Plan Review Details - Permit 20100104
Plan Review Stops For Permit 20100104
Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status P Date 2021-03-03 Cont ID  
Sent By rmcdouga Date 2021-03-03 Time 15:32 Rev Time 0.00
Received By rmcdouga Date 2021-03-03 Time 15:32 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status F Date 2021-03-03 Cont ID  
Sent By rmcdouga Date 2021-03-03 Time 08:10 Rev Time 0.00
Received By rmcdouga Date 2021-03-03 Time 08:10 Sent To  
Notes
2021-03-03 08:24:51PLAN
 REVIEW COMMENTS
  
 3RD REVIEW: FBC SIXTH EDITION (2017)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) NOT RESOLVED. [THE OVERALL SITE PLAN DOES NOT SHOW
 THE CHANGES MADE TO AREA 2 WHERE AN ADDITIONAL CHARGING
 STATION WAS ADDED TO COMPLY WITH ACCESSIBILITY.] THE
 RE-SUBMITTED PLANS DO NOT COMPLETELY ADDRESS THE
 ACCESSIBILITY ISSUE. THE SITE PLAN INDICATES THAT THE
 EVC STATIONS ARE LOCATED IN TWO DIFFERENT PARKING AREAS
 WHICH ARE FOR TWO DIFFERENT BUILDINGS. THE AREAS ARE
 NAMED AREA 1 AND AREA 2.
 AREA 1 HAS SIX EXISTING ACCESSIBLE PARKING SPACES AND
 THIS PARKING LOT SERVES THE DIALYSIS CENTER. THERE WILL
 BE A TOTAL OF 5 EV SPACES IN THIS AREA. THE PLAN
 INDICATES THAT AN EVC STATION WILL BE INSTALLED AT ONE
 OF THE EXISTING ACCESSIBLE SPACES. THIS IS ACCEPTABLE.
 AREA 2 HAS EIGHT EXISTING ACCESSIBLE PARKING SPACES AND
 THIS LOT SERVES THE AMBULATORY SURGICAL CENTER. THERE
 WILL BE A TOTAL OF 8 EV SPACES IN THIS AREA. THERE ARE
 NO ACCESSIBLE EVC STATIONS INDICATED ON THE PLANS FOR
 AREA 2. AT LEAST ONE OF THESE CHARGING STATIONS SHOULD
 BE ACCESSIBLE. FBC ACCESSIBILITY CHAPTERS 3, 4 AND 5
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2021-02-11 Cont ID  
Sent By rmcdouga Date 2021-02-11 Time 07:47 Rev Time 0.00
Received By rmcdouga Date 2021-02-10 Time 15:33 Sent To  
Notes
2021-02-11 07:53:13PLAN
 REVIEW COMMENTS
  
 2ND REVIEW: FBC SIXTH EDITION (2017)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) THE RE-SUBMITTED PLANS DO NOT COMPLETELY ADDRESS THE
 ACCESSIBILITY ISSUE. THE SITE PLAN INDICATES THAT THE
 EVC STATIONS ARE LOCATED IN TWO DIFFERENT PARKING AREAS
 WHICH ARE FOR TWO DIFFERENT BUILDINGS. THE AREAS ARE
 NAMED AREA 1 AND AREA 2.
 AREA 1 HAS SIX EXISTING ACCESSIBLE PARKING SPACES AND
 THIS PARKING LOT SERVES THE DIALYSIS CENTER. THERE WILL
 BE A TOTAL OF 5 EV SPACES IN THIS AREA. THE PLAN
 INDICATES THAT AN EVC STATION WILL BE INSTALLED AT ONE
 OF THE EXISTING ACCESSIBLE SPACES. THIS IS ACCEPTABLE.
 AREA 2 HAS EIGHT EXISTING ACCESSIBLE PARKING SPACES AND
 THIS LOT SERVES THE AMBULATORY SURGICAL CENTER. THERE
 WILL BE A TOTAL OF 8 EV SPACES IN THIS AREA. THERE ARE
 NO ACCESSIBLE EVC STATIONS INDICATED ON THE PLANS FOR
 AREA 2. AT LEAST ONE OF THESE CHARGING STATIONS SHOULD
 BE ACCESSIBLE. FBC ACCESSIBILITY CHAPTERS 3, 4 AND 5
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2021-01-11 Cont ID  
Sent By rmcdouga Date 2021-01-11 Time 13:15 Rev Time 0.00
Received By rmcdouga Date 2021-01-11 Time 11:55 Sent To  
Notes
2021-01-11 13:15:01PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC SIXTH EDITION (2017)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) SPECIFY INTENDED USERS OF THE CAR CHARGING STATIONS.
 FOR EXAMPLE ARE THEY FOR THE USE OF THE PATIENTS,
 EMPLOYEES, FLEET VECHILES, ETC.
  
 2) SHOW HOW THE CAR CHARGING STATIONS AND PARKING
 COMPLY WITH FBC ACCESSIBILITY.
  
 3) WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A
 RESPONSE LETTER ADDRESSING EACH ITEM ALONG WITH THE
 CITY RE-SUBMITTAL FORM.
2021-01-08 17:11:11THIS STOP WAS ADDED TO SEE IF THEY NEED TO COMPLY WITH
 ADA REQUIREMENTS. JLEAHY

Review Stop E ELECTRICAL
Rev No 6 Status P Date 2021-03-03 Cont ID  
Sent By jleahy Date 2021-03-03 Time 08:18 Rev Time 0.00
Received By jleahy Date 2021-03-03 Time 06:53 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 5 Status F Date 2021-02-12 Cont ID  
Sent By jleahy Date 2021-02-12 Time 08:16 Rev Time 0.00
Received By jleahy Date 2021-02-10 Time 17:10 Sent To  
Notes
2021-02-11 12:57:07ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW.
  
 FLORIDA BUILDING CODE 2017 6TH EDITION
 FLORIDA BUILDING CODE ENERGY CONSERVATION 2017 6TH ED
 NFPA 70 2014 EDITION
  
 JAKE LEAHY BN, BU, PX
 ELECTRICAL PLANS EXAMINER II
 561-805-6713
 [email protected]
  
 PAGE E-1 LOAD CALCULATION FOR FEEDER TO PANEL EV NOT IN
 ACCORDANCE WITH 625.40.
  
 PAGE E-2 LOAD CALCULATION FOR FEEDER TO EAST LOT PANEL
 NOT IN ACCORDANCE WITH 625.40.
  
 PAGE AREA 1 SHOWS A FEEDER WITH 3 #1 AND A #6 AND
 ANOTHER BRANCH GOING TO THE HANDICAP SPACE WHAT FEEDS
 THE HANDICAP SPACE. WHERE IS THE HANDICAP FED FROM?
 125A MAIN/ 200A MAIN?
  
 PAGE AREA 2 SHOWS 3/0 GOING TO THE PANEL, LOAD
 CALCULATION SHOWN FOR THESE CONDUCTORS IS NOT PER
 625.40. 200A MAIN/300A MAIN?
  
 PLEASE PROVIDE A VOLTAGE DROP CALCULATION BASED ON
 625.40 LOAD CALCULATION.
  
 DO YOU HAVE LOAD MANAGEMENT IF SO PLEASE EXPLAN HOW IT
 WORKS.
  
  

Review Stop E ELECTRICAL
Rev No 4 Status F Date 2021-01-08 Cont ID  
Sent By jleahy Date 2021-01-08 Time 16:32 Rev Time 0.00
Received By jleahy Date 2021-01-08 Time 16:27 Sent To  
Notes
2021-01-08 17:05:44ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW.
  
 FLORIDA BUILDING CODE 2017 6TH EDITION
 FLORIDA BUILDING CODE ENERGY CONSERVATION 2017 6TH ED
 NFPA 70 2014 EDITION
  
 JAKE LEAHY BN, BU, PX
 ELECTRICAL PLANS EXAMINER II
 561-805-6713
 [email protected]
  
 1) VALUE OF JOB DOES NOT INCLUDE THE VALUE OF THE
 CHARGERS.
  
 FBC 109.3 BUILDING PERMIT VALUATION. FOR PERMITTING
 PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL BE
 TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL,
 ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH,
 RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES,
 MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING ONLY
 LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE LATEST
 PUBLISHED DATA OF NATIONAL CONSTRUCTION COST ANALYSIS
 SERVICES (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY
 INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT
 VALUATION SHALL BE SET BY THE BUILDING OFFICIAL.
  
 2) ALL PAGES ARE NOT SIGNED IF THEY ARE FROM AN
 ENGINEERING FIRM THEY WILL NEED TO SIGNED AND SEALED BY
 THAT FIRM. SITE PLAN NOT SIGNED,
  
 PLAN IS NOT DIGITALLY SIGNED BY THE DESIGNER OF RECORD
  
 PLAN IS REQUIRED TO BE SIGNED AND SEALED BY A DESIGN
 PROFESSIONAL OR THE ELECTRICAL CONTRACTOR QUALIFIER. FS
 471.003(2)(H); 471.025; FBC 107.2.1
  
 3) PLEASE SHOW A BETTER DETAIL OF EXACTLY WHERE
 PANELS(SERVICE) AND CHARGERS ARE TO BE INSTALLED IN
 PARKING LOT. SITE PLAN IS TO VAGUE. PLAN NEEDS TO SHOW
 IF BOLLARDS OR SOME OTHER TYPE OF PROTECTION WILL BE
 REQUIRED FOR PROTECTION OF THE SERVICE, PANELS, OR
 CHARGERS AS INSTALLED.
  
 107.2.1.4 QUALITY OF BUILDING PLANS. BUILDING PLANS
 SHALL BE DRAWN TO A MINIMUM 1/8 INCH SCALE UPON
 SUBSTANTIAL PAPER, CLOTH OR OTHER ACCEPTABLE MEDIUM.
 THIS POLICY MAY INCLUDE SUCH THINGS AS MINIMUM SIZE,
 SHAPE, CONTRAST, CLARITY, OR OTHER ITEMS RELATED TO
 RECORDS MANAGEMENT.

Review Stop E ELECTRICAL
Rev No 3 Status F Date 2020-11-20 Cont ID  
Sent By jleahy Date 2020-11-20 Time 15:33 Rev Time 0.00
Received By jleahy Date 2020-11-20 Time 15:28 Sent To  
Notes
2020-11-20 15:37:38ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW.
  
 FLORIDA BUILDING CODE 2017 6TH EDITION
 FLORIDA BUILDING CODE ENERGY CONSERVATION 2017 6TH ED
 NFPA 70 2014 EDITION
  
 JAKE LEAHY BN, BU, PX
 ELECTRICAL PLANS EXAMINER II
 561-805-6713
 [email protected]
  
 APPLICATION STILL STATES 3 CHARGERS. IS IT 3 OR 12?
  
 SUBMIT A SIGNED CONTRACT FOR THE WORK INVOLVED
 (MATERIALS, LABOR ECT) THIS INCLUDES THE CHARGERS.
 FBC 109.3 BUILDING PERMIT VALUATION. FOR PERMITTING
 PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL BE
 TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL,
 ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH,
 RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES,
 MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING ONLY
 LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE LATEST
 PUBLISHED DATA OF NATIONAL CONSTRUCTION COST ANALYSIS
 SERVICES (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY
 INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT
 VALUATION SHALL BE SET BY THE BUILDING OFFICIAL
  
 SHOW ON SITE PLAN WHERE POWER IS COMING FROM IN AREA 1
 AND 2 AND THE LOCATIONS OF THE SERVICES FOR THE
 CHARGERS. 215.5

Review Stop E ELECTRICAL
Rev No 2 Status F Date 2020-11-02 Cont ID  
Sent By jleahy Date 2020-11-02 Time 17:40 Rev Time 0.00
Received By jleahy Date 2020-11-02 Time 13:52 Sent To  
Notes
2020-11-02 17:43:05ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW.
  
 FLORIDA BUILDING CODE 2017 6TH EDITION
 FLORIDA BUILDING CODE ENERGY CONSERVATION 2017 6TH ED
 NFPA 70 2014 EDITION
  
 JAKE LEAHY BN, BU, PX
 ELECTRICAL PLANS EXAMINER II
 561-805-6713
 [email protected]
  
 1) PAPER WORK SHOWS 6 CHARGERS ELECTRICAL PLAN SHOWS 4.
  
 2) NEED A SITE PLAN TO SHOW WHERE CHARGERS ARTE GOING
 TO BE INSTALLED.
  
 3) SENT TO ZONING FOR REVIEW.

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2020-10-19 Cont ID  
Sent By fgiaquin Date 2020-10-19 Time 22:00 Rev Time 0.00
Received By fgiaquin Date 2020-10-19 Time 21:31 Sent To  
Notes
2020-10-19 22:00:15ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW.
  
 1. PROVIDE ELECTRICAL PLAN FOR REVIEW, SIGNED AND
 SEALED BY A LICENSED DESIGN PROFESSIONAL OR SIGNED BY
 THE ELECTRICAL CONTRACTOR QUALIFIER. FS 471.003(2)(H);
 471.025; WPB FBC 107.2.1, 107.3.5
  
 END OF COMMENTS.
  
 PLEASE NOTE: SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. WHEN
 RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RESUBMITTAL FORM. ADDITIONALLY, INSERT CORRECTED PAGES
 INTO THE ORIGINAL SUBMITTAL AND REMOVE OR VOID THE
 PREVIOUSLY REVIEWED SHEETS.
 CODES IN EFFECT:
  
 HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B
 UILDING-PERMIT-FORMS
  
  
 FBC = FLORIDA BUILDING CODE 2017 6TH EDITION
 WPB FBC = WEST PALM BEACH AMENDMENTS TO THE FLORIDA
 BUILDING CODE 2017 6TH ED.
 FBC EB = FLORIDA BUILDING CODE EXISTING BUILDING 2017
 6TH EDITION
 FBC EC = FLORIDA BUILDING CODE ENERGY CONSERVATION 2017
 6TH EDITION
 FBC RE = FLORIDA RESIDENTIAL CODE 2017 6TH EDITION
 NEC = NFPA 70 2014 EDITION, NATIONAL ELECTRICAL CODE
 FS = FLORIDA STATUTES
  
 V/R,
  
 FRANK GIAQUINTO III
 ELECTRICAL INSPECTOR
 ELECTRICAL PLANS EXAMINER
 CITY OF WEST PALM BEACH
 [email protected]
 CELL: 561-657-1653
  
  

Review Stop I INCOMING/PROCESSING
Rev No 7 Status N Date 2021-03-04 Cont ID  
Sent By jleahy Date 2021-03-04 Time 09:00 Rev Time 0.00
Received By jleahy Date 2021-03-01 Time 14:38 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 6 Status N Date 2021-02-12 Cont ID  
Sent By jleahy Date 2021-02-12 Time 08:22 Rev Time 0.00
Received By jleahy Date 2021-02-09 Time 10:06 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 5 Status N Date 2021-01-11 Cont ID  
Sent By rmcdouga Date 2021-01-11 Time 13:15 Rev Time 0.00
Received By rmcdouga Date 2020-12-29 Time 15:10 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2020-12-29 Cont ID  
Sent By lmarchan Date 2020-12-29 Time 11:47 Rev Time 0.00
Received By lmarchan Date 2020-12-17 Time 22:34 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2020-11-20 Cont ID  
Sent By jleahy Date 2020-11-20 Time 15:38 Rev Time 0.00
Received By jleahy Date 2020-11-10 Time 13:34 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2020-11-06 Cont ID  
Sent By ccarvaja Date 2020-11-06 Time 10:19 Rev Time 0.00
Received By ccarvaja Date 2020-10-23 Time 15:31 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-10-19 Cont ID  
Sent By fgiaquin Date 2020-10-19 Time 22:00 Rev Time 0.00
Received By fgiaquin Date 2020-10-02 Time 15:04 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 6 Status P Date 2021-03-03 Cont ID  
Sent By jleahy Date 2021-03-03 Time 08:18 Rev Time 0.00
Received By jleahy Date 2021-03-03 Time 08:18 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 5 Status P Date 2021-02-12 Cont ID  
Sent By jleahy Date 2021-02-12 Time 08:19 Rev Time 0.00
Received By jleahy Date 2021-02-12 Time 08:19 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 4 Status F Date 2021-01-08 Cont ID  
Sent By jleahy Date 2021-01-08 Time 17:09 Rev Time 0.00
Received By jleahy Date 2021-01-08 Time 17:08 Sent To  
Notes
2021-01-08 17:09:49NOT ALL PAGES ARE SIGNED THAT WERE SUBMITED. JLEAHY

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 3 Status F Date 2020-11-20 Cont ID  
Sent By jleahy Date 2020-11-20 Time 15:37 Rev Time 0.00
Received By jleahy Date 2020-11-20 Time 15:37 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2020-11-02 Cont ID  
Sent By jleahy Date 2020-11-02 Time 17:43 Rev Time 0.00
Received By jleahy Date 2020-11-02 Time 13:52 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2020-10-19 Cont ID  
Sent By fgiaquin Date 2020-10-19 Time 22:00 Rev Time 0.00
Received By fgiaquin Date 2020-10-19 Time 22:00 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 5 Status P Date 2021-03-04 Cont ID  
Sent By llouie Date 2021-03-04 Time   Rev Time 0.00
Received By llouie Date 2021-03-04 Time   Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 4 Status P Date 2020-12-31 Cont ID  
Sent By llouie Date 2020-12-31 Time   Rev Time 0.00
Received By llouie Date 2020-12-31 Time   Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 3 Status F Date 2020-12-28 Cont ID  
Sent By llouie Date 2020-12-28 Time   Rev Time 0.00
Received By llouie Date 2020-12-28 Time   Sent To  
Notes
2020-12-28 18:39:58** FAILED **
  
 PLEASE ADDRESS THE FOLLOWING COMMENTS. RESPOND TO THE
 COMMENTS IN WRITING AND/OR ON THE PLANS WHERE
 APPLICABLE:
  
 1.) SITE PLAN SHOWING EXACT LOCATION OF THE CHARGING
 STATIONS, AS DISCUSSED WITH ANJUL CHOKSHI OF FPL, HAS
 NOT INCLUDED WITH THE LATEST RESUBMITTAL FOR THE
 PERMIT. MUST BE ADDRESSED PRIOR TO ZONING SIGN-OFF.
  
 NOTES:
  
 * ANY REVISIONS MAY RESULT IN ADDITIONAL COMMENTS.
  
 * CONTACT LINDA LOUIE @ (561) 822-1458 IF THERE ARE
 QUESTIONS.
  

