Plan Review Details - Permit 19120882
Plan Review Stops For Permit 19120882
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2020-01-21 Cont ID  
Sent By rmcdouga Date 2020-01-21 Time 08:57 Rev Time 0.00
Received By rmcdouga Date 2020-01-21 Time 08:57 Sent To I
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2020-01-03 Cont ID  
Sent By rmcdouga Date 2020-01-03 Time 09:58 Rev Time 0.00
Received By rmcdouga Date 2020-01-03 Time 09:57 Sent To  
Notes
2020-01-03 10:01:29PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC SIXTH EDITION (2017)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) THE PAD DIMENSIONS THAT ARE SPECIFIED ON THE
 ELECTRICAL DRAWINGS ARE SMALLER THAN THE MINIMUM
 RECOMMENDED CONCRETE PAD SIZE IN NOTE #1 ON PAGE 9 OF
 THE GENERAC INSTALLATION LAYOUT. FBC 107.2.1

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2020-01-16 Cont ID  
Sent By jleahy Date 2020-01-16 Time 11:44 Rev Time 0.00
Received By jleahy Date 2020-01-16 Time 11:44 Sent To G
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2020-01-02 Cont ID  
Sent By jleahy Date 2020-01-02 Time 10:56 Rev Time 0.00
Received By jleahy Date 2020-01-02 Time 10:56 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 2 Status N Date 2020-01-17 Cont ID  
Sent By lcrespo Date 2020-01-16 Time 17:33 Rev Time 0.00
Received By lcrespo Date 2020-01-16 Time 17:33 Sent To  
Notes
2020-01-16 17:33:15GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN
 THIS SUBMITTAL PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN
 PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND PLANS
 WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE
 RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT
 REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE PER
 THE WPB AMENDMENTS TO FBC SEC. 107.2.1.

Review Stop G GAS REVIEW
Rev No 1 Status N Date 2020-01-17 Cont ID  
Sent By lcrespo Date 2019-12-30 Time 17:31 Rev Time 0.00
Received By lcrespo Date 2019-12-30 Time 17:31 Sent To  
Notes
2019-12-30 17:32:28GAS PLAN REVIEW, A GAS PLAN HAS NOT BEEN INCLUDED IN
 THIS SUBMITTAL PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN
 PERFORMED AT THIS TIME. A SEPARATE GAS PERMIT AND PLANS
 WILL BE REQUIRED FOR A CONTRACTOR TO PERFORM THE
 RELATED WORK. PROVIDE COMPLETE PLANS AND GAS RISER THAT
 REFLECTS THE ENTIRE SCOPE OF GAS WORK TO BE DONE PER
 THE WPB AMENDMENTS TO FBC SEC. 107.2.1.
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2020-01-21 Cont ID  
Sent By rmcdouga Date 2020-01-21 Time 08:58 Rev Time 0.00
Received By rmcdouga Date 2020-01-13 Time 13:24 Sent To  
Notes
2020-01-14 13:24:14RESUB ROUTED TO JLEAHY

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2020-01-03 Cont ID  
Sent By rmcdouga Date 2020-01-03 Time 09:58 Rev Time 0.00
Received By rmcdouga Date 2019-12-19 Time 13:25 Sent To  
Notes
2019-12-20 13:25:20ROUTED TO ZONING INBOX

Review Stop Z ZONING
Rev No 1 Status P Date 2019-12-23 Cont ID  
Sent By rfalcone Date 2019-12-23 Time 14:40 Rev Time 0.00
Received By rfalcone Date 2019-12-23 Time 14:40 Sent To B
Notes
***NONE***