Plan Review Stops For Permit 20110342
Review Stop AD ADDRESSING
Rev No 1 Status P Date 2020-12-17 Cont ID  
Sent By cpuell Date 2020-12-17 Time 10:04 Rev Time 0.00
Received By cpuell Date 2020-12-17 Time 10:04 Sent To  
Notes
2020-12-17 10:04:41PLEASE CONTACT [email protected] TO ESTABLISH AN ADDRESS

Review Stop B BUILDING (STRUCTURAL)
Rev No 5 Status P Date 2021-03-23 Cont ID  
Sent By rmcphers Date 2021-03-23 Time 09:35 Rev Time 0.00
Received By rmcphers Date 2021-03-23 Time 09:35 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status F Date 2021-03-05 Cont ID  
Sent By rmcphers Date 2021-03-05 Time 08:29 Rev Time 0.00
Received By rmcphers Date 2021-03-04 Time 15:23 Sent To  
Notes
2021-03-05 08:29:12NEW SFR
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected].
 CODE USED FOR REVIEW - 2017 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107
 1) STORAGE ROOM NEXT TO THE GARAGE SHOWS FLOOD VENTS -
 THE EXTERIOR GRADE APPEARS HIGH - PLEASE SHOW THE
 EXTERIOR GRADE TO COMPLY WITH FBC
 R322.2.2.1INSTALLATION OF OPENINGS.
 THE WALLS OF ENCLOSED AREAS SHALL HAVE OPENINGS
 INSTALLED SUCH THAT: THE BOTTOM OF EACH OPENING SHALL
 BE NOT MORE THAN 1 FOOT (305 MM) ABOVE THE HIGHER OF
 THE FINAL INTERIOR GRADE OR FLOOR AND THE FINISHED
 EXTERIOR GRADE IMMEDIATELY UNDER EACH OPENING.
 2) THE STORAGE ROOM WALLS AND FLOORING BELOW BASE FLOOD
 ELEVATION NEED TO COMPLY WITH FBC R322.1.8
 FLOOD-RESISTANT MATERIALS.
 BUILDING MATERIALS AND INSTALLATION METHODS USED FOR
 FLOORING AND INTERIOR AND EXTERIOR WALLS AND WALL
 COVERINGS BELOW THE ELEVATION REQUIRED IN SECTION
 R322.2 OR R322.3 SHALL BE FLOOD DAMAGE-RESISTANT
 MATERIALS THAT CONFORM TO THE PROVISIONS OF FEMA TB-2.
 3) DRAWING C-1 HAS NOT BEEN REVISED - DRAWING "C1"
 SHOWS THE FFE AT 7.63 NAVD - PLEASE REVISE AS THE FLOOR
 PLANS WERE REVISED TO SHOW 8.13 NAVD
 4) DRAWING C-1 - PLEASE SHOW ELEVATIONS USING NAVD -
 LEGEND ON DRAWING C-1 SHOWS ELEVATIONS USING NGVD BUT
 THE FLOOR ELEVATION IS SHOWN USING NAVD.
 ELEVATION CERTIFICATE =
 A8 PLEASE SHOW THE SQUARE FOOTAGE FOR THE STORAGE ROOM
 (ENCLOSED FLOOR).
 C2(A) PLEASE SHOW THE TOP OF ENCLOSURE FLOOR ELEVATION.
 C2(B) PLEASE SHOW THE TOP OF THE NEXT HIGHEST FLOOR
 (THE FIRST FLOOR OF THE HOUSE)
 C2(F) THE LOWEST ADJACENT GRADE IS ABOVE THE STORAGE
 ROOM AND GARAGE FLOOD VENTS?
  
 5) ROOFING SYSTEM TO BE DEFERRED.
  
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status F Date 2021-02-04 Cont ID  
Sent By rmcphers Date 2021-02-04 Time 15:38 Rev Time 0.00
Received By rmcphers Date 2021-02-04 Time 13:45 Sent To  
Notes
2021-02-04 15:37:02NEW SFR
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected].
 CODE USED FOR REVIEW - 2017 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107
 1) ONLY ROOMS USED FOR "STORAGE", "PARKING", AND
 "BUILDING ACCESS" CAN HAVE THE FLOOR ELEVATION BELOW
 THE "LOWEST FLOOR" ELEVATION. THE ROOM MARKED
 "MECHANICAL ROOM" WILL NEED TO HAVE THE LOWEST FLOOR
 ELEVATION AT 8.00 NAVD - FLOOD ZONE IS SHOWN ON DRAWING
 A-003 AS AE 6 - THE BUILDING "LOWEST FLOOR" (FBC
 R322.1.5) WILL NEED TO BE 8.00 NAVD PER CITY ORDINANCE
 4729-17 SEC. 18-33 (1). BUILDINGS AND STRUCTURES IN
 FLOOD HAZARD AREAS NOT DESIGNATED AS COASTAL A ZONES
 SHALL HAVE THE LOWEST FLOORS ELEVATED TO OR ABOVE THE
 BASE FLOOD ELEVATION PLUS TWO FEET OR THE DESIGN FLOOD
 ELEVATION, WHICHEVER IS HIGHER. (IF THE ROOM
 DESIGNATION IS CHANGED TO "STORAGE" IT CAN REMAIN AT
 THE PROPOSED FLOOR ELEVATION BUT WILL REQUIRE FLOOD
 VENTS - YOU WILL NEED TO SHOW THAT THE AC EQUIPMENT
 WILL BE ELEVATED TO THE REQUIRED ELEVATION FBC R322.1.6
 - YOU MAY ALSO NEED TO REVISE THE ELEVATION CERTIFICATE
 IF YOU ADD MORE FLOOD VENTS)
 2) PLEASE PROVIDE COMPLETE MIAMI DADE OR FLORIDA STATE
 PRODUCT APPROVAL FOR THE OVERHEAD GARAGE DOOR THAT IS
 LISTED BY PRODUCT APPROVAL NUMBER ON THE DRAWINGS.
 3) PLEASE PROVIDE A COMPLETE MIAMI DADE OR FLORIDA
 STATE METAL ROOFING PRODUCT APPROVAL FOR THE METAL
 ROOFING PRODUCT APPROVAL LISTED ON THE DRAWINGS.
 4) PRODUCT APPROVAL FOR THE FLAT DECK ROOFING = PLEASE
 CIRCLE THE ROOFING SYSTEM TO BE USED IN THE PRODUCT
 APPROVAL - IF NEEDED PLEASE PROVIDE SIGNED AND SEALED
 ADDITIONAL ATTACHMENT DETAILS FROM AN ARCHITECT OR
 ENGINEER FOR THE ROOF ZONES 2 AND 3 WHICH MAY REQUIRE A
 HIGHER WIND PRESSURE - SEE NOTES ON THE PRODUCT
 APPROVAL.
 5) PRODUCT APPROVAL FOR THE MULL BAR (18-0205.05) HAS
 EXPIRED - PLEASE PROVIDE AN UPDATED MULL BAR PRODUCT
 APPROVAL.
 6) DRAWING "C1" SHOWS THE FFE AT 7.63 NAVD - PLEASE
 REVISE AS THE FLOOR PLANS WERE REVISED TO SHOW 8.13
 NAVD
  
 7) ROOFING SYSTEM AND WINDOW AND DOOR PRODUCT APPROVALS
 MAY BE DEFERRED SUBMITTALS BY LISTING ITEMS TO BE
 DEFERRED ON THE CONSTRUCTION DOCUMENTS - 107.3.4.1
 DEFERRED SUBMITTALS. FOR THE PURPOSES OF THIS SECTION,
 DEFERRED SUBMITTALS ARE DEFINED AS THOSE PORTIONS OF
 THE DESIGN THAT ARE NOT SUBMITTED AT THE TIME OF THE
 APPLICATION AND THAT ARE TO BE SUBMITTED TO THE
 BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. DEFERRAL
 OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF
 THE BUILDING OFFICIAL. THE REGISTERED DESIGN
 PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE
 DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR
 REVIEW BY THE BUILDING OFFICIAL. DOCUMENTS FOR DEFERRED
 SUBMITTAL ITEMS SHALL BE SUBMITTED TO THE REGISTERED
 DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE WHO SHALL
 REVIEW THEM AND FORWARD THEM TO THE BUILDING OFFICIAL
 WITH A NOTATION INDICATING THAT THE DEFERRED SUBMITTAL
 DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE IN GENERAL
 CONFORMANCE TO THE DESIGN OF THE BUILDING. THE DEFERRED
 SUBMITTAL ITEMS SHALL NOT BE INSTALLED UNTIL THE
 DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE
 BUILDING OFFICIAL.
  
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2021-01-13 Cont ID  
Sent By mcphers Date 2021-01-13 Time 15:36 Rev Time 0.00
Received By rmcphers Date 2021-01-13 Time 14:53 Sent To  
Notes
2021-01-13 15:24:41NEW SFR
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected].
 CODE USED FOR REVIEW - 2017 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107
 1) FLOOD ZONE IS SHOWN ON DRAWING A-003 AS AE 6 - THE
 BUILDING "LOWEST FLOOR" (FBC R322.1.5) WILL NEED TO BE
 8.00 NAVD PER CITY ORDINANCE 4729-17 SEC. 18-33 (1).
 BUILDINGS AND STRUCTURES IN FLOOD HAZARD AREAS NOT
 DESIGNATED AS COASTAL A ZONES SHALL HAVE THE LOWEST
 FLOORS ELEVATED TO OR ABOVE THE BASE FLOOD ELEVATION
 PLUS TWO FEET OR THE DESIGN FLOOD ELEVATION, WHICHEVER
 IS HIGHER.
 2) PLEASE PROVIDE A PROPOSED ELEVATION CERTIFICATE FOR
 BUILDINGS IN FLOOD ZONES (AE6)
 3) PLEASE SHOW EQUIPMENT PAD ELEVATIONS TO MEET
 REQUIREMENTS FBC R322.1.6
 4) ADDING FLOOD VENTS TO A GARAGE OVERHEAD DOOR WILL
 VOID THE MIAMI DADE NOA FOR THE OVERHEAD DOOR. PLEASE
 PROVIDE A FIX.
 5) PLEASE PROVIDE COMPLETE MIAMI DADE OR FLORIDA STATE
 PRODUCT APPROVALS FOR THE EXTERIOR WINDOWS AND DOORS.
 6) PLEASE PROVIDE A COMPLETE MIAMI DADE OR FLORIDA
 STATE ROOFING PRODUCT APPROVALS.
 7) ALL PRODUCT APPROVALS NEED TO BE REVIEWED AND MARKED
 APPROVED BY THE DESIGNER OF RECORD OR LISTED ON THE
 DRAWINGS.(PLEASE CHECK THE LISTED PRODUCT APPROVAL
 NUMBERS ON THE DRAWINGS - I CANNOT FIND SOME OF THEM ON
 THE FLORIDA STATE PRODUCT APPROVAL WEB SITE).
 8) ROOFING SYSTEM AND WINDOW AND DOOR PRODUCT APPROVALS
 MAY BE DEFERRED SUBMITTALS BY LISTING ITEMS TO BE
 DEFERRED ON THE CONSTRUCTION DOCUMENTS - 107.3.4.1
 DEFERRED SUBMITTALS. FOR THE PURPOSES OF THIS SECTION,
 DEFERRED SUBMITTALS ARE DEFINED AS THOSE PORTIONS OF
 THE DESIGN THAT ARE NOT SUBMITTED AT THE TIME OF THE
 APPLICATION AND THAT ARE TO BE SUBMITTED TO THE
 BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. DEFERRAL
 OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF
 THE BUILDING OFFICIAL. THE REGISTERED DESIGN
 PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE
 DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR
 REVIEW BY THE BUILDING OFFICIAL. DOCUMENTS FOR DEFERRED
 SUBMITTAL ITEMS SHALL BE SUBMITTED TO THE REGISTERED
 DESIGN PROFESSIONAL IN RESPONSIBLE CHARGE WHO SHALL
 REVIEW THEM AND FORWARD THEM TO THE BUILDING OFFICIAL
 WITH A NOTATION INDICATING THAT THE DEFERRED SUBMITTAL
 DOCUMENTS HAVE BEEN REVIEWED AND FOUND TO BE IN GENERAL
 CONFORMANCE TO THE DESIGN OF THE BUILDING. THE DEFERRED
 SUBMITTAL ITEMS SHALL NOT BE INSTALLED UNTIL THE
 DEFERRED SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE
 BUILDING OFFICIAL.
 9) A GUARD RAIL IS REQUIRED FOR THE 2ND FLOOR GUEST
 ROOM EXTERIOR DOOR FBC R312
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2020-11-24 Cont ID  
Sent By rmcphers Date 2020-11-24 Time 09:18 Rev Time 0.00
Received By rmcphers Date 2020-11-23 Time 14:55 Sent To  
Notes
2020-11-24 09:15:41NEW SFR
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected].
 CODE USED FOR REVIEW - 2017 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107
 1) ON THE SITE PLAN OR ON A SURVEY WITH THE BUILDING
 PLACED SHOW THE SEPARATION LINE BETWEEN FLOOD ZONE AE6
 AND X - NEEDED TO DETERMINE IF THE BUILDING IS IN THE
 AE6 ZONE - THE LOWEST FLOOR ELEVATION WILL NEED TO BE
 8.00 NAVD (CITY ORD: 4729 17)
 2) PLEASE SHOW THE DOOR FROM THE GARAGE TO THE LIVING
 SPACE TO COMPLY WITH FBC R302.5.1
 3) PLEASE SHOW EQUIPMENT PAD ELEVATIONS TO MEET
 REQUIREMENTS FBC R322.1.6
 4) PLEASE SHOW THE FLOOD VENTS IN THE GARAGE TO COMPLY
 WITH FBC R322.2.2
 5) PLEASE PROVIDE COMPLETE MIAMI DADE OR FLORIDA STATE
 PRODUCT APPROVALS FOR THE EXTERIOR WINDOWS AND DOORS.
 6) PLEASE PROVIDE A COMPLETE MIAMI DADE OR FLORIDA
 STATE ROOFING PRODUCT APPROVALS.
 7) ALL PRODUCT APPROVALS NEED TO BE REVIEWED AND MARKED
 APPROVED BY THE DESIGNER OF RECORD OR LISTED ON THE
 DRAWINGS.
  

