Plan Review Details - Permit 20100646
Plan Review Stops For Permit 20100646
Review Stop FIRE FIRE DEPARTMENT
Rev No 3 Status P Date 2020-12-04 Cont ID  
Sent By pleduc Date 2020-12-04 Time   Rev Time 0.00
Received By pleduc Date 2020-12-04 Time 13:08 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status F Date 2020-11-06 Cont ID  
Sent By pleduc Date 2020-11-06 Time   Rev Time 0.00
Received By pleduc Date 2020-11-06 Time 14:36 Sent To  
Notes
2020-11-06 14:56:00THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE
 MARSHAL, WITH THE FOLLOWING COMMENTS:
  
  
 1) THERE ARE TWO NEW SHEETS SUBMITTED WITH THE ORIGINAL
 SHEETS DELETED.
  
 THE ORIGNAL SHEETS NEED TO BE INCLUDED AS SOME OF THE
 INFOAMTION WAS ACCEPTABLE AND NEEDS TO REPRESENTED
  
  
  
 2) THE NEW SHEETS INDICATE SOME NUMBERS BUT I DON'T
 KNOW WHAT THOSE NUMBERS EQUATE TO IN INCHES.
  
 PLEASE CLARIFY.
  
  
 2A) WHAT WILL THE HEIGHT BE TO THE TOP OF THE GLASS
 ABOVE THE FLAME?
  
  
  
  
 3) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET
 REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE
 ABOVE.
  
  
 4) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE
 RE-SUBMITTAL OF THE ABOVE.
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status F Date 2020-10-16 Cont ID  
Sent By pleduc Date 2020-10-16 Time   Rev Time 0.00
Received By pleduc Date 2020-10-16 Time 11:20 Sent To  
Notes
2020-10-16 11:21:45THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE
 MARSHAL, WITH THE FOLLOWING COMMENTS:
  
 IT APPEARS THAT THIS GLASS SCREEN APPEARS TO BE 6" AND
 WOULD BARELY EXCEED THE HEIGHT OF THE FLAME.
 INTENTIONAL ACCESS TO THE FLAME IS EASILY DONE.
  
 THE GLASS SCREEN WOULD NEED TO BE HIGHER AND ACT AS A
 GREATER DETERENT. A 12" SCREEN MAY PROVIDE THE NEEDED
 HEIGHT.
  
 FIRE MARSHAL
 561-804-4709
 [email protected]
  

Review Stop G GAS REVIEW
Rev No 1 Status N Date 2020-10-19 Cont ID  
Sent By lcrespo Date 2020-10-19 Time 17:00 Rev Time 0.00
Received By lcrespo Date 2020-10-19 Time 17:00 Sent To  
Notes
2020-10-19 17:02:51THIS GAS PERMIT APPORVED UNDER PERMIT 20090600, SUMITAL
 ALLPY FOR FIRE PIT TO BE REVIEWED BY FIRE.

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2020-12-04 Cont ID  
Sent By ccarvaja Date 2020-12-04 Time 14:08 Rev Time 0.00
Received By ccarvaja Date 2020-12-03 Time 16:30 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2020-11-06 Cont ID  
Sent By ccarvaja Date 2020-11-06 Time 16:12 Rev Time 0.00
Received By ccarvaja Date 2020-11-04 Time 10:17 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-10-19 Cont ID  
Sent By lcrespo Date 2020-10-19 Time 17:01 Rev Time 0.00
Received By lcrespo Date 2020-10-14 Time 11:19 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status N Date 2020-10-19 Cont ID  
Sent By lcrespo Date 2020-10-19 Time 17:00 Rev Time 0.00
Received By lcrespo Date 2020-10-19 Time 17:00 Sent To  
Notes
2020-10-19 17:03:01THIS GAS PERMIT APPORVED UNDER PERMIT 20090600, SUMITAL
 ALLPY FOR FIRE PIT TO BE REVIEWED BY FIRE.

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status N Date 2020-10-19 Cont ID  
Sent By lcrespo Date 2020-10-19 Time 17:01 Rev Time 0.00
Received By lcrespo Date 2020-10-19 Time 17:01 Sent To  
Notes
***NONE***