Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2019-02-08 Cont ID  
Sent By pvalenti Date 2019-02-08 Time 17:06 Rev Time 0.00
Received By pvalenti Date 2019-02-08 Time 16:42 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2019-02-04 Cont ID  
Sent By shill Date 2019-02-04 Time 07:41 Rev Time 0.00
Received By pvalenti Date 2019-02-04 Time 10:59 Sent To  
Notes
2019-02-04 08:05:14****CORRECTIONS****
 PETER E VALENTI
 BUILDING PLANS EXAMINER
 [email protected]
 501 PALM STREET
  
 PERMIT REVISION # 19010782
 MASTER # 16090622
  
 APPROVAL IS PENDING:
  
 1. FBC B 109.3 THE TOTAL VALUATION OF $150,000.00
 APPEARS TO BE TOO LOW AS THE WORK UNDER THIS REVISION
 INCLUDES THE ASSOCIATED MECHANICAL, ELECTRIC &
 PLUMBING.
  
 2. FBC B 107 THERE IS NO DETAIL FOR THE BATHROOM
 CEILING FRAMING.
  
 3. FBC B 107 THERE IS NO DETAIL/UL ASSEMBLY PROVIDED
 FOR ATTACHING FRAMING/DRYWALL TO THE ABOVE CEILING
 STEEL BEAMS (W24X117 & HSS 18X16) IN ORDER TO CONTINUE
 WITH THE S6 DETAIL TO THE UNDERSIDE OF ROOF DECK AS
 NOTED ON PLANS.
 PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL COMMENTS MAY
 RESULT IN NEW PLAN REVIEW COMMENTS.
  
 PROVISO:
  
 REQUIRED PRODUCT APPROVALS NEED TO BE SUBMITTED, PRIOR
 TO INSPECTION, INCLUDING:
 A. EXTERIOR STORE FRONT FRAMES/WINDOWS/DOORS.
 B. INTERIOR WINDOWS/DOORS WITHIN BUILDING C OFFICES.

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2019-02-04 Cont ID  
Sent By jpearson Date 2019-02-04 Time 15:59 Rev Time 0.00
Received By jleahy Date 2019-02-04 Time 15:59 Sent To  
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2019-01-23 Cont ID  
Sent By pleduc Date 2019-01-23 Time   Rev Time 0.00
Received By pleduc Date 2019-01-23 Time 10:38 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2019-02-08 Cont ID  
Sent By pvalenti Date 2019-02-08 Time 17:08 Rev Time 0.00
Received By pvalenti Date 2019-02-06 Time 15:06 Sent To  
Notes
2019-02-07 15:06:21RESUB ROUTED TO ZONING INBOX

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2019-02-04 Cont ID  
Sent By jleahy Date 2019-02-04 Time 15:59 Rev Time 0.00
Received By jleahy Date 2019-01-18 Time 15:55 Sent To  
Notes
2019-01-22 15:55:56C01

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2019-02-01 Cont ID  
Sent By ccole Date 2019-02-01 Time 14:36 Rev Time 0.00
Received By hmoser Date 2019-02-01 Time 13:23 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status P Date 2019-01-31 Cont ID  
Sent By gjohnson Date 2019-01-31 Time 12:29 Rev Time 0.00
Received By jesmith Date 2019-01-31 Time 10:59 Sent To  
Notes
2019-01-31 12:29:18APPROVED
 A SEPARATE PERMIT IS REQUIRED FOR THE BACKFLOW DEVICE
  

Review Stop Z ZONING
Rev No 2 Status P Date 2019-02-08 Cont ID  
Sent By jroach Date 2019-02-08 Time 16:02 Rev Time 0.00
Received By jroach Date 2019-02-08 Time 16:02 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status F Date 2019-01-30 Cont ID  
Sent By jroach Date 2019-01-30 Time 09:04 Rev Time 0.00
Received By jroach Date 2019-01-25 Time 15:55 Sent To  
Notes
2019-01-30 09:04:52ZONING PLAN REVIEW
 ___________________________________________
  
 DATE OF REVIEW: 01.30.2019
 PERMIT NO.: 16090622 (REVISION NO. 19010782)
 ___________________________________________
  
 REVIEW STATUS: FAILED
 ___________________________________________
  
 PLEASE PROVIDE A WRITTEN RESPONSE TO THE FOLLOWING PLAN
 REVIEW COMMENTS:
  
 1. THE REVISED PLANS PROVIDE FOR AN ENCLOSED EQUIPMENT
 ROOM WITH ROOF-MOUNTED EQUIPMENT BETWEEN BUILDINGS B &
 C; THIS WAS NOT INCLUDED ON THE ORIGINAL APPROVALS. THE
 SITE PLAN AND ALL SITE DATA CALCULATIONS (GROSS FLOOR
 AREA, PARKING RATIOS, BUILDING COVERAGE, ETC.) SHALL
 ALL BE REVISED ACCORDINGLY. STAFF ALSO HAS OBJECTION
 REGARDING THE ROOF-MOUNTED EQUIPMENT ON THE EQUIPMENT
 ROOM AND VISIBILITY FROM GROUND LEVEL; IT APPEARS THE
 PARAPET ON THIS BUILDING IS NOT HIGH ENOUGH TO SCREEN
 THE EQUIPMENT FROM VIEW.
 ___________________________________________
  
 PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS.
 ___________________________________________
  
 QUESTIONS/COMMENTS, PLEASE CONTACT THE FOLLOWING:
  
 JOHN P. ROACH, AICP, PRINCIPAL PLANNER
 CITY OF WEST PALM BEACH
 DEVELOPMENT SERVICES DEPARTMENT ? PLANNING DIVISION
 401 CLEMATIS STREET - P.O. BOX 3147
 WEST PALM BEACH, FLORIDA 33402
  
 P: 561.822.1448
  
 E: [email protected]
  
 W: WPB.ORG
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved