Plan Review Stops For Permit 20061023 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
3 |
Status |
P |
Date |
2020-08-04 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2020-08-04 |
Time |
15:02 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2020-08-04 |
Time |
15:02 |
Sent To |
|
|
Notes |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
P |
Date |
2020-07-15 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2020-07-15 |
Time |
10:31 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2020-07-15 |
Time |
10:31 |
Sent To |
|
|
Notes |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
F |
Date |
2020-07-01 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2020-07-01 |
Time |
08:44 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2020-07-01 |
Time |
08:44 |
Sent To |
|
|
Notes |
2020-07-01 08:47:37 | ROOFING | | REVIEWED BY ROGER MCPHERSON | | 561-805-6716 | | [email protected]. | | | | CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107 | | 1) DOCUMENT LABELED "ENGINEERING.PDF" IN PROJECTDOX = | | DRAWINGS/DOCUMENTS NEED TO BE DIGITALLY/ELECTRONICALLY | | SIGNED BY THE ENGINEER OR ARCHITECT TO BE USED IN | | ELECTRONIC PLAN REVIEW. DRAWINGS/DOCUMENTS DO NOT SHOW | | IN "ADOBE READER" AS DIGITALLY/ELECTRONICALLY SIGNED. | | 2) PLEASE PROVIDE THE PRODUCT APPROVAL LISTED ON THE | | ENGINEERING DOCUMENT LABELED "ENGINEERING.PDF" IN | | PROJECTDOX . |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
4 |
Status |
N |
Date |
2020-08-11 |
|
|
Cont ID |
|
Sent By |
jgomez |
Date |
2020-08-11 |
Time |
17:41 |
Rev Time |
0.00 |
Received By |
jgomez |
Date |
2020-08-10 |
Time |
14:30 |
Sent To |
I |
|
Notes |
2020-08-11 06:31:09 | SIGNATURE ROUTED TO S1 |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2020-08-04 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2020-08-04 |
Time |
15:11 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2020-07-30 |
Time |
07:32 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2020-07-15 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2020-07-15 |
Time |
10:34 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2020-07-09 |
Time |
10:37 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2020-07-01 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2020-07-01 |
Time |
08:48 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2020-06-29 |
Time |
10:12 |
Sent To |
|
|
Notes |
|
|
Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
Rev No |
4 |
Status |
P |
Date |
2020-08-11 |
|
|
Cont ID |
|
Sent By |
jgomez |
Date |
2020-08-11 |
Time |
17:22 |
Rev Time |
0.00 |
Received By |
jgomez |
Date |
2020-08-11 |
Time |
17:20 |
Sent To |
|
|
Notes |
2020-08-11 17:39:06 | RAS 117 CALCULATIONS SUBMITTED WITH ENGINEER'S ORIGINAL | | EMBOSSED SEAL AND SIGNATURE MATCH. SAME ENGINEER SAME | | CALCULATIONS. JG. |
|
|
Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
Rev No |
3 |
Status |
F |
Date |
2020-08-04 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2020-08-04 |
Time |
15:03 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2020-08-04 |
Time |
15:03 |
Sent To |
|
|
Notes |
2020-08-04 15:07:06 | DOCUMENT LABELED "ELECTRONICALLY SIGNED ENGINEERING.PDF | | " IN PROJECTDOX = DOES NOT NOT SHOW IN "ADOBE READER" | | AS DIGITALLY/ELECTRONICALLY SIGNED. - WHEN PRINTED OUT | | THE DIGITAL/ELECTRONIC SIGNATURE IS LOST - THEY MUST | | TRAVEL FROM COMPUTER TO COMPUTER (PROJECTDOX) - - - .OR | | - - - - PLEASE DROP OFF (CITY HALL DROP BOX) THE | | ORIGINAL SIGNED AND SEALED DRAWINGS/DOCUMENTS ALONG | | WITH A "PLAN REVIEW REQUEST FORM" EXPLAINING THE REASON | | FOR SUBMITTING THE DOCUMENT OR DRAWINGS. PLAN REVIEW | | REQUEST FORM CAN BE OBTAINED BY E MAILING [email protected] | | AND ASKING FOR THE FORM. | | | | |
|
|
Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
Rev No |
2 |
Status |
F |
Date |
2020-07-15 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2020-07-15 |
Time |
10:32 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2020-07-15 |
Time |
10:32 |
Sent To |
|
|
Notes |
2020-07-15 10:33:59 | DOCUMENT LABELED "ENGINEER LETTER.PDF" IN PROJECTDOX = | | SIGNED AND SEALED DRAWINGS IN PROJECTDOX NEED TO BE | | DIGITALLY/ELECTRONICALLY SIGNED BY THE ENGINEER OR | | ARCHITECT TO BE USED IN ELECTRONIC PLAN REVIEW. | | DRAWINGS DO NOT SHOW IN "ADOBE READER" AS | | DIGITALLY/ELECTRONICALLY SIGNED. - OR - IF YOUR | | ENGINEER DOES NOT HAVE AN ELECTRONIC OR DIGITAL | | SIGNATURE - PLEASE DROP OFF (CITY HALL DROP BOX) THE | | ORIGINAL SIGNED AND SEALED DRAWINGS/DOCUMENTS ALONG | | WITH A "PLAN REVIEW REQUEST FORM" EXPLAINING THE REASON | | FOR SUBMITTING THE DOCUMENT OR DRAWINGS. PLAN REVIEW | | REQUEST FORM CAN BE OBTAINED BY E MAILING [email protected] | | AND ASKING FOR THE FORM. (AT THIS TIME DROP BOX ITEMS | | MAY TAKE 2 TO 3 WEEKS TO PROCESS - DUE TO LIMITED STAFF | | INSIDE THE BUILDING DEPT.) |
|
|
Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
Rev No |
1 |
Status |
F |
Date |
2020-07-01 |
|
|
Cont ID |
|
Sent By |
rmcphers |
Date |
2020-07-01 |
Time |
08:47 |
Rev Time |
0.00 |
Received By |
rmcphers |
Date |
2020-07-01 |
Time |
08:47 |
Sent To |
|
|
Notes |
2020-07-01 08:48:05 | SEE BUILDING PLAN REVIEW |
|
|