Plan Review Details - Permit 19071443
Plan Review Stops For Permit 19071443
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2019-08-23 Cont ID  
Sent By rmcdouga Date 2019-08-23 Time 08:15 Rev Time 0.00
Received By rmcdouga Date 2019-08-23 Time 08:15 Sent To I
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2019-08-07 Cont ID  
Sent By rmcdouga Date 2019-08-07 Time 09:03 Rev Time 0.00
Received By rmcdouga Date 2019-08-07 Time 09:03 Sent To  
Notes
***NONE***

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2019-08-07 Cont ID  
Sent By jleahy Date 2019-08-07 Time 14:45 Rev Time 0.00
Received By jleahy Date 2019-08-07 Time 14:45 Sent To P
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2019-08-23 Cont ID  
Sent By rmcdouga Date 2019-08-23 Time 08:15 Rev Time 0.00
Received By rmcdouga Date 2019-08-15 Time 13:43 Sent To  
Notes
2019-08-16 13:43:39RESUB ROUTED TO TKLARGE

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2019-08-08 Cont ID  
Sent By tklarge Date 2019-08-08 Time 04:18 Rev Time 0.00
Received By tklarge Date 2019-07-29 Time 15:03 Sent To  
Notes
2019-07-30 15:03:46ROUTED TO ZONING INBOX

Review Stop P PLUMBING
Rev No 2 Status P Date 2019-08-22 Cont ID  
Sent By tklarge Date 2019-08-22 Time 15:00 Rev Time 0.00
Received By tklarge Date 2019-08-22 Time 14:51 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status F Date 2019-08-08 Cont ID  
Sent By tklarge Date 2019-08-08 Time 04:18 Rev Time 0.00
Received By tklarge Date 2019-08-06 Time 10:34 Sent To  
Notes
2019-08-08 04:18:381) SHT. 3 OF 3 SHOWS A MAIN DRAIN IN THE SPA AND THE
 PIPING SCHEMATIC SHOWS ONE BUT NOT ON THE PLAN VIEW ON
 SHT. 1. CLARIFY.
 2) SUBMIT TOTAL DYNAMIC HEAD CALCULATIONS FOR THE
 MAXIMUM SYSTEM FLOW FOR THE SPA.. THE MAXIMUM FLOW OF
 THE PUMP FROM ITS PUMP CURVE AND THE SIMPLIFIED TOTAL
 DYNAMIC HEAD CALCULATION IS NO LONGER ALLOWED TO BE
 USED IN DETERMINING MAXIMUM SYSTEM FLOW RATE PER
 ANSI/APSP/ICC 7 - 2013 SECS. 4.4.9, 4.4.9.1. THE 2013
 EDITION ADDRESSES FLOW RATE IN GALLONS PER MINUTE
 (GPM). IT REQUIRES THAT MAXIMUM SYSTEM FLOW RATE DOES
 NOT EXCEED THE LISTED MAXIMUM FLOW RATE OF THE SUCTION
 OUTLET FITTING ASSEMBLY (DRAIN COVER).THE TDH
 CALCULATIONS MUST INCLUDE ALL OF THE SYSTEM COMPONENTS
 INCLUDING SUCTION AND RETURN PIPING, FITTINGS, VALVES,
 HEATER, FILTER, AND CHLORINATOR. ALL SYSTEM COMPONENTS
 EXCEPT THE PUMP.
 3) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE MAIN
 DRAINS. WPB AMEND. TO FBC SEC. 107.2.1.
 4) IDENTIFY ON THE PUMP CURVE WHICH CURVE KEY IS
 SPECIFIC TO THE PUMP BEING INSTALLED ON THIS POOL. THIS
 IS NEEDED TO CONFIRM THE MAXIMUM SYSTEM FLOW FROM THE
 TDH CALCULATIONS. ANSI/APSP/ICC 7 - 2013 SECS. 4.4.9,
 4.4.9.1.
 5) THE PROJECT SPECIFIC DETAILS ON SHT. 1CALL OUT A VS
 PENTAIR PUMP BUT THE SUBMITTED SPECS ARE FOR A VF PUMP.
 CLARIFY.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  
  

Review Stop Z ZONING
Rev No 1 Status P Date 2019-08-01 Cont ID  
Sent By ajones Date 2019-08-01 Time 12:40 Rev Time 0.00
Received By ajones Date 2019-08-01 Time 12:40 Sent To  
Notes
***NONE***