Review Stop Z ZONING
Rev No 2 Status F Date 2020-11-18 Cont ID  
Sent By llouie Date 2020-11-18 Time   Rev Time 0.00
Received By llouie Date 2020-11-18 Time   Sent To  
Notes
2020-11-18 09:39:13** FAILED **
  
 PLEASE ADDRESS THE FOLLOWING COMMENTS. RESPOND TO THE
 COMMENTS IN WRITING AND/OR ON THE PLANS WHERE
 APPLICABLE:
  
 1.) AN UPDATED SURVEY OF THE PROPERTY IS REQUIRED.
 [11/6/2020 REPEAT COMMENT: NOT ADDRESSED.]
  
 2.) SITE PLAN, SHOWING THE EXACT LOCATION OF THE
 PROPOSED CHARGING STATIONS IS REQUIRED. ALSO PARKING
 CALCULATIONS FOR THE ENTIRE SITE IS REQUIRED. PLEASE
 NOTE THAT CHARGING STATIONS WOULD ONLY BE PERMITTED IF
 THE PROVIDED PARKING IS IN EXCESS TO THE REQUIRED
 PARKING FOR THE USE. [11/6/2020 REPEAT COMMENT: NOT
 ADDRESSED.]
  
 3.) INFORMATION PROVIDED IN THE PERMIT PACKET IS
 INCONSISTENT. THE SCOPE OF WORK INDICATES THAT ONLY 3
 CHARGING STATIONS ARE PROPOSED; HOWEVER, DOCUMENTS
 PROVIDED WITH THE PERMIT PACKET INDICATE A TOTAL OF 6
 CHARGING STATIONS ARE PROPOSED FOR THE SITE. PLEASE
 CLARIFY. [11/6/2020 REPEAT COMMENT: NOT ADDRESSED.]
  
  
 NOTES:
  
 * ANY REVISIONS MAY RESULT IN ADDITIONAL COMMENTS.
  
 * CONTACT LINDA LOUIE @ (561) 822-1458 IF THERE ARE
 QUESTIONS.
  
 * ZONE: CSPD (TENANT ST. MARY'S)
  

Review Stop Z ZONING
Rev No 1 Status F Date 2020-11-06 Cont ID  
Sent By llouie Date 2020-11-06 Time   Rev Time 0.00
Received By llouie Date 2020-11-06 Time   Sent To  
Notes
2020-11-06 08:44:15** FAILED **
  
 PLEASE ADDRESS THE FOLLOWING COMMENTS. RESPOND TO THE
 COMMENTS IN WRITING AND/OR ON THE PLANS WHERE
 APPLICABLE:
  
 1.) AN UPDATED SURVEY OF THE PROPERTY IS REQUIRED.
  
 2.) SITE PLAN, SHOWING THE EXACT LOCATION OF THE
 PROPOSED CHARGING STATIONS IS REQUIRED. ALSO PARKING
 CALCULATIONS FOR THE ENTIRE SITE IS REQUIRED. PLEASE
 NOTE THAT CHARGING STATIONS WOULD ONLY BE PERMITTED IF
 THE PROVIDED PARKING IS IN EXCESS TO THE REQUIRED
 PARKING FOR THE USE.
  
 3.) INFORMATION PROVIDED IN THE PERMIT PACKET IS
 INCONSISTENT. THE SCOPE OF WORK INDICATES THAT ONLY 3
 CHARGING STATIONS ARE PROPOSED; HOWEVER, DOCUMENTS
 PROVIDED WITH THE PERMIT PACKET INDICATE A TOTAL OF 6
 CHARGING STATIONS ARE PROPOSED FOR THE SITE. PLEASE
 CLARIFY.
  
  
 NOTES:
  
 * ANY REVISIONS MAY RESULT IN ADDITIONAL COMMENTS.
  
 * CONTACT LINDA LOUIE @ (561) 822-1458 IF THERE ARE
 QUESTIONS.
  
 * ZONE: CSPD (TENANT ST. MARY?S)
  
2020-11-02 17:44:52CUSTOMER IS INSTALLING 4 TO 6 CHARGERS (ELECTRIC
 VEHICLES) SOMEWHERE IN THE PARKING LOT?


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved