Plan Review Details - Permit 20021044
Plan Review Stops For Permit 20021044 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
5 |
Status |
P |
Date |
2020-08-28 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2020-08-28 |
Time |
14:32 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2020-08-28 |
Time |
14:32 |
Sent To |
|
|
Notes |
2020-08-28 14:52:40 | APPROVED WITH PROVISO | | THE PERMIT FOR THIS BUILDING WAS ISSUED WHEN THE 1979 | | FLOOD INSURANCE RATE MAPS (FIRM) AND A 1' FREEBOARD BY | | CITY ORDINANCE WERE IN EFFECT. THE PROPERTY AT THAT | | TIME WAS IN AN A5 SPECIAL FLOOD HAZARD AREA (SFHA) WITH | | A BASE FLOOD ELEVATION OF 7' NGVD 1929. THE REQUIRED | | MINIMUM FINISH FLOOR ELEVATION WAS 8' NGVD 1929 BASED | | ON THE FIRM AND THE CITY'S FLOOD ORDINANCE AT THE TIME. | | THE FINISHED CONSTRUCTION MEETS THESE REQUIREMENTS. THE | | ELEVATION CERTIFICATE USES THE CURRENT NAVD 1988 | | VERTICAL DATUM. NGVD 1929 - 1.5223 = NAVD 1988. | | SAMANTHA HILL WILL BE ADDING THIS EXPLAINATION TO THE | | COMMUNITY COMMENT SECTION OF THE ELEVATION CERTIFICATE. |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
4 |
Status |
P |
Date |
2020-04-29 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2020-04-29 |
Time |
14:56 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2020-04-29 |
Time |
14:56 |
Sent To |
|
|
Notes |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
3 |
Status |
F |
Date |
2020-03-09 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2020-03-09 |
Time |
14:07 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2020-03-09 |
Time |
14:07 |
Sent To |
|
|
Notes |
2020-03-09 14:08:46 | ELEVATION CERTIFICATE REVIEW | | | | 1) THE ELEVATION CERTIFICATE FOR FINISHED CONSTRUCTION | | FOR THIS BUILDING CAN NOT BE APPROVED UNTIL ALL OF THE | | CONSTRUCTION HAS BEEN COMPLETED, ALL MACHINERY AND/OR | | EQUIPMENT HAS BEEN INSTALLED AND THE GRADING AROUND THE | | BUILDING IS COMPLETE. |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
F |
Date |
2020-03-05 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2020-03-05 |
Time |
13:39 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2020-03-05 |
Time |
13:39 |
Sent To |
|
|
Notes |
2020-03-05 13:39:29 | ELEVATION CERTIFICATE REVIEW | | | | 1) THE ERRORS FROM THE FIRST REVIEW HAVE BEEN CORRECTED | | ON THE REVISED ELEVATION CERTIFICATE, HOWEVER, THE | | BUILDING IS NOT YET COMPLETE AT THIS TIME. THE | | ELEVATION CERTIFICATE FOR FINISHED CONSTRUCTION FOR | | THIS BUILDING CAN NOT BE APPROVED UNTIL ALL OF THE | | CONSTRUCTION HAS BEEN COMPLETED, ALL MACHINERY AND/OR | | EQUIPMENT HAS BEEN INSTALLED AND THE GRADING AROUND THE | | BUILDING IS COMPLETE. | | | | 2) YOU WILL HAVE TO SUBMIT AN ELEVATION CERTIFICATE | | WITH THE ORIGINAL SIGNATURE AND SEAL OF THE SURVEYOR | | THAT PREPARED IT. THE ONE THAT I REVIEWED FOR YOU WAS | | EMAILED TO ME. |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
F |
Date |
2020-02-25 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2020-02-25 |
Time |
13:41 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2020-03-05 |
Time |
13:22 |
Sent To |
|
|
Notes |
2020-02-25 14:29:19 | ELEVATION CERTIFICATE REVIEW | | | | THERE ARE ERRORS THAT NEED TO BE CORRECTED. | | | | 1) THE ELEVATION CERTIFICATE HAS THE FINISHED | | CONSTRUCTION BOX MARKED. THE PHOTOGRAPHS THAT ARE | | ATTACHED DO NOT SHOW THAT THE GRADING AROUND THE | | BUILDING IS COMPLETED, WHICH IS REQUIRED FOR THE | | FINSHED CONSTRUCTION E.C. | | | | 2) UNDER ITEM B3, THE STATE OF FLORIDA IS SPELLED OUT | | AND THE INSTRUCTIONS REQUIRE THE 2-LETTER STATE | | ABBREVIATION. | | | | 3) THE LATITUDE AND LONGITUDE THAT IS LISTED IS A POINT | | ON A PROPERTY LOCATED ON THE SOUTH SIDE OF BANYAN BLVD. | | AND THE BUILDING IS LOCATED ON THE NORTH SIDE OF THE | | STREET. PLEASE CORRECT. | | | | 4) NOTE: ANY CETIFICATIONS DATED AFTER 2/21/2020 ARE | | REQUIRED TO USE THE NEW ELEVATION CERTIFICATES WITH THE | | EXPIRATION DATE OF NOVEMBER 30, 2022. |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2020-03-09 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2020-03-09 |
Time |
14:09 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2020-03-06 |
Time |
13:51 |
Sent To |
|
|
Notes |
2020-03-09 13:52:01 | RESUB ROUTED TO RMCDOUGAL |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2020-02-25 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2020-02-25 |
Time |
13:41 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2020-02-24 |
Time |
15:33 |
Sent To |
|
|
Notes |
|
|
|