Plan Review Details - Permit 20110184
Plan Review Stops For Permit 20110184
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2020-12-29 Cont ID  
Sent By pvalenti Date 2020-12-29 Time 13:51 Rev Time 0.00
Received By pvalenti Date 2020-12-29 Time 13:11 Sent To  
Notes
2020-12-29 13:55:10PETER E VALENTI
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6673
  
 FBC = FLORIDA BUILDING CODE, 6TH EDITION (2017)
 FBC B = FBC BUILDING
 FBC EB = FBC EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC R = FBC RESIDENTIAL
 FBC M = FBC MECHANICAL
 FBC FG = FBC FUEL GAS
  
 BUILDING REVIEW APPROVED WITH PROVISOS:
  
 1) PROVIDE ENGINEER, REVIEW STAMPED, APPROVED PRODUCT
 APPROVALS FOR ROOFING MATERIAL SUBMITTED BY ROOFING
 CONTRACTOR WITH ROOFING SUB-PERMIT.
  
 2) AWS D1.1 CLAUSE 5.2 & 6.7: AT TIME OF INSPECTION
 PLEASE PROVIDE A WELD PROCEDURE SPECIFICATION; THE
 W.P.S. SPECIFIES THE REQUIRED ESSENTIAL VARIABLES
 INCLUDING: BASE MATERIALS, JOINTS, PROCESS, AND FILLER
 METALS TO BE USED.
 AWS D1.1 CLAUSE 6.16: AT TIME OF INSPECTION PLEASE
 PROVIDE A WELDER PERFORMANCE QUALIFICATION RECORD; THE
 W.P.Q.R. PROVIDES INFORMATION WHICH CAN BE USED TO
 VERIFY THE WELDER?S QUALIFICATION AND CERTIFICATION AS
 IT RELATES TO THE WELDING REQUIREMENTS OF THE PROJECT.
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2020-11-06 Cont ID  
Sent By jwitmer Date 2020-11-06 Time 11:25 Rev Time 0.00
Received By jgomez Date 2020-11-06 Time 10:04 Sent To  
Notes
2020-11-06 11:26:37BUILDING REVIEW COMMENTS
 CODE: FBC 6TH EDITION (2017) AND CITY AMENDMENTS.
  
 NOTE:
 BUILDING REVIEW MAY BE APPROVED WITH PROVISO. PROVISO
 MEANS CONTRACTOR WILL SUBMIT REQUIRED INFORMATION AFTER
 THE PERMIT IS ISSUED BUT BEFORE INSPECTIONS TO AVOID
 CONFLICTS/DELAYS. REVISION FEES MAY APPLY. CONTRACTOR
 TO ADVICE IF PROVISO OPTION IS PREFERRED AT THIS TIME
 OR IF RE-SUBMITTING REQUIRED INFORMATION BEFORE PERMIT
 ISSUANCE.
  
 1- SECTION 1/S-1:
 A) DETAIL SHOWS A NEW FASCIA. WITH A NOTE STATING "(N)
 SHEATHING (SEE ARCH)". THERE ARE NOT ARCHITECTURAL
 DRAWINGS SUBMITTED. PROVIDE THE ARCHITECTURAL DRAWING
 WITH COMPLETE SHEATHING SPECIFICATIONS OR PROVIDE
 COMPLETE SPECIFICATIONS (TYPE, FASTENING, ETC).
 SEC. 702.6 FBC-EXISTING BUILDING. SEC. 1609.1
 FBC-BUILDING.
  
 B) DETAIL SHOWS "(E) ROOF COVERING MEMBRANE. (SEE ARCH
 FOR NEW ROOFING /FLASHING)". THERE ARE NOT
 ARCHITECTURAL DRAWINGS SUBMITTED. PROVIDE THE
 ARCHITECTURAL DRAWING WITH COMPLETE ROOFING
 SPECIFICATIONS OR PROVIDE COMPLETE SPECIFICATIONS
 (TYPE, FASTENING, ETC).
 SEC. 702.6 FBC-EXISTING BUILDING. SEC. 1609.1
 FBC-BUILDING.
  
 2- CLARIFY NOTE #4 OF EXISTING PARTIAL ROOF FRAMING
 PLAN. DESIGN PRESSURES SEEM TO BE LOW FOR A BUILDING
 LOCATED IN EXPOSURE "D" AS SPECIFIED ON WIND LOAD NOTE
 1(A) UNDER THE STRUCTURAL NOTES. REVISE/CLARIFY AS
 REQUIRED. ARE THESE NOMINAL LOADS. ARE THESE THE MAIN
 WINDFORCE RESISTING FORCES. ARE THESE THESE DESIGN
 PRESSURES FOR COMPONENTS AND CLADDING?. IF SO SPECIFY
 THE ROOF ZONES AND THE WALL ZONES.
 SEC. 702.6 FBC-EXISTING BUILDING. SEC. 1609.1
 FBC-BUILDING. SEC. 107.2.1 CITY AMENDMENTS.
  
 3- PRODUCT APPROVALS:
 A)PROVIDE PRODUCT APPROVAL AS REQUIRED BY FAC
 61G20-3.001 FOR FLAT ROOF ASSEMBLY. AND, CLEARLY
 IDENTIFY THE SPECIFIC ASSEMBLY TO BE INSTALLED.
  
