Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2018-07-05 Cont ID  
Sent By rmcdouga Date 2018-07-05 Time 17:43 Rev Time 0.00
Received By rmcdouga Date 2018-07-05 Time 16:47 Sent To I
Notes
2018-07-05 17:45:48FBC-R4501.19 FINAL INSPECTION. FINAL ELECTRICAL AND
 BARRIER CODE INSPECTION SHALL BE COMPLETED PRIOR TO
 FILLING THE POOL WITH WATER.

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2018-06-28 Cont ID  
Sent By jleahy Date 2018-06-28 Time 15:49 Rev Time 0.00
Received By jleahy Date 2018-06-28 Time 15:49 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 2 Status N Date 2018-07-17 Cont ID  
Sent By thunt Date 2018-07-17 Time 12:34 Rev Time 0.00
Received By thunt Date 2018-07-17 Time 12:34 Sent To  
Notes
2018-07-17 12:34:29A GAS PLAN HAS NOT BEEN INCLUDED IN THIS SUBMITTAL
 PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN PERFORMED AT
 THIS TIME. A SEPARATE GAS PERMIT AND PLANS WILL BE
 REQUIRED FOR A CONTRACTOR TO PERFORM THE RELATED WORK.
 PROVIDE COMPLETE PLANS AND GAS RISER THAT REFLECTS THE
 ENTIRE SCOPE OF GAS WORK TO BE DONE. WPB AMEND. TO FBC
 SEC. 107.2.1.

Review Stop G GAS REVIEW
Rev No 1 Status F Date 2018-06-30 Cont ID  
Sent By thunt Date 2018-06-30 Time 12:15 Rev Time 0.00
Received By thunt Date 2018-06-30 Time 12:15 Sent To  
Notes
2018-06-30 12:17:3906/30/2018 GAS 1ST REVIEW**DENIED**
  
 1) PROVIDE COMPLETE GAS POOL HEATER MANUFACTURE
 INSTALLATION MANUAL.SUBMIT MANUFACTURER?S SPECIFICATION
 SHEETS / INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO
 VERIFY COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND
 FBC-2017 FUEL GAS CODE SEC. 402.2, AND 301.3 OR 2017
 FBC-RES. SEC. G2404.3. GAS APPLIANCES SHALL BE LISTED
 AND LABELED. THE INSTALLATION MANUALS FOR ALL GAS
 APPLIANCES / EQUIPMENT SHALL BE ONSITE AT THE TIME OF
 INSPECTION. FGC SEC.305.1, FBC-RES. SEC.G2408.1
  
 2) PROVIDE A COMPLETE GAS PLAN ANS SEPERATE SUB PERMIT
 APPLICATION.
  
  
  
 TIM HUNT
 PLUMBING INSPECTOR / PLUMBING PLAN REVIEWER
 CITY OF WEST PALM BEACH DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 561-805-6695
 [email protected]

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2018-07-17 Cont ID  
Sent By thunt Date 2018-07-17 Time 12:34 Rev Time 0.00
Received By thunt Date 2018-07-10 Time 15:29 Sent To I
Notes
2018-07-11 15:30:22RESUB ROUTED TO THUNT

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2018-07-05 Cont ID  
Sent By rmcdouga Date 2018-07-05 Time 17:44 Rev Time 0.00
Received By rmcdouga Date 2018-06-25 Time 11:29 Sent To  
Notes
2018-06-26 11:29:25ROUTED TO ZONING INBOX

Review Stop P PLUMBING
Rev No 2 Status P Date 2018-07-17 Cont ID  
Sent By thunt Date 2018-07-17 Time 12:33 Rev Time 0.00
Received By thunt Date 2018-07-17 Time 12:33 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status F Date 2018-06-30 Cont ID  
Sent By thunt Date 2018-06-30 Time 12:17 Rev Time 0.00
Received By thunt Date 2018-06-30 Time 12:17 Sent To B
Notes
2018-06-30 12:21:5006/30/2018 1ST PLUMBING REVIEW**DENIED**
  
 1) PROVIDE POOL MAIN DRAIN MANUFACTURES'S MANUAL
 SHOWING FLOW RATE AND THAT IT MEETS VGB. FBC 107.2.1
  
 2) SEE GAS REVIEW COMMENTS
  
  
 TIM HUNT
 PLUMBING INSPECTOR / PLUMBING PLAN REVIEWER
 CITY OF WEST PALM BEACH DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 561-805-6695
 [email protected]
  
  

Review Stop Z ZONING
Rev No 1 Status P Date 2018-06-27 Cont ID  
Sent By mcruz Date 2018-06-27 Time 13:27 Rev Time 0.00
Received By mcruz Date 2018-06-27 Time 12:29 Sent To  
Notes