Plan Review Details - Permit 20050306
Plan Review Stops For Permit 20050306
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2020-11-30 Cont ID  
Sent By rmcphers Date 2020-11-30 Time 10:00 Rev Time 0.00
Received By rmcphers Date 2020-11-30 Time 10:00 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 3 Status P Date 2021-02-10 Cont ID  
Sent By jleahy Date 2021-02-10 Time 16:36 Rev Time 0.00
Received By jleahy Date 2021-02-10 Time 16:35 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 2 Status F Date 2021-01-14 Cont ID  
Sent By jleahy Date 2021-01-14 Time 09:12 Rev Time 0.00
Received By jleahy Date 2021-01-14 Time 09:11 Sent To  
Notes
2021-01-14 09:13:40SEE COMMENTS FROM 12/7/20 REVIEW JLEAHY

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2020-12-07 Cont ID  
Sent By jleahy Date 2020-12-07 Time 14:24 Rev Time 0.00
Received By jleahy Date 2020-12-07 Time 14:24 Sent To  
Notes
2020-12-07 14:26:45ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW.
  
 FLORIDA BUILDING CODE 2017 6TH EDITION
 FLORIDA BUILDING CODE ENERGY CONSERVATION 2017 6TH ED
 NFPA 70 2014 EDITION
  
 JAKE LEAHY BN, BU, PX
 ELECTRICAL PLANS EXAMINER II
 561-805-6713
 [email protected]
  
 NO WIRE SIZES OR BREAKER SIZES SHOWN ON PLANS 215.5
  
 PLANS TO BE SEALED BY AN ENGINEER (480V)

Review Stop FIRE FIRE DEPARTMENT
Rev No 3 Status P Date 2021-02-02 Cont ID  
Sent By pleduc Date 2021-02-02 Time   Rev Time 0.00
Received By pleduc Date 2021-02-02 Time 11:32 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status F Date 2021-01-06 Cont ID  
Sent By pleduc Date 2021-01-06 Time   Rev Time 0.00
Received By pleduc Date 2021-01-06 Time 10:35 Sent To  
Notes
2021-01-06 10:42:30FIRE COMMENTS PREVIOUSLY SUBMITTED DO NOT APPEAR TO BE
 SPECIFICALLY ADDRESSED OR PROVIDED WITH SPECIFIC DETAIL
 ON THIS RESUBMITTAL.
  
 THE PREVIOUS FIRE COMMENTS ARE RE-SUBMITTED BELOW:
  
  
 THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE
 MARSHAL, WITH THE FOLLOWING COMMENTS:
  
  
 1) THERE NO INDICATIONS OF EXHAUST PIPING/TUBING
  
 PER NFPA 110
  
 CHAPTER 1 ADMINISTRATION
 1.1 SCOPE. THIS STANDARD CONTAINS REQUIREMENTS COVERING
 THE
 PERFORMANCE OF EMERGENCY AND STANDBY POWER SYSTEMS
 PROVIDING
 AN ALTERNATE SOURCE OF ELECTRICAL POWER TO LOADS IN
 BUILDINGS
 AND FACILITIES IN THE EVENT THAT THE PRIMARY POWER
 SOURCE
 FAILS.
 1.1.1 POWER SYSTEMS COVERED IN THIS STANDARD INCLUDE
 POWER
 SOURCES, TRANSFER EQUIPMENT, CONTROLS, SUPERVISORY
 EQUIPMENT,
 AND ALL RELATED ELECTRICAL AND MECHANICAL AUXILIARY AND
 ACCESSORY
 EQUIPMENT NEEDED TO SUPPLY ELECTRICAL POWER TO THE LOAD
 TERMINALS OF THE TRANSFER EQUIPMENT.
 1.1.2 THIS STANDARD COVERS INSTALLATION, MAINTENANCE,
 OPERATION,
 AND TESTING REQUIREMENTS AS THEY PERTAIN TO THE
 PERFORMANCE
 OF THE EMERGENCY POWER SUPPLY SYSTEM (EPSS).
  
 7.10 EXHAUST SYSTEM.
 7.10.1 THE EXHAUST SYSTEM EQUIPMENT AND INSTALLATION,
 INCLUDING
 PIPING, MUFFLER, AND RELATED ACCESSORIES, SHALL BE IN
 ACCORDANCE WITH NFPA37, STANDARD FOR THE INSTALLATION
 AND USE OF
 STATIONARY COMBUSTION ENGINES AND GAS TURBINES, AND
 OTHER APPLICABLE
 STANDARDS.
 7.10.2 EXHAUST SYSTEM INSTALLATION SHALL BE GASTIGHT TO
 PREVENT
 EXHAUST GAS FUMES FROM ENTERING INHABITED ROOMS OR
 BUILDINGS
 AND TERMINATE IN SUCH A MANNER THAT TOXIC FUMES CANNOT
 REENTER A BUILDING OR STRUCTURE, PARTICULARLY THROUGH
 WINDOWS,
 AIR VENTILATION INLETS, OR THE ENGINE AIR-INTAKE
 SYSTEM.
 7.10.3* EXHAUST PIPING SHALL BE CONNECTED TO THE PRIME
 MOVER
 BY MEANS OF A FLEXIBLE CONNECTOR AND SHALL BE
 INDEPENDENTLY
 SUPPORTED THEREAFTER SO THAT NO DAMAGING WEIGHT OR
 STRESS IS
 APPLIED TO THE ENGINE EXHAUST MANIFOLD OR TURBOCHARGER.
 7.10.3.1 A CONDENSATE TRAP AND DRAIN VALVE SHALL BE
 PROVIDED
 AT THE LOW POINT(S) OF THE PIPING UNLESS THE PIPING IS
 SELFDRAINING.
  
 NFPA 37
  
 8.3 CLEARANCE FROM EXHAUST SYSTEMS WITH EXHAUST GAS
 TEMPERATURES
 OF LESS THAN 760?C (1400?F).
 8.3.1 EXHAUST PIPES AND DUCTS SHALL HAVE CLEARANCES OF
 AT LEAST
 225 MM (9 IN.) TO ADJACENT COMBUSTIBLE MATERIALS,
 EXCEPT AS
 SPECIFIED IN 8.3.2 AND 8.3.3. THE CLEARANCE SHALL BE
 MEASURED
 FROM THE OUTSIDE SURFACE OF THE EXHAUST PIPE OR DUCT
 AND NOT
 FROM ANY INSULATION THAT MIGHT BE PRESENT.
 8.3.2 EXHAUST PIPES AND DUCTS PASSING DIRECTLY THROUGH
 COMBUSTIBLE
 ROOFS SHALL BE GUARDED AT THE POINT OF PASSAGE BY
 VENTILATED
 METAL THIMBLES THAT EXTEND NOT LESS THAN 225MM(9 IN.)
 ON EACH SIDE (ABOVE AND BELOW) OF ROOF CONSTRUCTION AND
 ARE
 AT LEAST 150 MM (6 IN.) IN DIAMETER LARGER THAN THE
 EXHAUST
 PIPE OR DUCT.
 8.3.3 EXHAUST PIPES AND DUCTS PASSING DIRECTLY THROUGH
 COMBUSTIBLE
 WALLS OR PARTITIONS SHALL BE GUARDED AT THE POINT OF
 PASSAGE BY ONE OF THE FOLLOWING METHODS:
  
 (1) METAL VENTILATED THIMBLES NOT LESS THAN 300 MM (12
 IN.)
 LARGER IN DIAMETER THAN THE EXHAUST PIPE OR DUCT
 (2) METAL OR BURNED FIRE CLAY THIMBLES CONSTRUCTED OF
 BRICKWORK
 OR OTHER APPROVED FIREPROOFING MATERIALS PROVIDING
 NOT LESS THAN 200 MM (8 IN.) OF INSULATION BETWEEN THE
 THIMBLE AND COMBUSTIBLE MATERIAL
  
 PLEASE REVIEW AND PROVIDE DETAILS.
  
  
  
  
 2) THERE ARE INDICATIONS OF A FUEL TANK; HOWEVER, THERE
 ARE NO INDICATIONS OF FUEL LINE LOCATIONS AND/OR IF
 THEY BREACH FIRE RATED WALLS.
  
 PLEASE PROVIDE DETAILS.
  
  
  
 2A) THERE IS AN INDICATION OF A FUEL TANK; HOWEVER,
 THERE ARE NO INDICATIONS OF THE CLEARANCE DIMENSIONS
 AROUND THE TANK.
  
 PER NFPA 110
  
 7.9.12.1 A MINIMUM CLEARANCE OF 0.9 M (36 IN.) SHALL BE
 MAINTAINED ON ALL SIDES.
  
 PLEASE PROVIDE DETAILS.
  
  
  
 3) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET
 REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE
 ABOVE.
  
  
  
 4) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE
 RE-SUBMITTAL OF THE ABOVE.
  
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status F Date 2020-11-18 Cont ID  
Sent By pleduc Date 2020-11-18 Time   Rev Time 0.00
Received By pleduc Date 2020-11-18 Time 16:02 Sent To  
Notes
2020-11-18 16:24:04THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE
 MARSHAL, WITH THE FOLLOWING COMMENTS:
  
  
 1) THERE NO INDICATIONS OF EXHAUST PIPING/TUBING
  
 PER NFPA 110
  
 CHAPTER 1 ADMINISTRATION
 1.1 SCOPE. THIS STANDARD CONTAINS REQUIREMENTS COVERING
 THE
 PERFORMANCE OF EMERGENCY AND STANDBY POWER SYSTEMS
 PROVIDING
 AN ALTERNATE SOURCE OF ELECTRICAL POWER TO LOADS IN
 BUILDINGS
 AND FACILITIES IN THE EVENT THAT THE PRIMARY POWER
 SOURCE
 FAILS.
 1.1.1 POWER SYSTEMS COVERED IN THIS STANDARD INCLUDE
 POWER
 SOURCES, TRANSFER EQUIPMENT, CONTROLS, SUPERVISORY
 EQUIPMENT,
 AND ALL RELATED ELECTRICAL AND MECHANICAL AUXILIARY AND
 ACCESSORY
 EQUIPMENT NEEDED TO SUPPLY ELECTRICAL POWER TO THE LOAD
 TERMINALS OF THE TRANSFER EQUIPMENT.
 1.1.2 THIS STANDARD COVERS INSTALLATION, MAINTENANCE,
 OPERATION,
 AND TESTING REQUIREMENTS AS THEY PERTAIN TO THE
 PERFORMANCE
 OF THE EMERGENCY POWER SUPPLY SYSTEM (EPSS).
  
 7.10 EXHAUST SYSTEM.
 7.10.1 THE EXHAUST SYSTEM EQUIPMENT AND INSTALLATION,
 INCLUDING
 PIPING, MUFFLER, AND RELATED ACCESSORIES, SHALL BE IN
 ACCORDANCE WITH NFPA37, STANDARD FOR THE INSTALLATION
 AND USE OF
 STATIONARY COMBUSTION ENGINES AND GAS TURBINES, AND
 OTHER APPLICABLE
 STANDARDS.
 7.10.2 EXHAUST SYSTEM INSTALLATION SHALL BE GASTIGHT TO
 PREVENT
 EXHAUST GAS FUMES FROM ENTERING INHABITED ROOMS OR
 BUILDINGS
 AND TERMINATE IN SUCH A MANNER THAT TOXIC FUMES CANNOT
 REENTER A BUILDING OR STRUCTURE, PARTICULARLY THROUGH
 WINDOWS,
 AIR VENTILATION INLETS, OR THE ENGINE AIR-INTAKE
 SYSTEM.
 7.10.3* EXHAUST PIPING SHALL BE CONNECTED TO THE PRIME
 MOVER
 BY MEANS OF A FLEXIBLE CONNECTOR AND SHALL BE
 INDEPENDENTLY
 SUPPORTED THEREAFTER SO THAT NO DAMAGING WEIGHT OR
 STRESS IS
 APPLIED TO THE ENGINE EXHAUST MANIFOLD OR TURBOCHARGER.
 7.10.3.1 A CONDENSATE TRAP AND DRAIN VALVE SHALL BE
 PROVIDED
 AT THE LOW POINT(S) OF THE PIPING UNLESS THE PIPING IS
 SELFDRAINING.
  
 NFPA 37
  
 8.3 CLEARANCE FROM EXHAUST SYSTEMS WITH EXHAUST GAS
 TEMPERATURES
 OF LESS THAN 760?C (1400?F).
 8.3.1 EXHAUST PIPES AND DUCTS SHALL HAVE CLEARANCES OF
 AT LEAST
 225 MM (9 IN.) TO ADJACENT COMBUSTIBLE MATERIALS,
 EXCEPT AS
 SPECIFIED IN 8.3.2 AND 8.3.3. THE CLEARANCE SHALL BE
 MEASURED
 FROM THE OUTSIDE SURFACE OF THE EXHAUST PIPE OR DUCT
 AND NOT
 FROM ANY INSULATION THAT MIGHT BE PRESENT.
 8.3.2 EXHAUST PIPES AND DUCTS PASSING DIRECTLY THROUGH
 COMBUSTIBLE
 ROOFS SHALL BE GUARDED AT THE POINT OF PASSAGE BY
 VENTILATED
 METAL THIMBLES THAT EXTEND NOT LESS THAN 225MM(9 IN.)
 ON EACH SIDE (ABOVE AND BELOW) OF ROOF CONSTRUCTION AND
 ARE
 AT LEAST 150 MM (6 IN.) IN DIAMETER LARGER THAN THE
 EXHAUST
 PIPE OR DUCT.
 8.3.3 EXHAUST PIPES AND DUCTS PASSING DIRECTLY THROUGH
 COMBUSTIBLE
 WALLS OR PARTITIONS SHALL BE GUARDED AT THE POINT OF
 PASSAGE BY ONE OF THE FOLLOWING METHODS:
  
 (1) METAL VENTILATED THIMBLES NOT LESS THAN 300 MM (12
 IN.)
 LARGER IN DIAMETER THAN THE EXHAUST PIPE OR DUCT
 (2) METAL OR BURNED FIRE CLAY THIMBLES CONSTRUCTED OF
 BRICKWORK
 OR OTHER APPROVED FIREPROOFING MATERIALS PROVIDING
 NOT LESS THAN 200 MM (8 IN.) OF INSULATION BETWEEN THE
 THIMBLE AND COMBUSTIBLE MATERIAL
  
 PLEASE REVIEW AND PROVIDE DETAILS.
  
  
  
  
 2) THERE ARE INDICATIONS OF A FUEL TANK; HOWEVER, THERE
 ARE NO INDICATIONS OF FUEL LINE LOCATIONS AND/OR IF
 THEY BREACH FIRE RATED WALLS.
  
 PLEASE PROVIDE DETAILS.
  
  
  
 2A) THERE IS AN INDICATION OF A FUEL TANK; HOWEVER,
 THERE ARE NO INDICATIONS OF THE CLEARANCE DIMENSIONS
 AROUND THE TANK.
  
 PER NFPA 110
  
 7.9.12.1 A MINIMUM CLEARANCE OF 0.9 M (36 IN.) SHALL BE
 MAINTAINED ON ALL SIDES.
  
 PLEASE PROVIDE DETAILS.
  
  
  
 3) WHEN RESUBMITTING, PLEASE PROVIDE PLAN SHEET
 REVISION CLOUDS OR NUMBERED NARRATIVE RESPONSES TO THE
 ABOVE.
  
  
  
 4) ADDITIONAL COMMENTS MAY BE PROVIDED ON THE
 RE-SUBMITTAL OF THE ABOVE.
  
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2021-02-23 Cont ID  
Sent By medwards Date 2021-02-23 Time 07:19 Rev Time 0.00
Received By medwards Date 2021-02-19 Time 14:39 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2021-02-10 Cont ID  
Sent By jleahy Date 2021-02-10 Time 16:36 Rev Time 0.00
Received By jleahy Date 2021-02-01 Time 20:06 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2021-01-14 Cont ID  
Sent By jleahy Date 2021-01-14 Time 09:28 Rev Time 0.00
Received By jleahy Date 2021-01-04 Time 13:24 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-12-07 Cont ID  
Sent By jleahy Date 2020-12-07 Time 14:26 Rev Time 0.00
Received By jleahy Date 2020-11-17 Time 11:34 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 4 Status P Date 2021-02-23 Cont ID  
Sent By hmoser Date 2021-02-23 Time 06:57 Rev Time 0.00
Received By medwards Date 2021-02-23 Time 05:51 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 3 Status F Date 2021-02-04 Cont ID  
Sent By medwards Date 2021-02-04 Time 11:17 Rev Time 0.00
Received By medwards Date 2021-02-04 Time 10:02 Sent To  
Notes
2021-02-04 11:18:321ST REVIEW FBC-2020 MECHANICAL
 PERMIT-20050306
  
 CODES IN EFFECT:
  
 FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2020
 FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2020
 FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION
 2020
 FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2020
 FBC EX- FLORIDA EXISTING BUILDING CODE SIXTH EDITION
 2020
 FBC RES- FLORIDA RESIDENTIAL BUILDING CODE SIXTH
 EDITION 2020
 FS- FLORIDA STATUTES
 FAC- FLORIDA ADMINISTRATIVE CODE
 WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH
 EDITION 2020
  
 PLAN REVIEW RESULTS: DENIED.
  
 1) PLEASE SHOW THE GENERATOR INSIDE THE GENERATOR ROOM,
 PLEASE SHOW THE EXHAUST FROM THE GENERATOR AND THE WALL
 IT IS EXHAUSTING OUT OF. FBC 107.2.1
  
 2) PLEASE PROVIDE A DETAILED DRAWING SHOWING THE FUEL
 PIPING SYSTEM INCLUDING FROM TANK TO GENERATOR. ALSO
 SHOW THE FILL PIPING LOCATION ALONG WITH THE VENT
 PIPING AND TERMINATION LOCATION. FBC M 1305.6, 1305.7
  
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT
 CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE OLD
 SHEETS FROM THE PLAN SETS, BIND THEM TOGETHER
 SEPARATELY AND MARK VOID OR OLD ON THEM. PLEASE RETAIN
 THEM FOR REFERENCE WITH THE NEW SUBMITTED PLANS. THIS
 PROCESS WILL ALSO APPLY TO ANY DOCUMENTS SUCH AS
 PRODUCT APPROVALS OR CALCULATIONS BEING REPLACED OR
 UPDATED.
  
 MICHAEL EDWARDS
 MECHANICAL EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL. 33401
 561-805-6728
 [email protected]
  

Review Stop M MECHANICAL (A/C)
Rev No 2 Status F Date 2021-01-11 Cont ID  
Sent By medwards Date 2021-01-11 Time 13:36 Rev Time 0.00
Received By medwards Date 2021-01-11 Time 12:44 Sent To  
Notes
2021-01-11 13:37:30PLEASE SEE FIRE REVIEWERS COMMENTS. ME

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2020-11-24 Cont ID  
Sent By medwards Date 2020-11-24 Time 07:21 Rev Time 0.00
Received By medwards Date 2020-11-24 Time 07:18 Sent To  
Notes
2020-11-24 07:21:251ST REVIEW FBC-2017 MECHANICAL
 PERMIT-20050306
  
 CODES IN EFFECT:
  
 FBC B- FLORIDA BUILDING CODE SIXTH EDITION 2017
 FBC M- FLORIDA MECHANICAL CODE SIXTH EDITION 2017
 FBC EC- FLORIDA ENERGY CONSERVATION CODE SIXTH EDITION
 2017
 FBC FG- FLORIDA FUEL GAS CODE SIXTH EDITION 2017
 FBC EX- FLORIDA EXISTING BUILDING CODE SIXTH EDITION
 2017
 FBC RES- FLORIDA RESIDENTIAL BUILDING CODE SIXTH
 EDITION 2017
 FS- FLORIDA STATUTES
 FAC- FLORIDA ADMINISTRATIVE CODE
 WPB- WEST PALM BEACH AMENDMENTS TO THE FBC SIXTH
 EDITION 2017
  
 PLAN REVIEW RESULTS: DENIED.
  
 1) PLEASE PROVIDE A DETAIL DRAWING OF THE GENERATOR
 ROOM WITH THE EXHAUST DETAILS FOR THIS GENERATOR AND
 THE VENTILATION DETAILS OF THIS GENERATOR ROOM. FBC
 107.2
  
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT
 CORRECTED PLAN SHEETS INTO THE SETS, REMOVE THE OLD
 SHEETS FROM THE PLAN SETS, BIND THEM TOGETHER
 SEPARATELY AND MARK VOID OR OLD ON THEM. PLEASE RETAIN
 THEM FOR REFERENCE WITH THE NEW SUBMITTED PLANS. THIS
 PROCESS WILL ALSO APPLY TO ANY DOCUMENTS SUCH AS
 PRODUCT APPROVALS OR CALCULATIONS BEING REPLACED OR
 UPDATED.
  
 MICHAEL EDWARDS
 MECHANICAL EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL. 33401
 561-805-6728
 [email protected]
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 4 Status P Date 2021-02-23 Cont ID  
Sent By medwards Date 2021-02-23 Time 07:16 Rev Time 0.00
Received By medwards Date 2021-02-23 Time 07:16 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 3 Status F Date 2021-02-04 Cont ID  
Sent By medwards Date 2021-02-04 Time 11:20 Rev Time 0.00
Received By medwards Date 2021-02-04 Time 11:20 Sent To  
Notes
2021-02-04 11:23:13PLEASE PROVIDE DIGITALLY SIGNED SEALED AND THIRD PARTY
 CERTIFIED DIGITAL DRAWINGS FROM THE ENGINEER. DRAWINGS
 CREATED BY COMPANY'S MUST HAVE A TITLE BLOCK WITH THE
 DESIGNERS NAME AND SIGNATURE INCLUDED IN THE TITLE
 BLOCK.
  
 PER THE WPB AMENDMENTS TO THE FBC, EACH SHEET OF PLAN
 (INCLUDING THE SUPPORTING DOCUMENTS) IS REQUIRED TO BE
 SIGNED AND SEALED BY THE PERSON RESPONSIBLE FOR THE
 DESIGN. A DIGITAL PLAN REQUIRES A DIGITAL SIGNATURE
 WITH THE PROPER THIRD PARTY VERIFICATION. PROVIDE
 CORRECTION. ALTERNATIVELY, A SIGNED/SEALED PAPER SET
 MAY BE SUPPLIED TO THE BUILDING DEPARTMENT WHEN ALL
 TRADES ARE APPROVED. WPB FBC 107.1; FS 471/481
  
 MICHAEL EDWARDS
 MECHANICAL EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL. 33401
 561-805-6728
 [email protected]
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status F Date 2021-01-11 Cont ID  
Sent By medwards Date 2021-01-11 Time 13:46 Rev Time 0.00
Received By medwards Date 2021-01-11 Time 13:45 Sent To  
Notes
2021-01-11 13:47:28PER THE WPB AMENDMENTS TO THE FBC, EACH SHEET OF PLAN
 (INCLUDING THE SUPPORTING DOCUMENTS) IS REQUIRED TO BE
 SIGNED AND SEALED BY THE PERSON RESPONSIBLE FOR THE
 DESIGN. A DIGITAL PLAN REQUIRES A DIGITAL SIGNATURE
 WITH THE PROPER THIRD PARTY VERIFICATION. PROVIDE
 CORRECTION. ALTERNATIVELY, A SIGNED/SEALED PAPER SET
 MAY BE SUPPLIED TO THE BUILDING DEPARTMENT WHEN ALL
 TRADES ARE APPROVED. WPB FBC 107.1; FS 471/481
  
 61G15?23.004 F.A.C.
 (2) A PROFESSIONAL ENGINEER UTILIZING A DIGITAL
 SIGNATURE TO ELECTRONICALLY SIGN AND SEAL ENGINEERING
 PLANS, SPECIFICATIONS, REPORTS OR OTHER DOCUMENTS SHALL
 HAVE THEIR IDENTITY AUTHENTICATED BY A CERTIFICATION
 AUTHORITY AND SHALL ASSURE THAT THE DIGITAL SIGNATURE
 IS: (A) UNIQUE TO THE PERSON USING IT; (B) CAPABLE OF
 VERIFICATION; AS OF NOVEMBER 16, 2020 63 (C) UNDER THE
 SOLE CONTROL OF THE PERSON USING IT; AND, (D) LINKED TO
 A DOCUMENT IN SUCH A MANNER THAT THE DIGITAL SIGNATURE
 AND CORRESPONDINGLY THE DOCUMENT IS INVALIDATED IF ANY
 DATA IN THE DOCUMENT IS CHANGED.
  
 MICHAEL EDWARDS
 MECHANICAL EXAMINER
 401 CLEMATIS STREET
 WEST PALM BEACH FL. 33401
 561-805-6728
 [email protected]
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status N Date 2020-11-30 Cont ID  
Sent By rmcphers Date 2020-11-30 Time 10:22 Rev Time 0.00
Received By rmcphers Date 2020-11-30 Time 10:22 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2020-12-03 Cont ID  
Sent By aaponte Date 2020-12-03 Time 09:03 Rev Time 0.00
Received By aaponte Date 2020-12-03 Time 09:03 Sent To  
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved