Plan Review Details - Permit 20020109
Plan Review Stops For Permit 20020109
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2020-03-04 Cont ID  
Sent By rmcdouga Date 2020-03-04 Time 18:44 Rev Time 0.00
Received By rmcdouga Date 2020-03-04 Time 17:45 Sent To I
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2020-02-20 Cont ID  
Sent By jleahy Date 2020-02-20 Time 11:11 Rev Time 0.00
Received By jleahy Date 2020-02-20 Time 11:11 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-03-04 Cont ID  
Sent By rmcdouga Date 2020-03-04 Time 18:44 Rev Time 0.00
Received By rmcdouga Date 2020-02-04 Time 13:17 Sent To  
Notes
2020-02-18 07:41:25ROUTED TO PLUMBING INBOX
2020-02-05 13:17:39ROUTED TO ZONING INBOX

Review Stop P PLUMBING
Rev No 2 Status P Date 2020-03-03 Cont ID  
Sent By abelisle Date 2020-03-03 Time 17:18 Rev Time 0.00
Received By abelisle Date 2020-03-03 Time 17:17 Sent To  
Notes
2020-03-03 17:18:153/3/2020 REVIEWED FOR CODE COMPLIANCE (PLUMBING/GAS)
  
 1-GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN
 THIS SUBMITTAL PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN
 PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND PLANS
 WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE
 RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT
 REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE. AT
 THIS TIME. WPB AMENDMENTS TO FBC SEC. 107.2.1.
  
 2- SEPERATE PERMITS REQUIRED FOR PLUMBING AND GAS
  
 BY REVIEWING THE PLANS / SPECIFICATIONS FOR CODE
 COMPLIANCE DOES NOT RELIEVE THE OWNER, DESIGN
 PROFESSIONAL, CONTRACTORS OR THEIR REPRESENTATIVES FROM
 THE RESPONSIBILITY TO COMPLY WITH ALL LOCAL, STATE AND
 NATIONAL CODES AND STANDARDS IN EFFECT AT THE TIME OF
 PERMIT ISSUANCE. OUR REVIEW IS NOT A CHECK OF EVERY
 ITEM AND DOES NOT PREVENT THIS DEPARTMENT FROM
 REQUIRING CORRECTIONS DURING CONSTRUCTION. ANY CHANGES
 / ALTERATIONS TO APPROVED PLANS SHALL BE APPROVED TO
 AVOID VOIDING OF THE PERMIT.
  
 ATELYO BELISLE
 PLUMBING INSPECTOR /
 PLUMBING PLANS EXAMINER
 AVAILABLE FROM 1:00 PM TO 4:00 PM
 [email protected]
 561-805-6695
  

Review Stop P PLUMBING
Rev No 1 Status F Date 2020-02-25 Cont ID  
Sent By abelisle Date 2020-02-25 Time 13:21 Rev Time 0.00
Received By abelisle Date 2020-02-21 Time 06:48 Sent To  
Notes
2020-03-03 17:13:53 
  
  
  
2020-02-25 13:53:512/25/2020 1ST PLUMBING/POOL REVIEW **DENIED** WITH
 COMMENTS NOTE - A COMPREHENSIVE REVIEW COULD NOT BE
 DONE AT THIS TIME AND ADDITIONAL PLAN REVIEW COMMENTS
 MAY BE GENERATED UPON THE RE-REVIEW OF SUBMITTED
 CORRECTIONS.
  
 1- SUBMIT DOCUMENTATION THAT THE GAS POOL HEATER MEETS
 THE MINIMUM REQUIRED EFFICIENCY AS REQUIRED BY THE 2017
 FBC-ENERGY SEC.R403.10.4
  
 2- SWIMMING POOL HEAT PUMP POOL HEATERS SHALL HAVE A
 MINIMUM COP OF 4.0 WHEN TESTED IN ACCORDANCE WITH AHRI
 1160.
  
 3- ALL POOL HEATERS SHALL BE EQUIPPED WITH A READILY
 ACCESSIBLE ON-OFF SWITCH THAT IS MOUNTED OUTSIDE THE
 HEATER TO ALLOW SHUTTING OFF THE HEATER WITHOUT
 ADJUSTING THE THERMOSTAT SETTING. 2017 FBC-ENERGY ?
 SEC. R403.10.1
  
 4- HEATED SWIMMING POOLS AND IN GROUND PERMANENTLY
 INSTALLED SPAS SHALL BE EQUIPPED WITH A VAPOR-RETARDANT
 COVER ON OR AT THE WATER SURFACE OR A LIQUID COVER OR
 OTHER MEANS PROVEN TO REDUCE HEAT LOSS. 2017 FBC-
 ENERGY- SEC. R 403.10.3.
  
 5- THE DYNAMIC HEAD CALCULATIONS FOR THE MAXIMUM SYSTEM
 FLOW DOES NOT SHOW ALL FRICTION LOSS THROUGH ALL
 HEATERS. WPB AMENDMENTS TO THE FBC SEC. 107.2.1
 INFORMATION ON CONSTRUCTION DOCUMENTS.
  
 6- BACKFLOW PREVENTER REQUIRED PER THE CITY OF WEST
 PALM BEACH ORD #2853-95. A PERMIT REQUIRED BY A
 LICENSED CONTRACTOR AND MUST BE CERTIFIED BY UTILITIES
 PRIOR TO FINAL INSPECTION. A DUAL CHECK VALVE MAY BE
 USED IF NO POOL FILL IS INSTALLED AT THE METER AND
 INSTALLED BY UTILITIES WHICH DO NOT REQUIRE A PERMIT SO
 PLEASE CONTACT CITY OF WPB UTILITIES AT 561-822-2240
 FOR FURTHER DIRECTIONS.
  
 7- A CONTRACTOR LICENSED UNDER STATUES 489 SEPERATE
 PERMIT IS REQUIRED FOR THE GAS AND PLUMBING
  
 8- SHOW THE BTU LOAD FOR THE GAS POOL HEATER. THIS
 VALUE MUST BE INCLUDED IN THE SIZING OF THE SYSTEM.
 2017 FBC FUEL GAS SEC. 402.2 OR 2017 FBC FUEL GAS RES.
 SEC G2413.2 MAXIMUM GAS DEMAND
  
 9- THE CLAIMED VALUE APPEARS TO BE UNDERESTIMATED ON
 THE APPLICATION, PLEASE PROVIDE A BONA FIDE SIGNED
 CONTRACT AND SHALL INCLUDE DEMO OF EXISTING POOL. WPB
 AMENDMENTS TO THE FBC 109.3. BUILDING PERMITS
 VALUATIONS.
  
 10- GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED
 IN THIS SUBMITTAL PACKAGE. A GAS PLAN REVIEW HAS NOT
 BEEN PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND
 PLANS WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE
 RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT
 REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE. AT
 THIS TIME. WPB AMENDMENTS TO FBC SEC. 107.2.1.
  
 ATELYO BELISLE
 PLUMBING INSPECTOR /
 PLUMBING PLANS EXAMINER
 AVAILABLE FROM 1:00 PM TO 4:00 PM
 [email protected]
 561-805-6695
  

Review Stop Z ZONING
Rev No 1 Status P Date 2020-02-14 Cont ID  
Sent By rfalcone Date 2020-02-14 Time 10:37 Rev Time 0.00
Received By rfalcone Date 2020-02-14 Time 10:37 Sent To I
Notes
2020-02-14 10:38:04POOL EQUIPMENT SHALL BE NO CLOSER THAN 11 FEET FROM THE
 REAR PROPERTY LINE.