 (NOTE: THIS MAY BE SUBMITTED LATER AS A DEFERRED
 SUBMITTAL. PROVIDE COMPLETE INFORMATION PRIOR TO
 INSTALLATION TO AVOID CONFLICTS/DELAYS. ALL PRODUCT
 APPROVALS NEED TO BE APPROVED IN WRITING BY DESIGNER OF
 RECORD PRIOR TO SUBMITTAL).
  
 B) ROOFING SUBMIT REQUIRED. SEC. 105.1 CITY AMENDMENTS.
  
 4-DESIGNER OF RECORD TO REVIEW AND APPROVE IN WRITING
 (NOT SIGNING AND SEALING) ALL PRODUCT APPROVALS AS
 REQUIRED BY SEC. 107.3.4.1 CITY AMENDMENTS
  
 WHEN RESUBMITTING, A TRANSMITTAL LETTER LISTING THE
 ORIGINAL REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF
 THE REVISION MADE, IDENTIFYING THE SHEET OR
 SPECIFICATION PAGE WHERE THE CHANGES CAN BE FOUND WILL
 HELP TO EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR
 ANTICIPATED COOPERATION.
  
 PLEASE FEEL FREE TO CONTACT ME IF YOU HAVE ANY
 QUESTIONS REGARDING THESE COMMENTS,
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 (561)805-6712

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2020-12-29 Cont ID  
Sent By pleduc Date 2020-12-29 Time   Rev Time 0.00
Received By pleduc Date 2020-12-29 Time 15:34 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status F Date 2020-11-10 Cont ID  
Sent By pleduc Date 2020-11-10 Time   Rev Time 0.00
Received By pleduc Date 2020-11-10 Time 13:22 Sent To  
Notes
2020-11-10 13:24:48THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE
 MARSHAL, WITH THE FOLLOWING COMMENTS:
  
 1) THERE ARE NO INDICATIONS OF CHANGES/REVISIONS.
  
 PER NFPA 1
  
 1.14 PLAN REVIEW.
 1.14.5 WHEN REQUIRED BY THE AHJ, REVISED CONSTRUCTION
 DOCUMENTS OR SHOP DRAWINGS SHALL BE PREPARED AND
 SUBMITTED FOR REVIEW AND APPROVAL TO ILLUSTRATE
 CORRECTIONS OR MODIFICATIONS NECESSITATED BY FIELD
 CONDITIONS OR OTHER REVISIONS TO APPROVED PLANS.
  
 PLEASE SUBMIT PLANS THAT HAVE INDICATIONS WHERE THE
 REVISIONS OR MODIFICATIONS, FROM THE ORIGINAL PLANS,
 ARE LOCATED.
  
  
  
 2) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET
 REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE
 ABOVE.
  
  
 3) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE
 RE-SUBMITTAL OF THE ABOVE.
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2020-12-29 Cont ID  
Sent By lmarchan Date 2020-12-29 Time 16:20 Rev Time 0.00
Received By lmarchan Date 2020-11-30 Time 11:12 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-12-03 Cont ID  
Sent By jleahy Date 2020-12-03 Time 09:43 Rev Time 0.00
Received By jleahy Date 2020-11-05 Time 07:56 Sent To  
Notes
***NONE***

Review Stop R ROOF PLAN REVIEW
Rev No 1 Status N Date 2020-12-29 Cont ID  
Sent By pvalenti Date 2020-12-29 Time 13:56 Rev Time 0.00
Received By pvalenti Date 2020-12-29 Time 13:56 Sent To  
Notes
2020-12-29 13:59:32PETER E VALENTI
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6673
  
 FBC = FLORIDA BUILDING CODE, 6TH EDITION (2017)
 FBC B = FBC BUILDING
 FBC EB = FBC EXISTING BUILDING
 FBC A = FBC ACCESSIBILITY
 FBC EC = FBC ENERGY CONSERVATION
 FBC R = FBC RESIDENTIAL
 FBC M = FBC MECHANICAL
 FBC FG = FBC FUEL GAS
  
 ROOFING SUB-PERMIT IS REQUIRED. PROVIDE ROOFING PRODUCT
 APPROVALS (REVIEW STAMPED BY ENGINEER OF RECORD) WITH
 ROOFING SUB-PERMIT.

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2020-12-29 Cont ID  
Sent By medwards Date 2020-12-29 Time 13:39 Rev Time 0.00
Received By medwards Date 2020-12-29 Time 13:39 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status P Date 2020-11-04 Cont ID  
Sent By equinone Date 2020-11-04 Time 15:54 Rev Time 0.00
Received By equinone Date 2020-11-04 Time 15:54 Sent To  
Notes
2020-11-04 15:55:58PAPER DRAWINGS HAVE ORIGINAL SIGNATURE AND SEAL. ROUTED
 TO STORAGE. EQ

Review Stop Z ZONING
Rev No 1 Status P Date 2020-11-23 Cont ID  
Sent By aaponte Date 2020-11-23 Time 16:15 Rev Time 0.00
Received By aaponte Date 2020-11-23 Time 16:15 Sent To  
Notes
***NONE***