Plan Review Details - Permit 20050214
Plan Review Stops For Permit 20050214
Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2020-07-30 Cont ID  
Sent By rmcphers Date 2020-07-30 Time 08:17 Rev Time 0.00
Received By rmcphers Date 2020-07-30 Time 08:17 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2020-07-21 Cont ID  
Sent By rmcphers Date 2020-07-21 Time 07:50 Rev Time 0.00
Received By rmcphers Date 2020-07-21 Time 07:49 Sent To  
Notes
2020-07-21 07:56:58GENERATOR
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected].
 CODE USED FOR REVIEW - 2017 FBC WITH WPB CHAPTER 1
 AMENDMENTS
  
 CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107
 1) THE REVISED GENERATOR PAD DRAWING HAS A LIST OF
 GENERATORS AND THEIR WIND DESIGN VALUES - IT DOES NOT
 LIST ANY OF THE GENERATOR MODEL NUMBERS ON THE
 GENERATOR SPEC. SHEET PROVIDED - SO THE WIND DESIGN
 PRESSURES ARE STILL UNKNOWN. PLEASE PROVIDE SIGNED AND
 SEALED GENERATOR SLAB AND TIEDOWN DETAILS FROM AN
 ARCHITECT OR ENGINEER TO COMPLY WITH THE WIND LOADS FBC
 1609
  
 FYI = SIGNED AND SEALED DRAWINGS IN PROJECTDOX NEED TO
 BE DIGITALLY/ELECTRONICALLY SIGNED BY THE ENGINEER OR
 ARCHITECT TO BE USED IN ELECTRONIC PLAN REVIEW. - OR -
 IF YOUR ENGINEER DOES NOT HAVE AN ELECTRONIC OR DIGITAL
 SIGNATURE - PLEASE DROP OFF (CITY HALL DROP BOX) THE
 ORIGINAL SIGNED AND SEALED DRAWINGS/DOCUMENTS ALONG
 WITH A "PLAN REVIEW REQUEST FORM" EXPLAINING THE REASON
 FOR SUBMITTING THE DOCUMENT OR DRAWINGS. PLAN REVIEW
 REQUEST FORM CAN BE OBTAINED BY E MAILING [email protected]
 AND ASKING FOR THE FORM. (AT THIS TIME DROP BOX ITEMS
 MAY TAKE 2 TO 3 WEEKS TO PROCESS, TO SEND TO PLAN
 REVIEW - DUE TO LIMITED STAFF INSIDE THE BUILDING
 DEPT.)
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2020-05-27 Cont ID  
Sent By rmcphers Date 2020-05-27 Time 16:31 Rev Time 0.00
Received By rmcphers Date 2020-05-27 Time 16:21 Sent To  
Notes
2020-05-27 16:43:38GENERATOR PAD
 REVIEWED BY ROGER MCPHERSON
 561-805-6716
 [email protected]
  
 CORRECTIONS NEEDED - FBC WPB AMENDMENTS 107
 1) NEED SIGNED AND SEALED SITE SPECIFIC WIND DESIGN
 PRESSURES FROM AN ARCHITECT OR ENGINEER TO VERIFY WITH
 THE ALLOWABLE WIND PRESSURES SHOWN ON THE PAD
 ENGINEERING (SEE NOTE NUMBER 2 ON THE PROVIDED PAD
 ENGINEERING).
 2) ALL SIGNED AND SEALED ENGINEERING NEEDS TO BE
 DIGITALLY SIGNED AND SEALED BY THE ENGINEER.
  

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2020-05-26 Cont ID  
Sent By jleahy Date 2020-05-26 Time 16:35 Rev Time 0.00
Received By jleahy Date 2020-05-26 Time 16:18 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status P Date 2020-06-11 Cont ID  
Sent By medwards Date 2020-06-11 Time 10:54 Rev Time 0.00
Received By medwards Date 2020-06-11 Time 09:48 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2020-07-30 Cont ID  
Sent By shill Date 2020-07-30 Time 12:51 Rev Time 0.00
Received By shill Date 2020-07-30 Time 07:18 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2020-07-21 Cont ID  
Sent By rmcphers Date 2020-07-21 Time 07:58 Rev Time 0.00
Received By rmcphers Date 2020-07-06 Time 12:48 Sent To  
Notes
2020-07-16 12:48:5507/16/2020 RESUBMITTAL UPLOADED TO PROJECT DOX. DRAWING
 WITH ENGINEER'S ORIGINAL SIGNATURE SENT TO "STORAGE".
 JG.

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-06-11 Cont ID  
Sent By cpuell Date 2020-06-11 Time 11:05 Rev Time 0.00
Received By cpuell Date 2020-05-11 Time 09:10 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status N Date 2020-06-11 Cont ID  
Sent By medwards Date 2020-06-11 Time 10:55 Rev Time 0.00
Received By medwards Date 2020-06-11 Time 10:55 Sent To  
Notes
***NONE***

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 3 Status P Date 2020-07-30 Cont ID  
Sent By shill Date 2020-07-30 Time 12:50 Rev Time 0.00
Received By shill Date 2020-07-30 Time 12:50 Sent To  
Notes
2020-07-30 12:51:00PROVISO: SUBMIT ORIGINAL ENGINEERING (FPL APPT PENDING)
  

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 2 Status P Date 2020-07-16 Cont ID  
Sent By jgomez Date 2020-07-16 Time 12:49 Rev Time 0.00
Received By jgomez Date 2020-07-16 Time 12:49 Sent To  
Notes
2020-07-16 12:49:2007/16/2020 RESUBMITTAL UPLOADED TO PROJECT DOX. DRAWING
 WITH ENGINEER'S ORIGINAL SIGNATURE SENT TO "STORAGE".
 JG.

Review Stop SIGNATURE ELECTRONIC SIGNATURE SHEET
Rev No 1 Status F Date 2020-05-27 Cont ID  
Sent By rmcphers Date 2020-05-27 Time 16:43 Rev Time 0.00
Received By rmcphers Date 2020-05-27 Time 16:43 Sent To  
Notes
2020-05-27 16:44:39ENGINEERING PROVIDED NEEDS TO BE DIGITALLY SIGNED AND
 SEALED BY THE ENGINEER.

Review Stop Z ZONING
Rev No 1 Status P Date 2020-05-22 Cont ID  
Sent By rthermid Date 2020-05-22 Time   Rev Time  
Received By rthermid Date 2020-05-22 Time   Sent To I
Notes
***NONE***