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2020-12-04 Cont ID  
Sent By jleahy Date 2020-12-04 Time 12:11 Rev Time 0.00
Received By jleahy Date 2020-12-04 Time 12:11 Sent To  
Notes
***NONE***

Review Stop E-LOWVOLT ELECTRICAL LOW VOLTAGE
Rev No 1 Status P Date 2021-12-08 Cont ID  
Sent By mpeterso Date 2021-12-08 Time 15:16 Rev Time 0.00
Received By mpeterso Date 2021-12-08 Time 15:16 Sent To  
Notes
2021-12-08 15:15:59INSERTED LOW VOLTAGE STOP AS PER INSTRUCTIONS FROM S.H.
 12/8/21 M.PETERSON

Review Stop G GAS REVIEW
Rev No 2 Status P Date 2021-01-09 Cont ID  
Sent By abelisle Date 2021-01-09 Time 16:05 Rev Time 0.00
Received By abelisle Date 2021-01-09 Time 16:05 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status N Date 2020-11-30 Cont ID  
Sent By ccole Date 2020-11-30 Time 16:37 Rev Time 0.00
Received By ccole Date 2020-11-30 Time 16:37 Sent To  
Notes
2020-11-30 16:40:24GAS REVIEW
 11/30/2020
  
 1) THE GAS PIPING LAYOUT AND RISER DRAWING SHOWN ON THE
 PLANS WERE NOT REVIEWED AT THIS TIME. PLEASE SUBMIT THE
 DRAWINGS UNDER A SEPARATE PERMIT AND INCLUDE
 MANUFACTURER'S SPECIFICATIONS FOR ALL GAS APPLIANCES
 AND EQUIPMENT.
  
 CHRISTOPHER L. COLE
 MECHANICAL/PLUMBING PLANS EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL 33401
 561-805-6719
 [email protected]
  
  
  

Review Stop I INCOMING/PROCESSING
Rev No 6 Status N Date 2021-12-08 Cont ID  
Sent By mpeterso Date 2021-12-08 Time 15:18 Rev Time 0.00
Received By mpeterso Date 2021-12-08 Time 15:18 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 5 Status N Date 2021-03-23 Cont ID  
Sent By rmcphers Date 2021-03-23 Time 09:40 Rev Time 0.00
Received By rmcphers Date 2021-03-15 Time 15:24 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2021-03-05 Cont ID  
Sent By rmcphers Date 2021-03-05 Time 08:33 Rev Time 0.00
Received By rmcphers Date 2021-02-12 Time 15:20 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2021-02-12 Cont ID  
Sent By cpuell Date 2021-02-12 Time 09:38 Rev Time 0.00
Received By cpuell Date 2021-01-22 Time 13:33 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2021-01-13 Cont ID  
Sent By rmcphers Date 2021-01-13 Time 15:49 Rev Time 0.00
Received By rmcphers Date 2021-01-04 Time 14:32 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-12-18 Cont ID  
Sent By lmarchan Date 2020-12-18 Time 08:57 Rev Time 0.00
Received By lmarchan Date 2020-11-13 Time 16:18 Sent To  
Notes
***NONE***

Review Stop IMPACT COUNTY IMPACT FEES
Rev No 2 Status P Date   Cont ID  
Sent By   Date 2021-02-12 Time   Rev Time 0.00
Received By lmarchan Date 2021-02-02 Time 15:55 Sent To  
Notes
2021-02-12 10:57:0002/12/21 UPLOADED MU 2021 005140 - $22.46-PAID. CC
2021-02-02 15:56:062/2/21 EMAILED IMPACT OFFICE FOR REVIEW. LEM

Review Stop IMPACT COUNTY IMPACT FEES
Rev No 1 Status F Date 2020-11-24 Cont ID  
Sent By rmcphers Date 2020-11-24 Time 09:15 Rev Time 0.00
Received By rmcphers Date 2020-11-23 Time 15:57 Sent To  
Notes
2020-11-24 09:16:28PLANS WILL BE REVIEWED BY THE PBC IMPACT FEE OFFICE
 DIGITALLY VIA PROJECTDOX UPON NOTIFICATION BY THIS
 OFFICE. NOTIFICATION MAY OCCUR WHEN PLANS ARE NEAREST
 FINAL FORM. YOU MAY COORDINATE WITH THE IMPACT FEE
 OFFICE AT (561) 233-5025 OR SIMPLY UPLOAD THE MUNICIPAL
 IMPACT FEE QUESTIONNAIRE FORM TO YOUR PROJECT AND NAME
 THE FILE MUNICIPAL IMPACT FEE QUESTIONNAIRE. THE FORM
 CAN BE FOUND AT: HTTP://DISCOVER.PBCGOV.ORG/PZB/ADMINIS
 TRATION/PDF/IMPACTFEES/FORMS/QUESTIONNAIRE.PDF
  
 UPON APPROVAL AND FEE PAYMENT, PLEASE UPLOAD THE
 RECEIPT TO YOUR PROJECT OR EMAIL IT TO
 [email protected] .
  

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2021-01-11 Cont ID  
Sent By medwards Date 2021-01-11 Time 09:27 Rev Time 0.00
Received By medwards Date 2021-01-11 Time 08:33 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2020-11-18 Cont ID  
Sent By medwards Date 2020-11-18 Time 14:48 Rev Time 0.00
Received By medwards Date 2020-11-18 Time 14:48 Sent To  
Notes
2020-11-18 14:48:321ST REVIEW FBC-2017 MECHANICAL
 PERMIT-20110342
  
 CODES IN EFFECT:
  
 FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017
 FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017
 FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION
 2017
 FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017
 FBC EX- FLORIDA EXISTING BUILDING CODE SIXTH EDITION
 2017
 FBC RES- FLORIDA RESIDENTIAL BUILDING CODE SIXTH
 EDITION 2017
 FS- FLORIDA STATUTES
 FAC- FLORIDA ADMINISTRATIVE CODE
 WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH
 EDITION 2017
  
 PLAN REVIEW RESULTS: DENIED.
  
 1) PLEASE PROVIDE THE ENERGY CALCULATIONS. FBC EC
 101.5.1.1.2
  
 2) PLEASE PROVIDE THE MECHANICAL EQUIPMENT SIZING
 CALCULATIONS FOR ALL SYSTEMS. FBC RES M1401.3
  
 3) SHEET M1.1A- BECAUSE THE MECHANICAL ROOM IS
 CONDITIONED, VERIFY THAT THE MECHANICAL ROOM WHERE
 AHU-2 IS LOCATED IS SEPARATED FROM THE GARAGE. FBC
 R302.5.1
  
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT
 CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE OLD
 SHEETS FROM THE PLAN SETS, BIND THEM TOGETHER
 SEPARATELY AND MARK VOID OR OLD ON THEM. PLEASE RETAIN
 THEM FOR REFERENCE WITH THE NEW SUBMITTED PLANS. THIS
 PROCESS WILL ALSO APPLY TO ANY DOCUMENTS SUCH AS
 PRODUCT APPROVALS OR CALCULATIONS BEING REPLACED OR
 UPDATED.
  
 MICHAEL EDWARDS
 MECHANICAL EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL. 33401
 561-805-6728
 [email protected]
  

Review Stop NFIP NFIP REVIEW ACTIVITY
Rev No 5 Status P Date 2021-03-23 Cont ID  
Sent By rmcphers Date 2021-03-23 Time 09:35 Rev Time 0.00
Received By rmcphers Date 2021-03-23 Time 09:35 Sent To  
Notes
2021-03-23 09:36:37AE 6
 PROPOSED LOWEST FLOOR = 8.00

Review Stop NFIP NFIP REVIEW ACTIVITY
Rev No 4 Status F Date 2021-03-05 Cont ID  
Sent By rmcphers Date 2021-03-05 Time 08:30 Rev Time 0.00
Received By rmcphers Date 2021-03-05 Time 08:30 Sent To  
Notes
2021-03-05 08:30:23SEE BUILDING PLAN REVIEW

Review Stop NFIP NFIP REVIEW ACTIVITY
Rev No 3 Status F Date 2021-02-04 Cont ID  
Sent By rmcphers Date 2021-02-04 Time 15:38 Rev Time 0.00
Received By rmcphers Date 2021-02-04 Time 15:38 Sent To  
Notes
2021-02-04 15:39:20SEE BUILDING PLAN REVIEW

Review Stop NFIP NFIP REVIEW ACTIVITY
Rev No 2 Status F Date 2021-01-13 Cont ID  
Sent By mcphers Date 2021-01-13 Time 15:38 Rev Time 0.00
Received By rmcphers Date 2021-01-13 Time 15:37 Sent To  
Notes
2021-01-13 15:38:11SEE BUILDING PLAN REVIEW

Review Stop NFIP NFIP REVIEW ACTIVITY
Rev No 1 Status F Date 2020-11-24 Cont ID  
Sent By rmcphers Date 2020-11-24 Time 09:16 Rev Time 0.00
Received By rmcphers Date 2020-11-24 Time 09:16 Sent To  
Notes
2020-11-24 09:17:23SEE BUILDING PLAN REVIEW

Review Stop P PLUMBING
Rev No 2 Status P Date 2021-01-09 Cont ID  
Sent By abelisle Date 2021-01-09 Time 15:55 Rev Time 0.00
Received By abelisle Date 2021-01-09 Time 15:23 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status F Date 2020-11-30 Cont ID  
Sent By ccole Date 2020-11-30 Time 16:06 Rev Time 0.00
Received By ccole Date 2020-11-30 Time 10:44 Sent To  
Notes
2020-11-30 16:06:451ST REVIEW FBC-2017 RES.
 PERMIT- 20110342
 11/30/2020
  
 CODES IN EFFECT:
 FBC RES- FLORIDA RESIDENTIAL BUILDING CODE SIXTH
 EDITION 2017
 FBC P- FLORIDA PLUMBING CODE SIXTH EDITION 2017
 FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017
 FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017
 FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION
 2017
 FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017
 FBC EX- FLORIDA EXISTING BUILDING CODE SIXTH
 FS- FLORIDA STATUTES
 FAC- FLORIDA ADMINISTRATIVE CODE
 WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH
 EDITION 2017
  
 PLAN REVIEW RESULTS: DENIED.
  
 1) PLEASE NOTE SEPARATE PERMITS ARE REQUIRED FOR THE
 GAS PIPING, WATER SERVICE BACKFLOW PREVENTER, POOL, AND
 IRRIGATION SYSTEM- SECTIONS 105.1 & 107.2.1 WPB.
 COMPLETE PLANS AND SPECIFICATIONS ARE REQUIRED.
  
 A) THE GAS PIPING LAYOUT AND RISER DRAWING SHOWN ON THE
 PLANS WERE NOT REVIEWED AT THIS TIME. PLEASE SUBMIT THE
 DRAWINGS UNDER A SEPARATE PERMIT AND INCLUDE
 MANUFACTURER'S SPECIFICATIONS FOR ALL GAS APPLIANCES
 AND EQUIPMENT.
  
 B) BACKFLOW PREVENTER: A FLORIDA LICENSED PLUMBING
 CONTRACTOR SHALL OBTAIN A SEPARATE PERMIT FOR
 INSTALLATION OF THE POTABLE WATER SERVICE BACKFLOW
 PREVENTER IN ACCORDANCE WITH SECTION 105.1 WPB AND
 SECTION 90-33 WPB CODE OF ORDINANCES. THE DEVICE SHALL
 BE TESTED AND CERTIFIED BY THE WPB UTILITIES DEPARTMENT
 PRIOR TO FINAL INSPECTION BY THE WPB BUILDING
 DEPARTMENT. PLEASE CONTACT THE WPB UTILITIES CENTRAL
 OPERATIONS DEPT. AT 561-822-2210 FOR FURTHER
 INFORMATION.
  
 2) THE ENERGY FORM R405-2017 INDICATES THE TANKLESS
 WATER HEATER TO BE 50 GALLONS AND 0.97 EFFICIENCY.
 CORRECT THE GALLON SIZE DATA AND SUBMIT MANUFACTURER'S
 SPECIFICATIONS TO CONFIRM THE EFFICIENCY RATING- TABLE
 C404.1 FBC- EC.
  
 3) SHEET PS.1.1: THE LOCATION OF THE 2-WAY CLEANOUT
 SHALL BE AT THE JUNCTION OF THE BUILDING DRAIN AND
 BUILDING SEWER OR WITHIN 10 FT. UPSTREAM OF THE
 JUNCTION. PLEASE NOTE THAT BUILDING DRAIN BY DEFINITION
 EXTENDS 30 INCHES BEYOND THE EXTERIOR WALL AT WHICH
 POINT IT TRANSITIONS INTO THE BUILDING SEWER- SECTIONS
 R202 & P3005.2.3 FBC RES.
  
 4) SHEET P0.3 & P1.0B: CLEANOUTS AND ACCESS TO THE
 CLEANOUTS ARE REQUIRED WHERE THE VERTICAL RAIN WATER
 LEADERS CONNECT WITH THE HORIZONTAL UNDERSLAB STORM
 DRAINS- SEE SECTIONS 1101.8, 708.1.4, 708.1.10 FBC P
 AND P3005.2.4, AND P3005.2.10 FBC RES.
  
 5) P1.1A: PROVIDE WATER HAMMER ARRESTORS FOR SUPPLY
 LINES TO THE DISHWASHER, ICE MAKER, AND WASHING
 MACHINE- SECTION P2903.5 FBC RES.
  
 6) P1.1A: PROVIDE A BACKFLOW PREVENTER FOR THE SUPPLY
 LINE TO THE ICE MAKER- SECTION P2902.1 FBC RES.
  
 7) P1.1A: INDICATE HOW THE SUPPLY LINES UNDER THE SLAB
 WILL BE PROTECTED FROM CORROSION- SECTION P2603.3 FBC
 RES.
  
 8) A1-101.2 & A-102: PROVIDE THE DIMENSIONS OF THE
 SHOWERS- SECTION P2708.1 FBC RES.
  
 9) P0.2: PROVIDE A SHOWER PAN DETAIL- SECTIONS P2709.1
 & P2709.2 FBC RES.
  
 10) P1.3: PLEASE NOTE UPON COMPLETION OF THE NEW STORM
 DRAINAGE SYSTEMS AS SHOWN ON THE PLAN A CERTIFICATION
 FROM A LICENSED PROFESSIONAL SHALL BE SUBMITTED TO THE
 INSPECTOR IN ORDER TO RECEIVE FINAL APPROVAL- SECTION
 110.9 IMPACT OF CONSTRUCTION WPB.
  
 11) P1.3: THE ROOF DRAINAGE SYSTEMS SHALL BE IN
 COMPLIANCE WITH SECTIONS R903.4.1 FBC RES AND 1101.2
 FBC P:
  
 A) VERIFY THE ROOF IS DESIGNED FOR THE MAXIMUM POSSIBLE
 DEPTH OF WATER THAT WILL POND THEREON AS DETERMINED BY
 THE RELATIVE LEVELS OF ROOF DECK AND OVERFLOW WEIRS,
 SCUPPERS, EDGES OR SERVICEABLE DRAINS IN COMBINATION
 WITH THE DEFLECTED STRUCTURAL ELEMENTS. IN DETERMINING
 THE MAXIMUM POSSIBLE DEPTH OF WATER, ALL PRIMARY ROOF
 DRAINAGE MEANS SHALL BE ASSUMED TO BE BLOCKED- SECTION
 1101.7 FBC P.
  
 B) PROVIDE THE ROOF DRAIN FLOW RATE BASED ON SECTION
 1105.2, AND CALCULATIONS FOR SIZING THE PRIMARY
 VERTICAL CONDUCTORS AND LEADERS AND HORIZONTAL BRANCHES
 BASED ON SECTIONS 1106.1, FIGURE 1106.1 AND SECTION
 1108.3.
  
 C) PROVIDE A PRIMARY ROOF DRAIN INSTALLATION DETAIL.
 SHOW THE MAKES AND MODELS OF THE PRIMARY ROOF DRAINS,
 AND SUBMIT PRODUCT SPECIFICATION SHEETS- SECTIONS
 1102.6 AND 1108.1.
  
 D) PROVIDE AN OVERFLOW SCUPPER DETAIL PER SECTIONS
 R903.4.1 FBC RES. AND 1108.3 FBC P.
  
 E) SHOW THE LOCATIONS OF GUTTERS FOR THE SLOPED ROOFS
 AND PROVIDE VERTICAL LEADER AND HORIZONTAL GUTTER SIZES
 IN ACCORDANCE WITH TABLES 1106.3 AND 1106.6.
  
 12) PROVIDE A PLUMBING SUB-PERMIT APPLICATION- SECTION
 105.1 WPB.
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM.
  
 CHRISTOPHER L. COLE
 MECHANICAL/PLUMBING PLANS EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL 33401
 561-805-6719
 [email protected]
  

Review Stop R ROOF PLAN REVIEW
Rev No 5 Status N Date 2021-03-23 Cont ID  
Sent By rmcphers Date 2021-03-23 Time 09:37 Rev Time 0.00
Received By rmcphers Date 2021-03-23 Time 09:37 Sent To  
Notes
2021-03-23 09:37:23DEFERRED

Review Stop R ROOF PLAN REVIEW
Rev No 4 Status N Date 2021-03-05 Cont ID  
Sent By rmcphers Date 2021-03-05 Time 08:32 Rev Time 0.00
Received By rmcphers Date 2021-03-05 Time 08:32 Sent To  
Notes
2021-03-05 08:32:42ROOFING TO BE DEFERRED

Review Stop R ROOF PLAN REVIEW
Rev No 3 Status F Date 2021-02-04 Cont ID  
Sent By rmcphers Date 2021-02-04 Time 15:39 Rev Time 0.00
Received By rmcphers Date 2021-02-04 Time 15:39 Sent To  
Notes
2021-02-04 15:40:01SEE BUILDING PLAN REVIEW

Review Stop R ROOF PLAN REVIEW
Rev No 2 Status F Date 2021-01-13 Cont ID  
Sent By rmcphers Date 2021-01-13 Time 15:37 Rev Time 0.00
Received By rmcphers Date 2021-01-13 Time 15:37 Sent To  
Notes
2021-01-13 15:37:45SEE BUILDING PLAN REVIEW

Review Stop R ROOF PLAN REVIEW
Rev No 1 Status F Date 2020-11-24 Cont ID  
Sent By rmcphers Date 2020-11-24 Time 09:17 Rev Time 0.00
Received By rmcphers Date 2020-11-23 Time 15:57 Sent To  
Notes
2020-11-24 09:18:20SEE BUILDING PLAN REVIEW

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 5 Status P Date 2021-03-23 Cont ID  
Sent By rmcphers Date 2021-03-23 Time 09:36 Rev Time 0.00
Received By rmcphers Date 2021-03-23 Time 09:36 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 4 Status P Date 2021-03-05 Cont ID  
Sent By rmcphers Date 2021-03-05 Time 08:32 Rev Time 0.00
Received By rmcphers Date 2021-03-05 Time 08:32 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 3 Status P Date 2021-02-04 Cont ID  
Sent By rmcphers Date 2021-02-04 Time 15:43 Rev Time 0.00
Received By rmcphers Date 2021-02-04 Time 15:43 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2021-01-13 Cont ID  
Sent By rmcphers Date 2021-01-13 Time 15:49 Rev Time 0.00
Received By rmcphers Date 2021-01-13 Time 15:49 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2020-11-19 Cont ID  
Sent By medwards Date 2020-11-18 Time 15:22 Rev Time 0.00
Received By medwards Date 2020-11-18 Time 15:22 Sent To  
Notes
2020-11-19 07:16:46PER THE WPB AMENDMENTS TO THE FBC, EACH SHEET OF PLAN
 (INCLUDING THE SUPPORTING DOCUMENTS) IS REQUIRED TO BE
 SIGNED AND SEALED BY THE PERSON RESPONSIBLE FOR THE
 DESIGN. A DIGITAL PLAN REQUIRES A DIGITAL SIGNATURE
 WITH THE PROPER THIRD PARTY VERIFICATION. PROVIDE
 CORRECTION. ALTERNATIVELY, A SIGNED/SEALED PAPER SET
 MAY BE SUPPLIED TO THE BUILDING DEPARTMENT WHEN ALL
 TRADES ARE APPROVED. WPB FBC 107.1; FS 471/481
  
 MICHAEL EDWARDS
 MECHANICAL EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL. 33401
 561-805-6728
 [email protected]
  

Review Stop Z ZONING
Rev No 2 Status P Date 2021-02-10 Cont ID  
Sent By kalexand Date 2021-02-10 Time 09:37 Rev Time 0.00
Received By kalexand Date 2021-02-10 Time 09:37 Sent To I
Notes
2021-02-10 09:39:36SEE PREVIOUS COMMENT.

Review Stop Z ZONING
Rev No 1 Status P Date 2020-12-17 Cont ID  
Sent By kalexand Date 2020-12-17 Time 17:13 Rev Time 0.00
Received By kalexand Date 2020-12-17 Time 17:13 Sent To I
Notes
2020-12-17 17:23:17A SEPARATE LANDSCAPE PERMIT SHALL BE ISSUED. ALL
 LANDSCAPING SHALL BE INSTALLED AND PASS INSPECTION
 PRIOR TO THE ISSUANCE OF A CERTIFICATE OF OCCUPANCY /
 COMPLETION.


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved