Plan Review Stops For Permit 18050001 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
P |
Date |
2018-05-14 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2018-05-14 |
Time |
10:02 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2018-05-14 |
Time |
09:57 |
Sent To |
I |
|
Notes |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
2 |
Status |
P |
Date |
2018-05-20 |
|
|
Cont ID |
|
Sent By |
jpearson |
Date |
2018-05-20 |
Time |
08:54 |
Rev Time |
0.00 |
Received By |
jpearson |
Date |
2018-05-20 |
Time |
08:54 |
Sent To |
I |
|
Notes |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
F |
Date |
2018-05-10 |
|
|
Cont ID |
|
Sent By |
jpearson |
Date |
2018-05-10 |
Time |
14:47 |
Rev Time |
0.00 |
Received By |
jpearson |
Date |
2018-05-10 |
Time |
14:47 |
Sent To |
|
|
Notes |
2018-05-10 14:47:10 | CODES IN EFFECT: | | FBC = FLORIDA BUILDING CODE 2017 6TH EDITION | | WPB FBC = WEST PALM BEACH AMENDMENTS TO THE FLORIDA | | BUILDING CODE 2017 6TH ED. | | FBC EC = FLORIDA BUILDING CODE ENERGY CONSERVATION 2017 | | 6TH EDITION | | FBC RE = FLORIDA RESIDENTIAL CODE 2017 6TH EDITION | | NEC = NFPA 70 2014 EDITION, NATIONAL ELECTRICAL CODE | | FS = FLORIDA STATUTES | | | | ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW. | | | | 1. PER THE WPB AMENDMENTS TO THE FBC, PLAN (BOTH | | COPIES) IS REQUIRED TO BEAR THE NAME AND BE SIGNED BY | | THE PERSON RESPONSIBLE FOR THE DESIGN. PROVIDE | | CORRECTION. WPB FBC 107.1, 107.2; FS 471, 481 | | | | END OF COMMENTS. | | | | PLEASE NOTE: SUBMITTAL OF ADDITIONAL AND/OR REVISED | | MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. WHEN | | RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE | | LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY | | RESUBMITTAL FORM. ADDITIONALLY, INSERT CORRECTED PAGES | | INTO THE ORIGINAL SUBMITTAL AND REMOVE OR VOID THE | | PREVIOUSLY REVIEWED SHEETS. | | | | SINCERELY, | | | | JOHN PEARSON | | ELECTRICAL PLANS EXAMINER | | 561-805-6746 | | [email protected] | | |
|
|
Review Stop |
G |
GAS REVIEW |
Rev No |
4 |
Status |
P |
Date |
2018-07-12 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2018-07-12 |
Time |
09:50 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2018-07-11 |
Time |
06:47 |
Sent To |
I |
|
Notes |
|
|
Review Stop |
G |
GAS REVIEW |
Rev No |
3 |
Status |
F |
Date |
2018-06-18 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2018-06-18 |
Time |
13:03 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2018-06-18 |
Time |
12:40 |
Sent To |
I |
|
Notes |
2018-06-18 13:03:10 | 1) THE GAS PLAN SHOWS 1 1/4 INCH AND 3/4 INCH PIPING | | AND THE SHEET YOU HAVE SUBMITTED FOR THE REGULATOR | | SHOWS AN INLET SIZE OF 3/4 INCH AND AN OUTLET SIZE OF 1 | | INCH. CLARIFY. | | 2) SHOW THE ORIFICE SIZE FOR THE REGULATOR BEING USED | | SO THE BTU LOAD CAN BE CHECKED. | | 3) THERE ARE TWO DIFFERENT SETS OF GAS PLANS IN THIS | | SUBMITTAL. REMOVE ALL OLD DOCUMENTS AND SUBMIT ONLY TWO | | SETS OF PLANS FOR REVIEW. WPB AMEND. TO FBC SEC. 107.1. | | | | TIM LARGE | | CHIEF PLUMBING INSPECTOR | | PLUMBING PLAN REVIEW | | 561-805-6692 | | [email protected] |
|
|
Review Stop |
G |
GAS REVIEW |
Rev No |
2 |
Status |
F |
Date |
2018-05-19 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2018-05-19 |
Time |
08:54 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2018-05-19 |
Time |
08:53 |
Sent To |
|
|
Notes |
2018-05-19 08:54:16 | NONE OF THE COMMENTS BELOW HAVE BEEN ADDRESSED FROM THE | | FIRST REVIEW. COMPLY WITH ALL PREVIOUS COMMENTS. | | | | 1) THE COPIES OF THE GAS SIZING TABLES THAT HAVE BEEN | | SUBMITTED ARE FROM THE 2014 FBC-FUEL GAS. SUBMIT THE | | PROPER SIZING TABLES FROM THE 2017 FBC-FUEL GAS. THESE | | TABLES HAVE CHANGED IN THE 2017 FBC-FUEL GAS SO ENSURE | | YOU CHECK THAT THE TABLES YOU ARE SUBMITTING ARE | | CORRECT. TABLE 402.4 (6) FOR SCH. 40 METALLIC PIPE IN | | THE 2017 CODE HAS AN INLET PRESSURE OF 3 PSI WITH A | | PRESSURE DROP OF 2.0 PSI AND TABLE 402.4 (22) FOR PE | | PIPE IN THE 2017 FBC-FUEL GAS IS FOR AN INLET PRESSURE | | OF 2 PSI WITH A PRESSURE DROP OF 1.0 PSI. IT IS OBVIOUS | | YOU CANNOT USE THESE TABLES THAT YOU HAVE SUBMITTED. | | ***NOTE*** | | PLEASE DO NOT TRY TO ENLARGE THE GAS SIZING TABLES. THE | | PROCESS IS MAKING THE TABLES BLURRED AND VERY DIFFICULT | | TO READ. | | 2) THE GAS DRAWING APPEARS TO SHOW A SECOND STAGE | | REGULATOR JUST DOWNSTREAM OF THE GAS METER ON THE | | CONSUMER SIDE. WHY WOULD IT BE LOCATED AT THE OUTLET OF | | THE GAS METER? THAT WOULD MAKE THE PSI TO THE EXISTING | | POOL HEATER LESS THAN 2 PSI. CLARIFY. | | 3) THE GAS RISER IS SHOWING AN 1 1/4 INCH LINE AT 2 PSI | | TO THE EXISTING POOL HEATER WITH A 3/4 INCH SHUTOFF | | VALVE. CLARIFY. | | 4) IS THE EXISTING 1 1/4 INCH GALVANIZED LINE | | UNDERGROUND? I UNDERSTAND IT IS EXISTING BUT GALVANIZED | | PIPING IS NOT PERMITTED TO BE INSTALLED UNDERGROUND. | | ZINC COATINGS (GALVANIZING)SHALL NOT BE DEEMED ADEQUATE | | PROTECTION FOR GAS PIPING UNDERGROUND. 2017 FBC-FUEL | | GAS SEC.404.11. | | IN THE FUTURE, PLEASE ATTEMPT TO SUBMIT GAS DRAWINGS | | THAT ARE EXPANDED SO THAT ALL THE INFORMATION IS NOT | | CRAMMED TOGETHER . WPB AMEND. TO FBC SEC. 107.2.1. | | | | NOTE: I SUGGEST THE A REPRESENTATIVE FROM DIG IT | | UNLIMITED CONTACT ME TO SET UP A MEETING TO GO OVER | | THESE COMMENTS BECAUSE THE COMMENT REGARDING THE SIZING | | TABLES IS APPEARING IN OTHER PLAN REVIEWS FOR DIG IT | | AND I WOULD LIKE TO GET THE ISSUE RESOLVED SO WE CAN | | TRY TO GET YOUR PERMITS ISSUED AND GET YOUR PROJECTS | | GOING. | | | | TIM LARGE | | CHIEF PLUMBING INSPECTOR | | CITY OF WEST PALM BEACH | | 561-805-6692 | | [email protected] | | | | | | | | | | |
|
|
Review Stop |
G |
GAS REVIEW |
Rev No |
1 |
Status |
F |
Date |
2018-05-14 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2018-05-14 |
Time |
04:59 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2018-05-14 |
Time |
04:00 |
Sent To |
|
|
Notes |
2018-05-14 04:59:14 | 1) THE COPIES OF THE GAS SIZING TABLES THAT HAVE BEEN | | SUBMITTED ARE FROM THE 2014 FBC-FUEL GAS. SUBMIT THE | | PROPER SIZING TABLES FROM THE 2017 FBC-FUEL GAS. THESE | | TABLES HAVE CHANGED IN THE 2017 FBC-FUEL GAS SO ENSURE | | YOU CHECK THAT THE TABLES YOU ARE SUBMITTING ARE | | CORRECT. TABLE 402.4 (6) FOR SCH. 40 METALLIC PIPE IN | | THE 2017 CODE HAS AN INLET PRESSURE OF 3 PSI WITH A | | PRESSURE DROP OF 2.0 PSI AND TABLE 402.4 (22) FOR PE | | PIPE IN THE 2017 FBC-FUEL GAS IS FOR AN INLET PRESSURE | | OF 2 PSI WITH A PRESSURE DROP OF 1.0 PSI. IT IS OBVIOUS | | YOU CANNOT USE THESE TABLES THAT YOU HAVE SUBMITTED. | | ***NOTE*** | | PLEASE DO NOT TRY TO ENLARGE THE GAS SIZING TABLES. THE | | PROCESS IS MAKING THE TABLES BLURRED AND VERY DIFFICULT | | TO READ. | | 2) THE GAS DRAWING APPEARS TO SHOW A SECOND STAGE | | REGULATOR JUST DOWNSTREAM OF THE GAS METER ON THE | | CONSUMER SIDE. WHY WOULD IT BE LOCATED AT THE OUTLET OF | | THE GAS METER? THAT WOULD MAKE THE PSI TO THE EXISTING | | POOL HEATER LESS THAN 2 PSI. CLARIFY. | | 3) THE GAS RISER IS SHOWING AN 1 1/4 INCH LINE AT 2 PSI | | TO THE EXISTING POOL HEATER WITH A 3/4 INCH SHUTOFF | | VALVE. CLARIFY. | | 4) IS THE EXISTING 1 1/4 INCH GALVANIZED LINE | | UNDERGROUND? I UNDERSTAND IT IS EXISTING BUT GALVANIZED | | PIPING IS NOT PERMITTED TO BE INSTALLED UNDERGROUND. | | ZINC COATINGS (GALVANIZING)SHALL NOT BE DEEMED ADEQUATE | | PROTECTION FOR GAS PIPING UNDERGROUND. 2017 FBC-FUEL | | GAS SEC.404.11. | | IN THE FUTURE, PLEASE ATTEMPT TO SUBMIT GAS DRAWINGS | | THAT ARE EXPANDED SO THAT ALL THE INFORMATION IS NOT | | CRAMMED TOGETHER . WPB AMEND. TO FBC SEC. 107.2.1. | | | | NOTE: I SUGGEST THE A REPRESENTATIVE FROM DIG IT | | UNLIMITED CONTACT ME TO SET UP A MEETING TO GO OVER | | THESE COMMENTS BECAUSE THE COMMENT REGARDING THE SIZING | | TABLES IS APPEARING IN OTHER PLAN REVIEWS FOR DIG IT | | AND I WOULD LIKE TO GET THE ISSUE RESOLVED SO WE CAN | | TRY TO GET YOUR PERMITS ISSUED AND GET YOUR PROJECTS | | GOING. | | | | TIM LARGE | | CHIEF PLUMBING INSPECTOR | | CITY OF WEST PALM BEACH | | 561-805-6692 | | [email protected] | | | | | | | | | | |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
4 |
Status |
N |
Date |
2018-07-12 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2018-07-12 |
Time |
09:51 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2018-07-06 |
Time |
13:31 |
Sent To |
|
|
Notes |
2018-07-09 13:31:21 | RESUB ROUTED TO TKLARGE |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
3 |
Status |
N |
Date |
2018-06-18 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2018-06-18 |
Time |
13:03 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2018-06-12 |
Time |
10:57 |
Sent To |
|
|
Notes |
2018-06-13 10:57:31 | RESUB ROUTED TO TKLARGE |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
|
|
|
Cont ID |
|
Sent By |
|
Date |
2018-05-20 |
Time |
|
Rev Time |
0.00 |
Received By |
lmarchan |
Date |
2018-05-17 |
Time |
11:01 |
Sent To |
|
|
Notes |
2018-05-18 11:02:06 | RESUB ROUTED TO TKLARGE |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2018-05-14 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2018-05-14 |
Time |
10:07 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2018-05-01 |
Time |
09:47 |
Sent To |
|
|
Notes |
2018-05-02 09:47:54 | ROUTED TO ZONING INBOX |
|
|
Review Stop |
Z |
ZONING |
Rev No |
2 |
Status |
P |
Date |
2018-07-23 |
|
|
Cont ID |
|
Sent By |
mcruz |
Date |
2018-07-23 |
Time |
08:55 |
Rev Time |
0.00 |
Received By |
mcruz |
Date |
2018-07-23 |
Time |
08:51 |
Sent To |
PC |
|
Notes |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
P |
Date |
2018-07-23 |
|
|
Cont ID |
|
Sent By |
mcruz |
Date |
2018-05-08 |
Time |
|
Rev Time |
|
Received By |
mcruz |
Date |
2018-05-08 |
Time |
|
Sent To |
B |
|
Notes |
2018-05-08 10:47:36 | ZONING REVIEW PASSED - PLEASE NOTE GENERATOR SHALL BE | | AT LEAST 4' FROM SIDE PROPERTY LINE. | | M. CRUZ | | ASSOCIATE PLANNER | | 561-822-1442 | | [email protected] |
|
|