Plan Review Stops For Permit 20051004 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
3 |
Status |
P |
Date |
2020-08-21 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2020-08-21 |
Time |
15:14 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2020-08-21 |
Time |
15:11 |
Sent To |
|
|
Notes |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
P |
Date |
2020-08-03 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2020-08-03 |
Time |
11:36 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2020-08-03 |
Time |
11:26 |
Sent To |
|
|
Notes |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
F |
Date |
2020-06-09 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2020-06-09 |
Time |
15:04 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2020-06-09 |
Time |
15:04 |
Sent To |
|
|
Notes |
2020-06-09 15:08:56 | PLAN | | REVIEW COMMENTS | | | | 1ST REVIEW: FBC SIXTH EDITION (2017) | | ROBERT MCDOUGAL, CBO | | COMMERCIAL COMBINATION PLANS EXAMINER | | (561) 805-6714 | | [email protected] | | | | DENIED BY BUILDING | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | 1) ONLY PART OF THE GENERATOR PAD DRAWING WAS UPLOADED. | | THE ENTIRE DOCUMENT IS REQUIRED. FBC 107 |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
P |
Date |
2020-06-18 |
|
|
Cont ID |
|
Sent By |
jleahy |
Date |
2020-06-18 |
Time |
13:51 |
Rev Time |
0.00 |
Received By |
jleahy |
Date |
2020-06-18 |
Time |
13:48 |
Sent To |
|
|
Notes |
|
|
Review Stop |
G |
GAS REVIEW |
Rev No |
1 |
Status |
P |
Date |
2020-06-16 |
|
|
Cont ID |
|
Sent By |
medwards |
Date |
2020-06-16 |
Time |
15:10 |
Rev Time |
0.00 |
Received By |
medwards |
Date |
2020-06-16 |
Time |
15:07 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2020-08-21 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2020-08-21 |
Time |
15:15 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2020-08-17 |
Time |
07:22 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2020-08-10 |
|
|
Cont ID |
|
Sent By |
cpuell |
Date |
2020-08-10 |
Time |
13:15 |
Rev Time |
0.00 |
Received By |
cpuell |
Date |
2020-07-22 |
Time |
16:47 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
|
|
|
Cont ID |
|
Sent By |
|
Date |
2020-08-17 |
Time |
|
Rev Time |
0.00 |
Received By |
lmarchan |
Date |
2020-06-01 |
Time |
15:50 |
Sent To |
|
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
N |
Date |
2020-06-16 |
|
|
Cont ID |
|
Sent By |
medwards |
Date |
2020-06-16 |
Time |
15:11 |
Rev Time |
0.00 |
Received By |
medwards |
Date |
2020-06-16 |
Time |
15:11 |
Sent To |
|
|
Notes |
|
|
Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
Rev No |
4 |
Status |
P |
Date |
2020-08-21 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2020-08-21 |
Time |
15:49 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2020-08-21 |
Time |
15:49 |
Sent To |
|
|
Notes |
2020-08-21 15:50:08 | PROVISO: SUBMIT ORIGINAL ENGINEERING | | (FPL APPT) |
|
|
Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
Rev No |
3 |
Status |
F |
Date |
2020-08-21 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2020-08-21 |
Time |
15:14 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2020-08-21 |
Time |
15:14 |
Sent To |
|
|
Notes |
2020-08-21 15:15:27 | ****CORRECTIONS**** | | | | SAMANTHA HILL | | BUILDING PLANS EXAMINER | | [email protected] | | 561-805-6724 | | | | DOCUMENTS PREPARED BY AN ENGINEER AND SUBMITTED FOR | | PUBLIC RECORD ARE TO BE SIGNED, SEALED, DATED | | ORIGINALS. A SCAN OF A WET SIGNATURE IS NOT CONSIDERED | | A DIGITAL SIGNATURE. | | | | EITHER UPLOAD A DIGITALLY SIGNED DOCUMENT OR DROP OFF | | (OR MAIL) ONE PAPER ORIGINAL: | | | | BUILDING DIVISION, FIRST FLOOR | | CITY OF WEST PALM BEACH | | 401 CLEMATIS ST | | WEST PALM BEACH, FL 33401 | | | | |
|
|
Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
Rev No |
2 |
Status |
F |
Date |
2020-08-03 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2020-08-03 |
Time |
11:36 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2020-08-03 |
Time |
11:27 |
Sent To |
|
|
Notes |
2020-08-03 11:43:28 | THE PREFAB GENERATOR PAD DRAWINGS THAT WERE SUBMITTED | | ELECTRONICALLY DO NOT HAVE THE ENGINEER'S DIGITAL | | SIGNATURE. THE CONTRACTOR HAS THE OPTION TO SUBMIT | | ELECTRONIC GENERATOR PAD DRAWINGS WITH THE ENGINEER'S | | DIGITAL SIGNATURE OR SUBMIT PAPER DRAWINGS AT THE CITY | | BUILDING DEPARTMENT WITH THE ENGINEER'S ORIGINAL | | HANDWRITTEN SIGNATURE AND SEAL FOR REVIEW AND APPROVAL | | BEFORE THE PERMIT CAN BE ISSUED. FS 471 AND FAC 61G 15. |
|
|
Review Stop |
SIGNATURE |
ELECTRONIC SIGNATURE SHEET |
Rev No |
1 |
Status |
F |
Date |
2020-06-16 |
|
|
Cont ID |
|
Sent By |
medwards |
Date |
2020-06-16 |
Time |
15:10 |
Rev Time |
0.00 |
Received By |
medwards |
Date |
2020-06-16 |
Time |
15:10 |
Sent To |
|
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
2 |
Status |
P |
Date |
2020-08-10 |
|
|
Cont ID |
|
Sent By |
rthermid |
Date |
2020-08-10 |
Time |
|
Rev Time |
0.00 |
Received By |
rthermid |
Date |
2020-08-10 |
Time |
|
Sent To |
I |
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
F |
Date |
2020-06-09 |
|
|
Cont ID |
|
Sent By |
rthermid |
Date |
2020-06-09 |
Time |
15:04 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2020-06-09 |
Time |
15:04 |
Sent To |
|
|
Notes |
|
|