2020-11-06 12:53:32 | RESIDENTIAL (R3) SHUTTERS SECOND BUILDING REVIEW |
| COMMENTS |
| CODE: FBC 6TH EDITION (2017) AND CITY AMENDMENTS. |
| |
| NOTE: SEC. 702.6 FBC-EXISTING BUILDING. ALL NEW WORK |
| SHALL COMPLY WITH THE MATERIALS AND METHODS |
| REQUIREMENTS IN THE FLORIDA BUILDING CODE. |
| |
| ORIGINAL COMMENT: |
| |
| SHUTTERS INSTALLATION SCHEDULE SUBMITTED: |
| 1- CONTRACTOR SPECIFIES UNDER THE SUBSTRATE COLUMN THAT |
| THERE IS A "SOLID CONCRETE TOP BEAM". THERE ARE NOT |
| SPECIFICATIONS FOR THE SUBSTRATE AT THE BOTTOM OF THE |
| OPENING. TYPICALLY, THE CONCRETE ANCHOR SCHEDULE IS |
| USED FOR TOP ANCHORS AND CONCRETE BLOCK ANCHOR SCHEDULE |
| IS USED FOR BOTTOM ANCHORS UNLESS CONTRACTOR PROVES |
| THAT THE OPENING SILL IS CONCRETE WITH THE REQUIRED |
| CONCRETE STRENGTH. |
| CONTRACTOR IS USING THE SAME CONCRETE ANCHOR SCHEDULE |
| FOR TOP AND BOTTOM ANCHOR SPACING. REVISE ANCHOR |
| SPACING AS REQUIRED OR PROVIDE DETAILS OF THE OPENING |
| SILL CONSTRUCTION INCLUDING THE STRENGTH OF THE |
| CONCRETE. |
| |
| RESPONSE: |
| COMMENTS WERE NOT ADDRESSED. THE ONLY THING CONTRACTOR |
| RESUBMIT WAS A PRINTOUT FROM PAPA. THIS WAS NOT |
| REQUESTED AND DOESN'T ADDRESS THE COMMENTS. PLEASE |
| REVIEW THE COMMENTS ABOVE AND REVISE THE SHUTTERS |
| INSTALLATION SCHEDULE ACCORDINGLY AND RESUBMIT. |
| |
| PLEASE FEEL FREE TO CONTACT ME IF YOU HAVE ANY |
| QUESTIONS REGARDING THESE COMMENTS, |
| JULIO GOMEZ |
| COMMERCIAL COMBINATION PLANS EXAMINER |
| DEVELOPMENT SERVICES DEPARTMENT |
| BUILDING DIVISION |
| (561)805-6712 |
| [email protected] |
| |