Plan Review Details - Permit 18051511
Plan Review Stops For Permit 18051511
Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2018-06-22 Cont ID  
Sent By rmcdouga Date 2018-06-22 Time 11:16 Rev Time 0.00
Received By rmcdouga Date 2018-06-22 Time 11:00 Sent To I
Notes
2018-06-22 11:19:00POOL PERMIT WILL NOT BE ISSUED WITHOUT PLUMBING AND
 ELECTRICAL SUB-PERMITS.

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2018-06-08 Cont ID  
Sent By jleahy Date 2018-06-08 Time 17:00 Rev Time 0.00
Received By jleahy Date 2018-06-08 Time 17:00 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status N Date 2018-06-22 Cont ID  
Sent By tklarge Date 2018-06-22 Time 06:18 Rev Time 0.00
Received By tklarge Date 2018-06-22 Time 06:17 Sent To  
Notes
2018-06-22 06:18:20THERE IS NO GAS ASSOCIATED WITH THIS POOL.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2018-06-30 Cont ID  
Sent By tklarge Date 2018-06-30 Time 06:18 Rev Time 0.00
Received By tklarge Date 2018-06-28 Time 11:00 Sent To P
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2018-06-22 Cont ID  
Sent By rmcdouga Date 2018-06-22 Time 11:16 Rev Time 0.00
Received By rmcdouga Date 2018-05-31 Time 11:54 Sent To  
Notes
2018-06-01 11:54:31ROUTED TO ZONING INBOX

Review Stop P PLUMBING
Rev No 2 Status P Date 2018-06-30 Cont ID  
Sent By tklarge Date 2018-06-30 Time 06:18 Rev Time 0.00
Received By tklarge Date 2018-06-30 Time 06:08 Sent To I
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status F Date 2018-06-22 Cont ID  
Sent By tklarge Date 2018-06-22 Time 06:25 Rev Time 0.00
Received By tklarge Date 2018-06-22 Time 05:45 Sent To  
Notes
2018-06-22 06:25:091) SUBMIT TOTAL DYNAMIC HEAD CALCULATIONS FOR THE
 MAXIMUM SYSTEM FLOW. THE MAXIMUM FLOW OF THE PUMP FROM
 ITS PUMP CURVE IS NO LONGER ALLOWED TO BE USED IN
 DETERMINING MAXIMUM SYSTEM FLOW RATE PER ANSI/APSP/ICC
 7 ? 2013 SECS. 4.4.9, 4.4.9.1. THE 2013 EDITION
 ADDRESSES FLOW RATE IN GALLONS PER MINUTE (GPM). IT
 REQUIRES THAT MAXIMUM SYSTEM FLOW RATE DOES NOT EXCEED
 THE LISTED MAXIMUM FLOW RATE OF THE SUCTION OUTLET
 FITTING ASSEMBLY (DRAIN COVER).
 2) THE SPECIFIC PUMP TO BE USED SHALL BE IDENTIFIED ON
 THE PUMP CURVE SO THE THE MAXIMUM SYSTEM FLOW CAN BE
 CHECKED AGAINST THE TOTAL DYNAMIC HEAD ON CURVE.WPB
 AMEND. TO FBC SEC. 107.2.1.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  

Review Stop Z ZONING
Rev No 1 Status P Date 2018-06-07 Cont ID  
Sent By mcruz Date 2018-06-07 Time 08:52 Rev Time 0.00
Received By mcruz Date 2018-06-07 Time 08:22 Sent To B
Notes
2018-06-07 08:51:12PASSED WITH THE FOLLOWING PROVISO: POOL EQUIPMENT SHALL
 BE AT LEAST 3.5' FROM SIDE PROPERTY LINE.
  
 MAGGIE CRUZ
 ASSOCIATE PLANNER
 PLANNING AND ZONING DEPARTMENT
 TEL: 561-822-1442
 E-MAIL: [email protected]


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved