Plan Review Details - Permit 19120883
Plan Review Stops For Permit 19120883
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2020-01-21 Cont ID  
Sent By rmcdouga Date 2020-01-21 Time 10:07 Rev Time 0.00
Received By rmcdouga Date 2020-01-21 Time 09:47 Sent To I
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2020-01-03 Cont ID  
Sent By rmcdouga Date 2020-01-03 Time 08:39 Rev Time 0.00
Received By rmcdouga Date 2020-01-03 Time 08:39 Sent To  
Notes
2020-01-03 09:25:33PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC SIXTH EDITION (2017)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) PROVIDE TWO SETS OF A GENERATOR PAD DETAIL DRAWING.
 SPECIFY THE LENGTH, WIDTH AND THICHNESS OF THE CONCRETE
 SLAB. SPECIFY THE STEEL REINFORCING IN THE SLAB AND THE
 TYPE AND SIZE OF THE ANCHORS THAT WILL ATTACH THE
 GENERATOR TO THE SLAB. SOME OF THIS INFORMATION WAS
 PROVIDED ON THE ELECTRIAL PLANS. NOTE #1 ON PAGE 8 OF
 THE GENERAC INSTALLATION LAYOUT LISTS THE RECOMMENDED
 CONCRETE PAD SIZE. PLEASE PROVIDE ALL OF THIS
 INFORMATION ON THE GENERATOR PAD DETAIL DRAWINGS ALONG
 WITH THE PROPERTY ADDRESS AND THE PRINTED NAME AND
 SIGNATURE OF THE PERSON THAT DID THE DRAWING. FBC
 107.2.1
  

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2020-01-16 Cont ID  
Sent By jleahy Date 2020-01-16 Time 11:46 Rev Time 0.00
Received By jleahy Date 2020-01-16 Time 11:46 Sent To G
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2020-01-03 Cont ID  
Sent By jleahy Date 2020-01-03 Time 10:54 Rev Time 0.00
Received By jleahy Date 2020-01-03 Time 10:54 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 2 Status N Date 2020-01-16 Cont ID  
Sent By lcrespo Date 2020-01-16 Time 17:03 Rev Time 0.00
Received By lcrespo Date 2020-01-16 Time 17:03 Sent To  
Notes
2020-01-16 17:12:12GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN
 THIS SUBMITTAL PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN
 PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND PLANS
 WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE
 RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT
 REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE PER
 THE WPB AMENDMENTS TO FBC SEC. 107.2.1.

Review Stop G GAS REVIEW
Rev No 1 Status N Date 2020-01-17 Cont ID  
Sent By lcrespo Date 2019-12-30 Time 17:46 Rev Time 0.00
Received By lcrespo Date 2019-12-30 Time 17:46 Sent To  
Notes
2019-12-30 17:55:28GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN
 THIS SUBMITTAL PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN
 PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND PLANS
 WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE
 RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT
 REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE PER
 THE WPB AMENDMENTS TO FBC SEC. 107.2.1.
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2020-01-21 Cont ID  
Sent By rmcdouga Date 2020-01-21 Time 10:08 Rev Time 0.00
Received By rmcdouga Date 2020-01-13 Time 13:25 Sent To  
Notes
2020-01-14 13:25:54RESUB ROUTED TO JLEAHY

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-01-03 Cont ID  
Sent By jleahy Date 2020-01-03 Time 10:55 Rev Time 0.00
Received By jleahy Date 2019-12-19 Time 13:23 Sent To  
Notes
2019-12-20 13:23:33ROUTED TO ZONING INBOX

Review Stop Z ZONING
Rev No 1 Status P Date 2019-12-23 Cont ID  
Sent By rfalcone Date 2019-12-23 Time 14:38 Rev Time 0.00
Received By rfalcone Date 2019-12-23 Time 14:38 Sent To B
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved