Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status P Date 2020-12-11 Cont ID  
Sent By jgomez Date 2020-12-11 Time 13:27 Rev Time 0.00
Received By jgomez Date 2020-12-11 Time 13:16 Sent To  
Notes
2020-12-11 13:28:46CONTRACTOR SUBMITTED REVISED DESIGN PRESSURES
 ENGINEERING. JG.

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2020-08-27 Cont ID  
Sent By rmcphers Date 2020-08-27 Time 13:03 Rev Time 0.00
Received By rmcphers Date 2020-08-27 Time 13:03 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2020-08-04 Cont ID  
Sent By rmcphers Date 2020-08-04 Time 14:42 Rev Time 0.00
Received By rmcphers Date 2020-08-04 Time 14:42 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2020-07-17 Cont ID  
Sent By rmcphers Date 2020-07-17 Time 14:49 Rev Time 0.00
Received By rmcphers Date 2020-07-17 Time 14:49 Sent To  
Notes
2020-07-17 15:02:47WINDOWS
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected].
 CODE USED FOR REVIEW - 2017 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107
 1) PLEASE PROVIDE AN ORIGINAL SIGNED AND SEALED WIND
 DESIGN PRESSURES FOR THE OPENINGS FBC 1609 - THE WIND
 PRESSURES PROVIDED ARE BASED ON WHETHER OR NOT THE
 ADJACENT WINDOWS/ DOORS OR SHUTTERS MEET IMPACT - SINCE
 WE DON'T KNOW WE WOULD NEED TO SAY THEY DON'T - SO WE
 WOULD NEED TO USE THE NON IMPACT SIDE OF THE CHART -
 WHICH HAS A HIGHER PRESSURE - AND THE PRODUCT APPROVALS
 PROVIDED FOR THE WINDOWS WILL NOT MEET THE HIGHER
 PRESSURES. YOU MAY WANT TO PROVIDE A WIND PRESSURE
 ENGINEERING THAT SHOWS WIND ZONES 4 AND 5 - SINCE IT
 APPEARS BY YOUR DRAWING THAT YOU ARE IN A WIND ZONE 4.
 2) PLEASE SHOW THE HEIGHT OF THE BUILDING ON YOUR FLOOR
 PLAN.
  
 FYI = SIGNED AND SEALED DRAWINGS IN PROJECTDOX NEED TO
 BE DIGITALLY/ELECTRONICALLY SIGNED BY THE ENGINEER OR
 ARCHITECT TO BE USED IN ELECTRONIC PLAN REVIEW.
 DRAWINGS DO NOT SHOW IN "ADOBE READER" AS
 DIGITALLY/ELECTRONICALLY SIGNED. - OR - IF YOUR
 ENGINEER DOES NOT HAVE AN ELECTRONIC OR DIGITAL
 SIGNATURE - PLEASE DROP OFF (CITY HALL DROP BOX) THE
 ORIGINAL SIGNED AND SEALED DRAWINGS/DOCUMENTS ALONG
 WITH A "PLAN REVIEW REQUEST FORM" EXPLAINING THE REASON
 FOR SUBMITTING THE DOCUMENT OR DRAWINGS. PLAN REVIEW
 REQUEST FORM CAN BE OBTAINED BY E MAILING [email protected]
 AND ASKING FOR THE FORM. (AT THIS TIME DROP BOX ITEMS
 MAY TAKE 2 TO 3 WEEKS TO PROCESS, TO SEND TO PLAN
 REVIEW - DUE TO LIMITED STAFF INSIDE THE BUILDING
 DEPT.)

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2020-12-11 Cont ID  
Sent By jgomez Date 2020-12-11 Time 13:28 Rev Time 0.00
Received By jgomez Date 2020-12-11 Time 13:15 Sent To I
Notes
2020-12-11 13:16:14CONTRACTOR SUBMITTED REVISED DESIGN PRESSURES
 ENGINEERING. JG.

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2020-08-27 Cont ID  
Sent By rmcphers Date 2020-08-27 Time 13:04 Rev Time 0.00
Received By rmcphers Date 2020-08-25 Time 14:31 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2020-08-04 Cont ID  
Sent By rmcphers Date 2020-08-04 Time 14:43 Rev Time 0.00
Received By rmcphers Date 2020-07-28 Time 16:47 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-07-17 Cont ID  
Sent By rmcphers Date 2020-07-17 Time 15:04 Rev Time 0.00
Received By rmcphers Date 2020-07-13 Time 11:11 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 4 Status P Date 2020-12-11 Cont ID  
Sent By jgomez Date 2020-12-11 Time 13:17 Rev Time 0.00
Received By jgomez Date 2020-12-11 Time 10:58 Sent To  
Notes
2020-12-11 13:18:05DESIGN PRESSURES WITH ENGINEER'S ORIGINAL
 SEAL/SIGNATURE. JG.

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 3 Status F Date 2020-08-27 Cont ID  
Sent By rmcphers Date 2020-08-27 Time 13:04 Rev Time 0.00
Received By rmcphers Date 2020-08-27 Time 13:04 Sent To  
Notes
2020-08-27 13:04:39SIGNED AND SEALED DRAWINGS IN PROJECTDOX NEED TO BE
 DIGITALLY/ELECTRONICALLY SIGNED BY THE ENGINEER OR
 ARCHITECT TO BE USED IN ELECTRONIC PLAN REVIEW.
 DRAWINGS DO NOT SHOW IN "ADOBE READER" AS
 DIGITALLY/ELECTRONICALLY SIGNED. - OR - IF YOUR
 ENGINEER DOES NOT HAVE AN ELECTRONIC OR DIGITAL
 SIGNATURE - PLEASE DROP OFF (CITY HALL DROP BOX) THE
 ORIGINAL SIGNED AND SEALED DRAWINGS/DOCUMENTS ALONG
 WITH A "PLAN REVIEW REQUEST FORM" EXPLAINING THE REASON
 FOR SUBMITTING THE DOCUMENT OR DRAWINGS. PLAN REVIEW
 REQUEST FORM CAN BE OBTAINED BY E MAILING [email protected]
 AND ASKING FOR THE FORM.

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status F Date 2020-08-04 Cont ID  
Sent By rmcphers Date 2020-08-04 Time 14:43 Rev Time 0.00
Received By rmcphers Date 2020-08-04 Time 14:43 Sent To  
Notes
2020-08-04 14:43:45SIGNED AND SEALED DRAWINGS IN PROJECTDOX NEED TO BE
 DIGITALLY/ELECTRONICALLY SIGNED BY THE ENGINEER OR
 ARCHITECT TO BE USED IN ELECTRONIC PLAN REVIEW.
 DRAWINGS DO NOT SHOW IN "ADOBE READER" AS
 DIGITALLY/ELECTRONICALLY SIGNED. - OR - IF YOUR
 ENGINEER OR ARCHITECT DOES NOT HAVE AN ELECTRONIC OR
 DIGITAL SIGNATURE - PLEASE DROP OFF (CITY HALL DROP
 BOX) THE ORIGINAL SIGNED AND SEALED DRAWINGS/DOCUMENTS
 ALONG WITH A "PLAN REVIEW REQUEST FORM" EXPLAINING THE
 REASON FOR SUBMITTING THE DOCUMENT OR DRAWINGS. PLAN
 REVIEW REQUEST FORM CAN BE OBTAINED BY E MAILING
 [email protected] AND ASKING FOR THE FORM

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2020-07-17 Cont ID  
Sent By rmcphers Date 2020-07-17 Time 15:04 Rev Time 0.00
Received By rmcphers Date 2020-07-17 Time 15:03 Sent To  
Notes
2020-07-17 15:04:20SEE BUILDING PLAN REVIEW