Plan Review Details - Permit 20080929
Plan Review Stops For Permit 20080929
Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 2 Status P Date 2020-09-22 Cont ID  
Sent By cthroop Date 2020-09-22 Time 06:17 Rev Time 0.00
Received By cthroop Date 2020-09-21 Time 18:59 Sent To  
Notes
2020-09-22 06:18:08NO NOTES

Review Stop ASBESTOS CONFIRM RPT SENT TO PBC HEALTH
Rev No 1 Status F Date 2020-09-12 Cont ID  
Sent By shill Date 2020-09-12 Time 08:41 Rev Time 0.00
Received By shill Date 2020-09-12 Time 08:41 Sent To  
Notes
2020-09-12 08:41:36SEE BUILDING REVIEW
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2020-09-22 Cont ID  
Sent By cthroop Date 2020-09-22 Time 06:18 Rev Time 0.00
Received By cthroop Date 2020-09-21 Time 18:59 Sent To  
Notes
2020-09-22 06:33:16NO NOTES

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2020-09-12 Cont ID  
Sent By shill Date 2020-09-12 Time 08:40 Rev Time 0.00
Received By shill Date 2020-09-12 Time 08:25 Sent To  
Notes
2020-09-12 08:41:06****CORRECTIONS****
  
 SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 1. TOO MANY UNNECESSARY DOCUMENTS WERE UPLOADED. THE
 WPB UTILITY RELEASE FORM WAS UPLOADED TWICE, NEITHER
 WAS SIGNED OFF BY UTILITIES (SO BOTH WILL BE DELETED).
 A NUMBER OF "WORK ORDER" DOCUMENTS WERE UPLOADED; THEY
 ARE NOT NEEDED TO OBTAIN A PERMIT. THE CHECKLIST WAS
 UPLOADED BUT THE DOCUMENTS REQUIRED WERE NOT. IN THE
 FUTURE PLEASE DO NOT UPLOAD DOCUMENTS THAT ARE NOT
 NEEDED AS THIS DELAYS PLAN REVIEW.
  
 THE FOLLOWING ITEMS ARE REQUIRED PRIOR TO ISSUANCE OF A
 DEMO PERMIT PER FLORIDA BUILDING CODE, BUILDING 3303:
  
 1. UTILITY RELEASE - FLORIDA POWER & LIGHT (ELECTRIC)
 RELEASE OF SERVICE CONFIRMATION
  
 2. UTILITY RELEASE - FLORIDA PUBLIC UTILITIES (GAS)
 RELEASE OF SERVICE CONFIRMATION
  
 3. UTILITY RELEASE - CITY OF WEST PALM BEACH WATER
 DEPARTMENT, REQUEST FOR METER PULL, ON THEIR FORM
 "DEMOLITION APPLICATION"
  
 HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B
 UILDING-PERMIT-FORMS
  
  IF A HYDRANT METER OR BACKFLOW PREVENTER IS DESIRED,
 THEN A PARTIAL RELEASE WILL BE NOTED ON THEIR FORM.
  
 FAX THE COMPLETED "DEMOLITION APPLICATION" FORM TO
 561-822-2183. AFTER THEY FAX THE RELEASE TO YOU, SEND A
 COPY VIA EMAIL TO [email protected] WITH THE PERMIT
 NUMBER IN THE SUBJECT LINE.
  
 5. EXTERMINATION LETTER - LETTER FROM A LICENSED PEST
 CONTROL COMPANY STATING THAT DEMOLITION ADDRESS HAS
 BEEN INSPECTED AND/OR TREATED FOR RODENTS.
  
 6. COMPLETE THE DEMO DEBRIS FORM:
  
 HTTP://WPB.ORG/DEPARTMENTS/DEVELOPMENT-SERVICES/FORMS/B
 UILDING-PERMIT-FORMS
  
 7. PROVIDE A SITE PLAN OR SURVEY SHOWING LOCATION OF
 THE STRUCTURE(S) TO BE DEMOLISHED.
  
 8. PROVIDE A STORMWATER POLLUTION PREVENTION PLAN.
  
 9. PROVIDE A SIGNED ACKNOWLEDGEMENT FROM THE
 CONTRACTOR, ON LETTERHEAD, STATING THAT THE
 INSTRUCTIONS ON THE WEBSITE OF ASBESTOS PROGRAM
 COORDINATOR, FLORIDA DEPARTMENT OF HEALTH PALM BEACH
 COUNTY WILL BE FOLLOWED AND THAT NOTIFICATION WILL BE
 GIVEN TIMELY. ADDITIONAL INFORMATION REGARDING ASBESTOS
 REQUIREMENTS CAN BE FOUND ON THEIR WEBSITE:
  
 HTTP://PALMBEACH.FLORIDAHEALTH.GOV/PROGRAMS-AND-SERVICE
 S/ENVIRONMENTAL-HEALTH/AIR-QUALITY/ASBESTOS-DEMOLITION-
 RENOVATION.HTML
  
  

Review Stop ENG ENGINEERING CSD
Rev No 3 Status P Date 2020-09-21 Cont ID  
Sent By rrossano Date 2020-09-21 Time   Rev Time 0.00
Received By rrossano Date 2020-09-21 Time   Sent To  
Notes
2020-09-21 16:04:04PASSED WITH PROVISOS:
  
 PLEASE MAINTAIN POLLUTION CONTROL PLAN ONSITE SHOWING:
  
 A) WHERE SILT SCREENS WILL BE INSTALLED, INCLUDING A
 DETAIL SHOWING THE SILT FENCE INSTALLATION. THESE BMPS
 ARE TO BE USED AS PER THE FDEP EROSION AND SEDIMENT
 CONTROL MANUAL.
 B) SHOW THE PROTECTION OF ALL ON-SITE CATCH BASINS, IF
 ANY.
 C) SHOW PROTECTION OF ALL OFF-SITE CATCH BASINS, IF
 ANY.
 D) INCLUDE DETAILS AS TO THE TYPE OF PROTECTION USED ON
 THE CATCH BASINS, IF ANY.
 E) SHOW HOW SITE DIRT WILL NOT BE TRACKED INTO THE
 ROADS.
 F) SHOW HOW DUST CONTROL WILL BE PROVIDED.
  
 HTTP://WWW.DEP.STATE.FL.US/WATER/STORMWATER/NPDES/DOCS/
 CONST_ACTIVITY.PDF
  
 HTTP://WWW.PBCO-NPDES.ORG/CONSTRUN.ASP?MENU=SWMPMENU
  
 THERE ARE WATER AND SEWER LINES IN THE VICINITY OF THIS
 PROJECT. PER CHAPTER 556 OF THE FLORIDA STATE STATUTES,
 YOU MUST CALL 811 FOR UTILITY LOCATES AT LEAST TWO FULL
 BUSINESS DAYS IN ADVANCE OF ANY CONSTRUCTION OR
 DEMOLITION WORK. INFORMATION CAN BE FOUND HERE:
 HTTP://WWW.SUNSHINE811.COM/
  
 FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR
 CONCERNS, THANKS.
  
 RICK ROSSANO
 PROJECT COORDINATOR
 ENGINEERING SERVICES DEPARTMENT
 401 CLEMATIS STREET, 4TH FLOOR
 WEST PALM BEACH, FL 33401
 (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402)
 MAIN PHONE: (561) 822-1200
 DIRECT: (561) 494-1098
 FAX: (561) 494-1116
 MOBILE: (561) 246-9525
 EMAIL: [email protected]
 WWW.WPB.ORG/ENGINEERING
  

Review Stop ENG ENGINEERING CSD
Rev No 2 Status F Date 2020-09-15 Cont ID  
Sent By rrossano Date 2020-09-15 Time   Rev Time 0.00
Received By rrossano Date 2020-09-15 Time   Sent To  
Notes
2020-09-15 09:22:39PLEASE PROVIDE ALL CITY UTILITY SIGN OFFS
 (WATER/SEWER).

Review Stop ENG ENGINEERING CSD
Rev No 1 Status F Date 2020-09-09 Cont ID  
Sent By rrossano Date 2020-09-09 Time   Rev Time  
Received By rrossano Date 2020-09-09 Time   Sent To  
Notes
2020-09-09 14:48:35PLEASE PROVIDE ALL CITY UTILITY SIGN OFFS
 (WATER/SEWER).

Review Stop HIST HISTORICAL
Rev No 1 Status P Date 2020-08-27 Cont ID  
Sent By fmittner Date 2020-08-27 Time 16:46 Rev Time 0.00
Received By fmittner Date 2020-08-27 Time 16:46 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2020-09-22 Cont ID  
Sent By cthroop Date 2020-09-22 Time 06:33 Rev Time 0.00
Received By cthroop Date 2020-09-14 Time 09:12 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-09-12 Cont ID  
Sent By shill Date 2020-09-12 Time 08:41 Rev Time 0.00
Received By shill Date 2020-08-21 Time 14:39 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status N Date 2020-09-15 Cont ID  
Sent By shill Date 2020-09-15 Time 09:15 Rev Time 0.00
Received By shill Date 2020-09-15 Time 09:15 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2020-08-27 Cont ID  
Sent By fmittner Date 2020-08-27 Time 16:46 Rev Time 0.00
Received By fmittner Date 2020-08-27 Time 16:46 Sent To  