Plan Review Details - Permit 20071107
Plan Review Stops For Permit 20071107
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2020-08-26 Cont ID  
Sent By rmcdouga Date 2020-08-26 Time 10:06 Rev Time 0.00
Received By rmcdouga Date 2020-08-26 Time 10:00 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2020-08-13 Cont ID  
Sent By jleahy Date 2020-08-13 Time 12:03 Rev Time 0.00
Received By jleahy Date 2020-08-13 Time 11:56 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status N Date 2020-08-05 Cont ID  
Sent By lcrespo Date 2020-08-05 Time 16:03 Rev Time 0.00
Received By lcrespo Date 2020-08-05 Time 16:03 Sent To  
Notes
2020-08-05 16:03:24GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN
 THIS SUBMITTAL PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN
 PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND PLANS
 WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE
 RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT
 REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE PER
 THE WPB AMENDMENTS TO FBC SEC. 107.2.1.

Review Stop HIST HISTORICAL
Rev No 1 Status P Date 2020-08-04 Cont ID  
Sent By fmittner Date 2020-08-04 Time 09:19 Rev Time 0.00
Received By fmittner Date 2020-08-04 Time 09:19 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status P Date 2020-09-02 Cont ID  
Sent By lcrespo Date 2020-09-02 Time 18:23 Rev Time 0.00
Received By lcrespo Date 2020-09-02 Time 16:56 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-08-26 Cont ID  
Sent By rmcdouga Date 2020-08-26 Time 10:07 Rev Time 0.00
Received By rmcdouga Date 2020-07-23 Time 15:14 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status P Date 2020-09-02 Cont ID  
Sent By lcrespo Date 2020-09-02 Time 18:16 Rev Time 0.00
Received By lcrespo Date 2020-09-02 Time 18:00 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status F Date 2020-08-05 Cont ID  
Sent By lcrespo Date 2020-08-05 Time 15:18 Rev Time 0.00
Received By lcrespo Date 2020-08-05 Time 15:18 Sent To  
Notes
2020-08-05 16:01:3208/05/20 1ST PLUMBING REVIEW**DENIED** WITH COMMENTS
  
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1. A BACKFLOW PREVENTER REQUIRED PER THE CITY OF WEST
 PALM BEACH ORD #2853-95. A DUAL CHECK VALVE MAY BE USED
 IF NO POOL FILL IS INSTALLED AT THE METER AND INSTALLED
 BY UTILITIES WHICH DO NOT REQUIRE A PERMIT SO PLEASE
 CONTACT THE CITY OF WPB UTILITIES AT 561-822-2240 FOR
 FURTHER DIRECTIONS.
  
 2. A SUB GAS PERMIT IS REQUIRED BY A LICENSED
 CONTRACTOR FOR THE SCOPE OF WORK PER THE WPB AMENDMENTS
 TO THE FBC SEC. 105.1.
  
 3. SUBMIT TOTAL DYNAMIC HEAD CALCULATIONS FOR THE
 MAXIMUM SYSTEM FLOW. THE MAXIMUM FLOW OF THE PUMP FROM
 ITS PUMP CURVE IS NO LONGER ALLOWED TO BE USED IN
 DETERMINING THE MAXIMUM SYSTEM FLOW RATE PER
 ANSI/APSP/ICC 7 - 2013 SECS. 4.4.9, 4.4.9.1. THE 2013
 EDITION ADDRESSES THE FLOW RATE IN GALLONS PER MINUTE
 (GPM). IT REQUIRES THAT THE MAXIMUM SYSTEM FLOW RATE
 DOES NOT EXCEED THE LISTED MAXIMUM FLOW RATE OF THE
 SUCTION OUTLET FITTING ASSEMBLY (DRAIN COVER). THE TDH
 CALCULATIONS MUST INCLUDE ALL OF THE SYSTEM COMPONENTS
 INCLUDING SUCTION AND RETURN PIPING, FITTINGS, VALVES,
 HEATER, FILTER, AND CHLORINATOR. ALL SYSTEM COMPONENTS
 EXCEPT THE PUMP.
  
 4. IDENTIFY ON THE PUMP CURVE WHICH CURVE KEY IS
 SPECIFIC TO THE PUMP BEING INSTALLED ON THIS POOL. THIS
 IS NEEDED TO CONFIRM THE MAXIMUM SYSTEM FLOW FROM THE
 TDH CALCULATIONS PER THE ANSI/APSP/ICC 7 - 2013 SECS.
 4.4.9, 4.4.9.1.
  
 5. SHOWS A VELOCITY CHART PER ANSI/APSP -7 SEC. 4.4. I
 COULD NOT FIND THIS CHART IN APSP-7 2013 PER THE WPB
 AMENDMENTS TO THE FBC SEC. 107.2.1 INFORMATION ON
 CONSTRUCTION DOCUMENTS.
  
 6. INDICATE ON THE PLANS IF THE POOL IS EQUIPPED WITH
 AN AUTOFILL PER THE WPB AMENDMENTS TO THE FBC SEC.
 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
 7. ALL HOSE BIBBS EXPOSED TO THE POOL AREA SHALL BE
 EQUIPPED WITH A VACUUM BREAKER PER THE 2017 FBC
 R4501.9.
  
 8. PLANS NEED TO BE DIGITALLY SIGNED AND SEAL PER THE
 61G15-23.005.
  
 WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION &
 REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS
 NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL
 REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE
 REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION
 PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO
 EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED
 COOPERATION.
  
 LUIS A. CRESPO
 PLUMBING INSPECTOR /
 PLUMBING PLAN REVIEW
 AVAILABLE FROM 1:00 PM TO 4:00 PM
 [email protected]
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2020-09-02 Cont ID  
Sent By lcrespo Date 2020-09-02 Time 18:23 Rev Time 0.00
Received By lcrespo Date 2020-09-02 Time 18:20 Sent To  
Notes
2020-09-02 18:23:47SIGNED AND SEALED DRAWINGS NEED TO BE
 DIGITALLY/ELECTRONICALLY SIGNED BY THE ENGINEER OR
 ARCHITECT TO BE USED IN ELECTRONIC PLAN REVIEW - OR -
 IF YOUR ENGINEER DOES NOT HAVE A ELECTRONIC OR DIGITAL
 SIGNATURE - PLEASE DROP OFF (CITY HALL DROP BOX) THE
 ORIGINAL SIGNED AND SEALED DOCUMENT ALONG WITH A "PLAN
 REVIEW REQUEST FORM" EXPLAINING THE REASON FOR
 SUBMITTING THE DOCUMENT OR DRAWINGS. PLAN REVIEW
 REQUEST FORM CAN BE OBTAINED BY E MAILING [email protected]
 AND ASKING FOR THE FORM.

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2020-08-26 Cont ID  
Sent By rmcdouga Date 2020-08-26 Time 10:07 Rev Time 0.00
Received By rmcdouga Date 2020-08-26 Time 10:07 Sent To  
Notes
2020-08-26 10:13:03ELECTRONICALLY SUBMITTED DRAWINGS ARE REQUIRED TO HAVE
 THE ENGINEER'S DIGITAL SIGNATURE ON THEM. YOU ALSO HAVE
 THE OPTION TO SUBMIT THE SIGNED AND SEALED PAPER
 VERSION OF DRAWINGS. AFTER THE ELECTRONIC PLANS HAVE
 BEEN APPROVED, YOU CAN SUBMIT THE CORRESPONDING PAPER
 DRAWINGS AT THE BUILDING DEPARTMENT TO BE VERIFIED. THE
 ENGINEER'S ORIGINAL HANDWRITTEN SIGNATURE AND SEAL IS
 REQUIRED TO BE ON THE DRAWINGS. NO PHOTOCOPY OR OTHER
 FACSIMILES OF THE SIGNATURE ARE ACCEPTABLE. FS 471 &
 61G15
2020-08-13 12:04:07SIGNATURE ON ELECTRIC IS NOT DIGITALLY SIGNED

Review Stop Z ZONING
Rev No 1 Status P Date 2020-08-04 Cont ID  
Sent By kalexand Date 2020-08-04 Time 09:19 Rev Time 0.00
Received By fmittner Date 2020-08-04 Time 09:19 Sent To  
Notes
***NONE***