Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2020-09-05 Cont ID  
Sent By pvalenti Date 2020-09-05 Time 11:49 Rev Time 0.00
Received By pvalenti Date 2020-09-05 Time 11:49 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2020-08-03 Cont ID  
Sent By rmcdouga Date 2020-08-03 Time 12:02 Rev Time 0.00
Received By rmcdouga Date 2020-08-03 Time 12:02 Sent To  
Notes
2020-08-03 12:10:25PLAN
 REVIEW COMMENTS
  
 2ND REVIEW: FBC SIXTH EDITION (2017)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1A) THE GENERATOR PAD THAT WAS UPLOADED ON 7/22 IS NOT
 FOR THE 27 KW, MODEL RG027 GENERATOR. THE ONE THAT WAS
 UPLOADED THE FIRST TIME IS THE CORRECT ONE. IT WAS JUST
 NOT THE COMPLETE SHEET. PART OF THE SHEET WAS CUT OFF.
 FBC 107 ALSO SEE SIGNATURE COMMENT.
  
 ORIGINAL COMMENT: 1) ONLY PART OF THE GENERATOR PAD
 DRAWING WAS UPLOADED. THE ENTIRE DOCUMENT IS REQUIRED.
 FBC 107

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2020-06-09 Cont ID  
Sent By rmcdouga Date 2020-06-09 Time 16:10 Rev Time 0.00
Received By rmcdouga Date 2020-06-09 Time 16:10 Sent To  
Notes
2020-06-09 16:10:37PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC SIXTH EDITION (2017)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) ONLY PART OF THE GENERATOR PAD DRAWING WAS UPLOADED.
 THE ENTIRE DOCUMENT IS REQUIRED. FBC 107

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2020-06-18 Cont ID  
Sent By jleahy Date 2020-06-18 Time 13:45 Rev Time 0.00
Received By jleahy Date 2020-06-18 Time 13:45 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 3 Status P Date 2020-08-26 Cont ID  
Sent By lcrespo Date 2020-08-26 Time 16:30 Rev Time 0.00
Received By lcrespo Date 2020-08-26 Time 16:15 Sent To  
Notes
2020-08-26 16:30:5608/26/20 REVIEWED FOR CODE COMPLIANCE (GAS)
  
 BY REVIEWING THE PLANS / SPECIFICATIONS FOR CODE
 COMPLIANCE DOES NOT RELIEVE THE OWNER, DESIGN
 PROFESSIONAL, CONTRACTORS OR THEIR REPRESENTATIVES FROM
 THE RESPONSIBILITY TO COMPLY WITH ALL LOCAL, STATE AND
 NATIONAL CODES AND STANDARDS IN EFFECT AT THE TIME OF
 PERMIT ISSUANCE. OUR REVIEW IS NOT A CHECK OF EVERY
 ITEM AND DOES NOT PREVENT THIS DEPARTMENT FROM
 REQUIRING CORRECTIONS DURING CONSTRUCTION. ANY CHANGES
 / ALTERATIONS TO APPROVED PLANS SHALL BE APPROVED TO
 AVOID VOIDING OF THE PERMIT.
  
 LUIS A. CRESPO
 PLUMBING PLAN EXAMINER / INSPECTOR
 EMAIL: [email protected] OFFICE: 561 805-6720
  

Review Stop G GAS REVIEW
Rev No 2 Status F Date 2020-07-30 Cont ID  
Sent By lcrespo Date 2020-07-30 Time 16:59 Rev Time 0.00
Received By lcrespo Date 2020-07-30 Time 16:59 Sent To  
Notes
2020-07-30 16:59:4207/30/20 2ND GAS/ REVIEW **DENIED** WITH COMMENTS
  
 NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS
 TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE
 GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS.
  
 1. PLEASE SHOW ALL UNIONS IN FRONT OF REGULATOR 1' OF
 EITHER SIDE PER THE 2017 FBC RES. SEC G2421.2.
  
 2. PLEASE SHOW AND LABEL DRIP LEG ON EQUIPMENT
 INSTALLED IF INSIDE GENERATOR MAKE NOTE PER THE 2017
 FBC RES. SEC. G2419.2.
  
 3. PLEASE SHOW THE SHUTOFF VALVE ON GAS ISOMERIC PER
 THE 2017 FBC FG SEC. 409.4 OR 2017 FBC RES. SEC.
 G2401.1.3.
  
 4. PLEASE SHOW AND LABEL THE REGULATOR ON GAS ISOMERIC
 PER THE 2017 FBC FG SEC. 409.4 OR 2017 FBC RES. SEC.
 G2401.1.3.
  
 5. PLEASE SHOW THE PE LINES ON THE SIDE OF EXIT ON THE
 METER NOT THE INLET PER THE WPB AMENDMENTS TO THE FBC
 SEC. 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
 6. THE GENERATOR ON THE ISOMETRIC SAYS 27 KW, PLEASE
 CHANGE TO BTU'S AND BELOW YOU HAVE 330 BTU'S WHICH AT
 FULL LOAD A 27 KW SHOULD BE 359 BTU'S SO RECALCULATE
 AND CHANGE TOTAL BTU'S PER THE WPB AMENDMENTS TO THE
 FBC SEC. 107.2.1 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
 WHEN RESUBMITTING PLANS PLEASE INDICATE THE REVISION &
 REMOVE ANY VOIDED SHEETS & REPLACE ANY PAGES AS
 NECESSARY. A TRANSMITTAL LETTER LISTING THE ORIGINAL
 REVIEW COMMENT NUMBER, WITH A DESCRIPTION OF THE
 REVISION, MADE, IDENTIFYING THE SHEET OR SPECIFICATION
 PAGE WHERE THE CHANGES CAN BE FOUND WILL HELP TO
 EXPEDITE YOUR PERMIT. THANK YOU FOR YOUR ANTICIPATED
 COOPERATION.
  
 LUIS A. CRESPO
 PLUMBING INSPECTOR /
 PLUMBING PLAN REVIEW
 AVAILABLE FROM 6:30 AM 7:30 / 2:00 PM TO 5:00 PM
 [email protected]
 561-701-6437
  

Review Stop G GAS REVIEW
Rev No 1 Status F Date 2020-06-12 Cont ID  
Sent By medwards Date 2020-06-12 Time 14:55 Rev Time 0.00
Received By medwards Date 2020-06-12 Time 14:25 Sent To  
Notes
2020-06-12 14:55:471ST REVIEW FBC-2017 MECHANICAL
 PERMIT-20050996
  
 CODES IN EFFECT:
  
 FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017
 FBC RES- FLORIDA RESIDENTIAL BUILDING CODE SIXTH
 EDITION 2017
 FS- FLORIDA STATUTES
 FAC- FLORIDA ADMINISTRATIVE CODE
 WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH
 EDITION 2017
  
 PLAN REVIEW RESULTS: DENIED.
  
 1) . THIS SUBMISSION DOES NOT SHOW ANY EXISTING GAS
 LINE FOR THIS PROJECT. PLEASE PROVIDE A COMPLETE GAS
 LINE DIAGRAM SHOWING ALL THE EXISTING APPLIANCES AND
 GAS LINES. INCLUDE PIPE MATERIAL AND PIPE SIZES ALONG
 WITH ANY REGULATORS AND GAS PRESSURES FOR THE ENTIRE
 SYSTEM. PLEASE SHOW A DETAIL OF THE CONNECTION OF THE
 NEW GAS LINE FOR THE GENERATOR TO THE EXISTING GAS
 LINE.
  
  
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT
 CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE OLD
 SHEETS FROM THE PLAN SETS, BIND THEM TOGETHER
 SEPARATELY AND MARK VOID OR OLD ON THEM. PLEASE RETAIN
 THEM FOR REFERENCE WITH THE NEW SUBMITTED PLANS. THIS
 PROCESS WILL ALSO APPLY TO ANY DOCUMENTS SUCH AS
 PRODUCT APPROVALS OR CALCULATIONS BEING REPLACED OR
 UPDATED.
  
  
 MICHAEL EDWARDS
 MECHANICAL EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL. 33401
 561-805-6728
 [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2020-09-05 Cont ID  
Sent By pvalenti Date 2020-09-05 Time 11:50 Rev Time 0.00
Received By pvalenti Date 2020-08-21 Time 09:15 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2020-08-03 Cont ID  
Sent By rmcdouga Date 2020-08-03 Time 12:13 Rev Time 0.00
Received By rmcdouga Date 2020-07-22 Time 16:46 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-06-18 Cont ID  
Sent By jleahy Date 2020-06-18 Time 13:45 Rev Time 0.00
Received By jleahy Date 2020-06-01 Time 15:59 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 3 Status P Date 2020-08-26 Cont ID  
Sent By lcrespo Date 2020-08-26 Time 16:30 Rev Time 0.00
Received By lcrespo Date 2020-08-26 Time 16:15 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status N Date 2020-07-30 Cont ID  
Sent By lcrespo Date 2020-07-30 Time 16:59 Rev Time 0.00
Received By lcrespo Date 2020-07-30 Time 16:59 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status N Date 2020-06-12 Cont ID  
Sent By medwards Date 2020-06-12 Time 14:56 Rev Time 0.00
Received By medwards Date 2020-06-12 Time 14:56 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 3 Status P Date 2020-09-05 Cont ID  
Sent By pvalenti Date 2020-09-05 Time 11:49 Rev Time 0.00
Received By pvalenti Date 2020-09-05 Time 11:49 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status F Date 2020-08-03 Cont ID  
Sent By rmcdouga Date 2020-08-03 Time 12:10 Rev Time 0.00
Received By rmcdouga Date 2020-08-03 Time 12:10 Sent To  
Notes
2020-08-03 12:13:18THE PREFAB GENERATOR PAD DRAWINGS THAT WERE SUBMITTED
 ELECTRONICALLY DO NOT HAVE THE ENGINEER'S DIGITAL
 SIGNATURE. THE CONTRACTOR HAS THE OPTION TO SUBMIT
 ELECTRONIC GENERATOR PAD DRAWINGS WITH THE ENGINEER'S
 DIGITAL SIGNATURE OR SUBMIT PAPER DRAWINGS AT THE CITY
 BUILDING DEPARTMENT WITH THE ENGINEER'S ORIGINAL
 HANDWRITTEN SIGNATURE AND SEAL FOR REVIEW AND APPROVAL
 BEFORE THE PERMIT CAN BE ISSUED. FS 471 AND FAC 61G 15.

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2020-06-09 Cont ID  
Sent By rmcdouga Date 2020-06-09 Time 16:10 Rev Time 0.00
Received By rmcdouga Date 2020-06-09 Time 16:10 Sent To  
Notes
2020-06-09 16:12:01THE ENGINEER'S DIGITAL SIGNATURE IS REQUIRED ON THE
 GENERATOR PAD DRAWING. FS471 & FAC 61G15

Review Stop Z ZONING
Rev No 1 Status P Date 2020-06-11 Cont ID  
Sent By kalexand Date 2020-06-11 Time   Rev Time  
Received By kalexand Date 2020-06-11 Time   Sent To I
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy