Plan Review Details - Permit 19030747
Plan Review Stops For Permit 19030747
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2019-03-22 Cont ID  
Sent By pvalenti Date 2019-03-22 Time 16:29 Rev Time 0.00
Received By pvalenti Date 2019-03-22 Time 16:29 Sent To  
Notes
2019-03-22 17:05:27 
 APPROVED PV

Review Stop E ELECTRICAL
Rev No 1 Status N Date 2019-03-22 Cont ID  
Sent By pvalenti Date 2019-03-22 Time 17:11 Rev Time 0.00
Received By pvalenti Date 2019-03-22 Time 17:11 Sent To  
Notes
2019-03-22 17:10:47ELECTRIC NOT REQUIRED. PV

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2019-03-22 Cont ID  
Sent By pvalenti Date 2019-03-22 Time 17:11 Rev Time 0.00
Received By pvalenti Date 2019-03-15 Time 11:44 Sent To  
Notes
***NONE***