Plan Review Details - Permit 19020512
Plan Review Stops For Permit 19020512 |
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
P |
Date |
2019-03-20 |
|
|
Cont ID |
|
Sent By |
jleahy |
Date |
2019-03-20 |
Time |
11:07 |
Rev Time |
0.00 |
Received By |
jleahy |
Date |
2019-03-20 |
Time |
11:07 |
Sent To |
|
|
Notes |
|
|
Review Stop |
G |
GAS REVIEW |
Rev No |
5 |
Status |
P |
Date |
2020-02-07 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2020-02-07 |
Time |
05:40 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2020-02-07 |
Time |
05:00 |
Sent To |
|
|
Notes |
|
|
Review Stop |
G |
GAS REVIEW |
Rev No |
4 |
Status |
F |
Date |
2019-09-16 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2019-09-16 |
Time |
11:22 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2019-09-16 |
Time |
11:09 |
Sent To |
|
|
Notes |
2019-09-16 11:14:54 | 1) SUBMIT TWO COPIES OF AN ISOMETRIC DRAWING THAT | | CLEARLY SHOWS THE LENGTH OF ALL CUT SECTIONS OF PIPE | | PER 2017 FBC-FUEL GAS, SECS. 402.4.1, 402.4.2. OR 2017 | | FBC-R SEC. G2413.4.1, G2413.4.2. THE FLAT DRAWING THAT | | HAS BEEN SUBMITTED IS UNACCEPTABLE AS IT IS EXTREMELY | | DIFFICULT TO TELL WHERE THE LINES START AND END. | | SEC.107.3.5.3 OF WPB AMEND. TO FBC. 2ND REQUEST. | | 2.) LIST THE BTU LOAD OF EACH APPLIANCE AND THE TOTAL | | BTU LOAD ON THE SYSTEM. REFER TO THE 2017 FBC-FUEL GAS | | SECS.401.8, 402.2, AND TABLES 402.4 (1) THRU 402.4 (37) | | OR 2017 FBC-RES. SEC. G2413.3, G2413.4 AND TABLES | | G2413.4 (1 ) THROUGH G2413.4 (21). 2ND REQUEST | | 3.) SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS | | METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE | | OUTLET IN THE BUILDING AND / OR SYSTEM PER THE 2017 | | FBC-FUEL GAS SEC.402.4.1, 402.4.2, OR 2017 FBC-RES. | | SEC. G 2413.4.1, G2413.4.2.2ND REQUEST. | | 4) INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM | | ON THE PLAN PER 2017 FBC-FUEL GAS SEC.402.1, 402.4.3 | | THRU 402.6 OR 2017 FBC RES. SEC. G2413.2, G2413.4.3. | | THE GAS PLAN NOTES 5 PSI AND 1/2 LB. CLARIFY.2ND | | REQUEST. | | 5) INDICATE ON THE PLAN IF THE TANKLESS WATER HEATER IS | | THE ONLY GAS APPLIANCE ON THIS SYSTEM. IF NOT, SUBMIT A | | COMPLETE GAS RISER SHOWING ALL PIPE SIZES, TYPE OF | | PIPE, THE DEVELOPED LENGTH TO THE FURTHEST GAS OUTLET, | | THE BTU LOAD OF EACH APPLIANCE, THE PSI OF THE SYSTEM, | | THE TYPE OF GAS AND THE TOTAL BTU LOAD ON THE SYSTEM. | | THESE REQUIREMENTS ALSO APPLY TO A NEW GAS SYSTEM. | | 6) SUBMIT TWO COPIES OF A HOUSE PLAN / FLOOR PLAN | | SHOWING THE LOCATION OF THE TANKLESS WATER HEATER AND | | THE LOCATION AND DISTANCE OF ANY OPERABLE DOORS OR | | WINDOWS IN RELATION TO THE WATER HEATER. THE LOCATION | | OF THE WATER HEATER SHALL COMPLY WITH THE | | MANUFACTURER'S INSTALLATION INSTRUCTIONS. THE HOUSE | | PLAN / FLOOR PLAN CAN BE HAND DRAWN. WPB AMEND. TO FBC | | SEC. 107.2.1. 2ND REQUEST. THE FLOOR PLAN THAT WAS | | SUBMITTED NEEDS TO BE REDONE SO THAT IT CLEARLY | | REFLECTS THE LOCATION OF THE TANKLESS WATER HEATER.2ND | | REQUEST. | | 7) SUBMIT TWO COPIES OF THE APPLICABLE SIZING TABLES | | USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON THE | | PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) FROM | | THE GAS CODE OR OTHER STANDARD THAT WERE USED IN THE | | DESIGN OF THIS GAS SYSTEM. REFER TO THE 2017 FBC-FUEL | | GAS SECS. 401.4, 401.8, 402.3, AND TABLES 402.4 (1) | | THRU 402.4 (37) OR 2017 FBC-RES. SEC. G2413.3, G2412.8, | | G2413.1, G2413.2, & G2413.3.2ND REQUEST. | | 8) THE PLANS INDICATE AN EXISTING GAS METER/LP TANK AND | | CITY RECORDS SHOW AN EXISTING GAS SYSTEM FOR THIS | | ADDRESS. THE BTU LOAD OF THE EXISTING GAS SYSTEM MUST | | BE ADDED INTO THE TOTAL BTU LOAD ON THE SYSTEM TO | | ENSURE THE EXISTING SYSTEM IS PROPERLY SIZED. IF | | UNDERSIZED, THE EXISTING SYSTEM MUST BE REDONE TO | | ENSURE A SAFE OPERATING SYSTEM. SUBMIT A GAS PIPING | | RISER DIAGRAM THAT SHOWS THE TYPE OF EXISTING | | APPLIANCE, THE BTU LOAD OF EACH APPLIANCE, THE PIPE | | SIZE AND TYPE OF PIPE TO EACH APPLIANCE, AND THE | | DISTANCE OF THE LONGEST LENGTH OF PIPING FROM THE POINT | | OF DELIVERY TO THE MOST REMOTE OUTLET AND THE LOAD OF | | THE SECTION. NOTE: IF THE EXISTING SYSTEM IS LESS THAN | | A 2 PSI SYSTEM AND THE SYSTEM PRESSURE IS INCREASED TO | | 2 PSI, A LINE PRESSURE REGULATOR IS REQUIRED AT ALL THE | | EXISTING APPLIANCES. FGC SECS. 401.4, 401.8, 402.1, | | 402.2, 402.3 OR FBCR SECS.G2412.4, G2412.8, G2413.1, | | G2413.2, G2413.2ND REQUEST. | | 9) SUBMIT ONE ADDITIONAL COPY OF THE INSTALLATION | | MANUAL. WPB AMEND. TO FBC SEC. 107.2.1. | | 10) INDICATE ON THE MANUFACTURER'S SPECIFICATIONS WHICH | | MODEL OF THE WATER HEATER IS BEING INSTALLED. WPB | | AMEND. TO FBC SEC. 107.2.1. | | 11) PLACE A NOTE ON THE PLAN HOW THE WINDOW IS | | NON-OPERATIONAL. SCREWING THE WINDOW SHUT IS NOT | | ACCEPTABLE. IF THIS IS A FIXED WINDOW, THEN NOTE SUCH | | ON THE PLANS. | | | | TIM LARGE | | CHIEF PLUMBING INSPECTOR | | PLUMBING PLAN REVIEW | | 561-805-6692 | | [email protected] | | | | | | | | | | | | |
|
|
Review Stop |
G |
GAS REVIEW |
Rev No |
3 |
Status |
F |
Date |
2019-08-30 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2019-08-30 |
Time |
12:39 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2019-08-30 |
Time |
12:21 |
Sent To |
|
|
Notes |
2019-08-30 12:39:43 | 1) SUBMIT TWO COPIES OF AN ISOMETRIC DRAWING THAT | | CLEARLY SHOWS THE LENGTH OF ALL CUT SECTIONS OF PIPE | | PER 2017 FBC-FUEL GAS, SECS. 402.4.1, 402.4.2. OR 2017 | | FBC-R SEC. G2413.4.1, G2413.4.2. | | 2.) SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL | | PIPE SIZES, | | 3.) TYPE OF GAS (LP OR NATURAL).WPB AMEND. TO FBC SEC. | | 107.2.1. | | 4.) LIST THE BTU LOAD OF EACH APPLIANCE AND THE TOTAL | | BTU LOAD ON THE SYSTEM. REFER TO THE 2017 FBC-FUEL GAS | | SECS.401.8, 402.2, AND TABLES 402.4 (1) THRU 402.4 (37) | | OR 2017 FBC-RES. SEC. G2413.3, G2413.4 AND TABLES | | G2413.4 (1 ) THROUGH G2413.4 (21). | | 5.) SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS | | METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE | | OUTLET IN THE BUILDING AND / OR SYSTEM PER THE 2017 | | FBC-FUEL GAS SEC.402.4.1, 402.4.2, OR 2017 FBC-RES. | | SEC. G 2413.4.1, G2413.4.2. | | 6) INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM | | ON THE PLAN PER 2017 FBC-FUEL GAS SEC.402.1, 402.4.3 | | THRU 402.6 OR 2017 FBC RES. SEC. G2413.2, G2413.4.3. | | 7) INDICATE ON THE PLAN IF THE TANKLESS WATER HEATER IS | | THE ONLY GAS APPLIANCE ON THIS SYSTEM. IF NOT, SUBMIT A | | COMPLETE GAS RISER SHOWING ALL PIPE SIZES, TYPE OF | | PIPE, THE DEVELOPED LENGTH TO THE FURTHEST GAS OUTLET, | | THE BTU LOAD OF EACH APPLIANCE, THE PSI OF THE SYSTEM, | | THE TYPE OF GAS AND THE TOTAL BTU LOAD ON THE SYSTEM. | | THESE REQUIREMENTS ALSO APPLY TO A NEW GAS SYSTEM. | | 8) SUBMIT TWO COPIES OF A HOUSE PLAN / FLOOR PLAN | | SHOWING THE LOCATION OF THE TANKLESS WATER HEATER AND | | THE LOCATION AND DISTANCE OF ANY OPERABLE DOORS OR | | WINDOWS IN RELATION TO THE WATER HEATER. THE LOCATION | | OF THE WATER HEATER SHALL COMPLY WITH THE | | MANUFACTURER'S INSTALLATION INSTRUCTIONS. THE HOUSE | | PLAN / FLOOR PLAN CAN BE HAND DRAWN. WPB AMEND. TO FBC | | SEC. 107.2.1. | | 9) INDICATE ON THE PLAN IF THE TANKLESS WATER HEATER IS | | REPLACING AN EXISTING TANKLESS WATER HEATER OR IS IT | | REPLACING A STORAGE TANK TYPE WATER HEATER OR IS IT | | BEING ADDED TO THE EXISTING HOT WATER SYSTEM? INDICATE | | ON THE APPLICATION IN THE DESCRIPTION OF WORK. | | 10) SUBMIT TWO COPIES OF THE APPLICABLE SIZING TABLES | | USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON THE | | PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) FROM | | THE GAS CODE OR OTHER STANDARD THAT WERE USED IN THE | | DESIGN OF THIS GAS SYSTEM. REFER TO THE 2017 FBC-FUEL | | GAS SECS. 401.4, 401.8, 402.3, AND TABLES 402.4 (1) | | THRU 402.4 (37) OR 2017 FBC-RES. SEC. G2413.3, G2412.8, | | G2413.1, G2413.2, & G2413.3. | | 11) THE PLANS INDICATE AN EXISTING GAS METER/LP TANK | | AND CITY RECORDS SHOW AN EXISTING GAS SYSTEM FOR THIS | | ADDRESS. THE BTU LOAD OF THE EXISTING GAS SYSTEM MUST | | BE ADDED INTO THE TOTAL BTU LOAD ON THE SYSTEM TO | | ENSURE THE EXISTING SYSTEM IS PROPERLY SIZED. IF | | UNDERSIZED, THE EXISTING SYSTEM MUST BE REDONE TO | | ENSURE A SAFE OPERATING SYSTEM. SUBMIT A GAS PIPING | | RISER DIAGRAM THAT SHOWS THE TYPE OF EXISTING | | APPLIANCE, THE BTU LOAD OF EACH APPLIANCE, THE PIPE | | SIZE AND TYPE OF PIPE TO EACH APPLIANCE, AND THE | | DISTANCE OF THE LONGEST LENGTH OF PIPING FROM THE POINT | | OF DELIVERY TO THE MOST REMOTE OUTLET AND THE LOAD OF | | THE SECTION. NOTE: IF THE EXISTING SYSTEM IS LESS THAN | | A 2 PSI SYSTEM AND THE SYSTEM PRESSURE IS INCREASED TO | | 2 PSI, A LINE PRESSURE REGULATOR IS REQUIRED AT ALL THE | | EXISTING APPLIANCES. FGC SECS. 401.4, 401.8, 402.1, | | 402.2, 402.3 OR FBCR SECS.G2412.4, G2412.8, G2413.1, | | G2413.2, G2413. | | | | NOTE: THIS IS A RE-REVIEW OF THE LAST SUBMITTAL AND | | THESE COMEENTS TAKE PRECEDENCE. | | | | TIM LARGE | | CHIEF PLUMBING INSPECTOR | | PLUMBING PLAN REVIEW | | 561-805-6692 | | [email protected] | | | | | | | | | | | | |
|
|
Review Stop |
G |
GAS REVIEW |
Rev No |
2 |
Status |
F |
Date |
2019-04-01 |
|
|
Cont ID |
|
Sent By |
thunt |
Date |
2019-04-01 |
Time |
07:40 |
Rev Time |
0.00 |
Received By |
thunt |
Date |
2019-04-01 |
Time |
07:40 |
Sent To |
|
|
Notes |
2019-04-01 07:46:03 | GAS 1ST REVIEW***DENIED** NOTE - A COMPREHENSIVE REVIEW | | COULD NOT BE DONE AT THIS TIME AND ADDITIONAL PLAN | | REVIEW COMMENTS MAY BE GENERATED UPON THE RE-REVIEW OF | | SUBMITTED CORRECTIONS. | | | | | | | | 1) SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE | | LENGTH OF ALL CUT SECTIONS OF PIPE PER 2017 FBC-FUEL | | GAS, SECS. 402.4.1, 402.4.2. OR 2017 FBC-RES SEC. | | G2413.4.1, G2413.4.2 | | | | 2) ANSWERED*****SHOW THE TYPE OF PIPE MATERIAL BEING | | INSTALLED, ALL PIPE SIZES, AND THE CORRESPONDING EHD | | NUMBER OF THE CORRUGATED STAINLESS STEEL TUBING | | (IF APPLICABLE) FOR EACH PIPE SIZE. WPB AMENDMENTS TO | | FBC SEC.107.2.1. | | | | 3) TYPE OF GAS (LP OR NATURAL).WPB AMEND. TO FBC SEC. | | 107.2.1.\ | | | | 4) SUBMIT TWO COPIES OF THE APPLICABLE SIZING TABLES | | USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON THE | | PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) FROM | | THE GAS CODE OR OTHER STANDARD THAT WERE USED IN THE | | DESIGN OF THIS GAS SYSTEM. REFER TO THE 2017 FBC-FUEL | | GAS SECS. 401.4, 401.8, 402.3, AND TABLES 402.4 (1) | | THRU 402.4 (37) OR 2017 FBC-RES. SEC. G2413.3, G2412.8, | | G2413.1, G2413.2, & G2413.3. YOU SUBMITTED 37 DIFFERENT | | SIZING CHARTS. WHICH ONE? | | | | 5) PAGE 21 CALLS OUT 4' MIN FOR A NON DIRECT VENT UNIT. | | YOU PLAN CALLS OUT FOR 28". PROVIDE A PLAN WITH A NEW | | LOCATION.SUBMIT TWO COPIES OF A HOUSE PLAN SHOWING THE | | LOCATION OF THE TANKLESS WATER HEATER AND THE LOCATION | | AND DISTANCE OF ANY OPERABLE DOORS OR WINDOWS IN | | RELATION TO THE WATER HEATER. THE LOCATION OF THE WATER | | HEATER SHALL COMPLY WITH THE MANUFACTURER'S | | INSTALLATION INSTRUCTIONS. THE HOUSE PLAN CAN BE HAND | | DRAWN. WPB AMEND. TO FBC SEC. 107.2.1 | | | | 6) ANSWERED****** INDICATE ON THE PLAN IF THE TANKLESS | | WATER HEATER IS THE ONLY GAS APPLIANCE ON THIS SYSTEM? | | IF NOT, SUBMIT A COMPLETE GAS RISER SHOWING ALL PIPE | | SIZES, TYPE OF PIPE, THE DEVELOPED LENGTH TO THE | | FURTHEST GAS OUTLET, THE BTU LOAD OF EACH APPLIANCE, | | THE PSI OF THE SYSTEM, THE TYPE OF GAS AND THE TOTAL | | BTU LOAD ON THE SYSTEM. THESE REQUIREMENTS ALSO APPLY | | TO A NEW GAS SYSTEM. NOTE CITY RECORDS SHOW OTHER GAS | | APPLIANCES. LIST THE BTU LOAD OF EACH APPLIANCE AND THE | | TOTAL BTU LOAD ON THE SYSTEM. REFER TO THE 2017 | | FBC-FUEL GAS SECS.401.8, 402.2, AND TABLES 402.4 (1) | | THRU 402.4 (37) OR 2017 FBC-RES. SEC. G2413.3, G2413.4 | | AND TABLES G2413.4 (1 ) THROUGH G2413.4 (21). | | | | 7) PROVIDE WHICH OF THE 3 DIFFERENT MODELS ON THE | | INSTALLATION MANUAL YOU ARE USING.STATE WHICH | | MODELTANKLESS YOU PLAN TO INSTALLED. SUBMIT FULL | | MANUFACTURER?S SPECIFICATION SHEETS / INSTALLATION | | MANUAL FOR ALL GAS EQUIPMENT TO VERIFY COMPLIANCE WITH | | STANDARDS NFPA 54, NFPA 58, AND FBC-2017 FUEL GAS CODE | | SEC. 402.2, AND 301.3 OR 2017 FBC-RES. SEC. G2404.3. | | GAS APPLIANCES SHALL BE LISTED AND LABELED. | | | | 8) ANSWERED******SHOW THE DISTANCE FROM THE POINT OF | | DELIVERY, (GAS METER / MP REGULATOR / LP TANK) TO THE | | MOST REMOTE OUTLET IN THE BUILDING AND / OR SYSTEM PER | | THE 2017 FBC-FUEL GAS SEC.402.4.1, 402.4.2, OR 2017 | | FBC-RES. SEC. G 2413.4.1, G2413.4.2 | | | | 9) NEW COMMENT: PLANS/ DOCUMENTS SHALL BE DRAWN UPON | | SUITABLE MATERIAL. PENCIAL IS NOT PERMITTED. FBC | | 107.2.1 | | | | | | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT | | CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID | | THE PREVIOUSLY REVIEWED SHEETS. | | | | | | TIM HUNT | | PLUMBING PLANS EXAMINER | | CITY OF WEST PALM BEACH | | [email protected] | | 561-248-2703 | | | | | | |
|
|
Review Stop |
G |
GAS REVIEW |
Rev No |
1 |
Status |
F |
Date |
2019-03-15 |
|
|
Cont ID |
|
Sent By |
thunt |
Date |
2019-03-15 |
Time |
06:59 |
Rev Time |
0.00 |
Received By |
thunt |
Date |
2019-03-15 |
Time |
06:59 |
Sent To |
E |
|
Notes |
2019-03-15 07:08:39 | GAS 1ST REVIEW***DENIED** NOTE - A COMPREHENSIVE REVIEW | | COULD NOT BE DONE AT THIS TIME AND ADDITIONAL PLAN | | REVIEW COMMENTS MAY BE GENERATED UPON THE RE-REVIEW OF | | SUBMITTED CORRECTIONS. | | | | | | | | 1) SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE | | LENGTH OF ALL CUT SECTIONS OF PIPE PER 2017 FBC-FUEL | | GAS, SECS. 402.4.1, 402.4.2. OR 2017 FBC-RES SEC. | | G2413.4.1, G2413.4.2 | | | | 2) SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL | | PIPE SIZES, AND THE CORRESPONDING EHD NUMBER OF THE | | CORRUGATED STAINLESS STEEL TUBING | | (IF APPLICABLE) FOR EACH PIPE SIZE. WPB AMENDMENTS TO | | FBC SEC.107.2.1. | | | | 3) TYPE OF GAS (LP OR NATURAL).WPB AMEND. TO FBC SEC. | | 107.2.1.\ | | | | 4) SUBMIT TWO COPIES OF THE APPLICABLE SIZING TABLES | | USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON THE | | PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) FROM | | THE GAS CODE OR OTHER STANDARD THAT WERE USED IN THE | | DESIGN OF THIS GAS SYSTEM. REFER TO THE 2017 FBC-FUEL | | GAS SECS. 401.4, 401.8, 402.3, AND TABLES 402.4 (1) | | THRU 402.4 (37) OR 2017 FBC-RES. SEC. G2413.3, G2412.8, | | G2413.1, G2413.2, & G2413.3 | | | | 5) SUBMIT TWO COPIES OF A HOUSE PLAN SHOWING THE | | LOCATION OF THE TANKLESS WATER HEATER AND THE LOCATION | | AND DISTANCE OF ANY OPERABLE DOORS OR WINDOWS IN | | RELATION TO THE WATER HEATER. THE LOCATION OF THE WATER | | HEATER SHALL COMPLY WITH THE MANUFACTURER'S | | INSTALLATION INSTRUCTIONS. THE HOUSE PLAN CAN BE HAND | | DRAWN. WPB AMEND. TO FBC SEC. 107.2.1 | | | | 6) INDICATE ON THE PLAN IF THE TANKLESS WATER HEATER IS | | THE ONLY GAS APPLIANCE ON THIS SYSTEM? IF NOT, SUBMIT A | | COMPLETE GAS RISER SHOWING ALL PIPE SIZES, TYPE OF | | PIPE, THE DEVELOPED LENGTH TO THE FURTHEST GAS OUTLET, | | THE BTU LOAD OF EACH APPLIANCE, THE PSI OF THE SYSTEM, | | THE TYPE OF GAS AND THE TOTAL BTU LOAD ON THE SYSTEM. | | THESE REQUIREMENTS ALSO APPLY TO A NEW GAS SYSTEM. NOTE | | CITY RECORDS SHOW OTHER GAS APPLIANCES. LIST THE BTU | | LOAD OF EACH APPLIANCE AND THE TOTAL BTU LOAD ON THE | | SYSTEM. REFER TO THE 2017 FBC-FUEL GAS SECS.401.8, | | 402.2, AND TABLES 402.4 (1) THRU 402.4 (37) OR 2017 | | FBC-RES. SEC. G2413.3, G2413.4 AND TABLES G2413.4 (1 ) | | THROUGH G2413.4 (21). | | | | 7) STATE WHICH MODELTANKLESS YOU PLAN TO INSTALLED. | | SUBMIT FULL MANUFACTURER?S SPECIFICATION SHEETS / | | INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO VERIFY | | COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND | | FBC-2017 FUEL GAS CODE SEC. 402.2, AND 301.3 OR 2017 | | FBC-RES. SEC. G2404.3. GAS APPLIANCES SHALL BE LISTED | | AND LABELED. | | | | 8) SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS | | METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE | | OUTLET IN THE BUILDING AND / OR SYSTEM PER THE 2017 | | FBC-FUEL GAS SEC.402.4.1, 402.4.2, OR 2017 FBC-RES. | | SEC. G 2413.4.1, G2413.4.2 | | | | | | | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT | | CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID | | THE PREVIOUSLY REVIEWED SHEETS. | | | | | | TIM HUNT | | PLUMBING PLANS EXAMINER | | CITY OF WEST PALM BEACH | | [email protected] | | 561-248-2703 | | | | | | |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
5 |
Status |
N |
Date |
2020-02-07 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2020-02-07 |
Time |
05:40 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2020-02-05 |
Time |
16:26 |
Sent To |
|
|
Notes |
2020-02-06 16:26:12 | RESUB ROUTED TO TKLARGE |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
4 |
Status |
N |
Date |
2019-09-16 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2019-09-16 |
Time |
11:24 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2019-09-12 |
Time |
13:47 |
Sent To |
|
|
Notes |
2019-09-13 13:47:51 | RESUB ROUTED TO TKLARGE |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2019-08-30 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2019-08-30 |
Time |
12:39 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2019-08-30 |
Time |
12:21 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2019-04-01 |
|
|
Cont ID |
|
Sent By |
thunt |
Date |
2019-04-01 |
Time |
07:46 |
Rev Time |
0.00 |
Received By |
thunt |
Date |
2019-03-28 |
Time |
12:54 |
Sent To |
I |
|
Notes |
2019-03-29 12:55:06 | RESUB ROUTED TO THUNT |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2019-03-20 |
|
|
Cont ID |
|
Sent By |
jleahy |
Date |
2019-03-20 |
Time |
11:07 |
Rev Time |
0.00 |
Received By |
jleahy |
Date |
2019-03-13 |
Time |
13:21 |
Sent To |
|
|
Notes |
2019-03-14 13:21:20 | ROUTED TO PLUMBING INBOX | 2019-02-13 06:43:07 | TANKLESS WATER HEATER, NEEDS REVIEW. |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
3 |
Status |
P |
Date |
2019-09-16 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2019-09-16 |
Time |
11:24 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2019-09-16 |
Time |
10:13 |
Sent To |
|
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
2 |
Status |
F |
Date |
2019-04-01 |
|
|
Cont ID |
|
Sent By |
thunt |
Date |
2019-04-01 |
Time |
07:30 |
Rev Time |
0.00 |
Received By |
thunt |
Date |
2019-04-01 |
Time |
07:29 |
Sent To |
|
|
Notes |
2019-04-01 07:30:12 | PLUMBING 2NDT REVIEW**DENIED** | | | | NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS | | TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE | | GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. | | SEE GAS REVIEW COMMENTS | | | | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED | | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT | | CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID | | THE PREVIOUSLY REVIEWED SHEETS. | | | | | | TIM HUNT | | PLUMBING PLANS EXAMINER | | CITY OF WEST PALM BEACH | | [email protected] | | 561-248-2703 |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
F |
Date |
2019-03-15 |
|
|
Cont ID |
|
Sent By |
thunt |
Date |
2019-03-15 |
Time |
06:56 |
Rev Time |
0.00 |
Received By |
thunt |
Date |
2019-03-15 |
Time |
06:56 |
Sent To |
G |
|
Notes |
2019-03-15 06:59:17 | PLUMBING 1ST REVIEW**DENIED** | | | | NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS | | TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE | | GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. | | SEE GAS REVIEW COMMENTS | | | | PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED | | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. | | WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT | | CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID | | THE PREVIOUSLY REVIEWED SHEETS. | | | | | | TIM HUNT | | PLUMBING PLANS EXAMINER | | CITY OF WEST PALM BEACH | | [email protected] | | 561-248-2703 |
|
|
|