2018-03-08 15:15:10 | 03/08/2018 GAS 1ST REVIEW**DENIED** |
| |
| NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS |
| TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| |
| 1) VALUE: THE PERMIT VALUE MUST INCLUDE THE COST OF ALL |
| GAS APPLIANCES. THE APPROVED PLAN DOES NOT SHOW ANY |
| APPLIANCES BEING OF GAS. WPB AMEND TO FBC109.3 BUILDING |
| PERMIT VALUATIONS. IF, IN THE OPINION OF THE BUILDING |
| OFFICIAL, THE CLAIMED VALUATION OF |
| BUILDING, ALTERATION, STRUCTURE, ELECTRICAL, GAS, |
| MECHANICAL OR PLUMBING SYSTEMS APPEARS TO BE |
| UNDERESTIMATED ON THE APPLICATION, THE PERMIT SHALL BE |
| DENIED, UNLESS THE APPLICANT CAN SHOW DETAILED, |
| QUANTITY ESTIMATES, AND/OR BONA FIDE SIGNED CONTRACTS |
| (EXCLUDING LAND VALUE) TO MEET THE APPROVAL OF THE |
| BUILDING OFFICIAL. FOR PERMITTING PURPOSES, VALUATION |
| OF BUILDINGS AND SYSTEMS SHALL BE TOTAL REPLACEMENT |
| VALUE TO INCLUDE STRUCTURAL, ELECTRIC, PLUMBING, |
| MECHANICAL, INTERIOR FINISH, RELATIVE SITE WORK, |
| ARCHITECTURAL AND DESIGN FEES, MARKETING COSTS, |
| OVERHEAD AND PROFIT; EXCLUDING ONLY LAND VALUE. |
| VALUATION REFERENCES MAY INCLUDE THE LATEST PUBLISHED |
| DATA OF NATIONAL CONSTRUCTION COST ANALYSIS SERVICES |
| (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY |
| INTERNATIONAL CODE CONGRESS. |
| |
| 2) YOUR PROPOSAL DOES NOT INCLUDE THE TANKLESS WATER |
| HEATER BUT SHOW A TANKLESS WATER HEATER ON THE |
| ISOMETRIC. FBC 107.2.1 |
| |
| 3) YOU SHOW 48? AS LONGEST LENGTH BUT JUST THE |
| UNDERGROUND P.E ON YOUR ISOMETRIC IS 50?. SHOW THE |
| DISTANCE FROM THE POINT OF DELIVERY, (GAS METER / MP |
| REGULATOR / LP TANK) TO THE MOST REMOTE OUTLET IN THE |
| BUILDING AND / OR SYSTEM PER THE 2014 FBC-FUEL GAS |
| SEC.402.4.1 OR 2014 FBC-RES. SEC. G 2413.3. |
| |
| 4) SUBMIT CALCULATIONS FOR COMBUSTION AIR PER THE 2014 |
| FBC-FUEL GAS CODE SEC.304.1, 614.5 (CLOTHES DRYERS) OR |
| 2014 FBC-RES. SEC. G 2407.1 AND G2439.4 (CLOTHES |
| DRYERS). SUBMIT COMBUSTION AIR CALCULATIONS FOR THE |
| ADDED GAS APPLIANCES. WHERE COMBUSTION AIR IS PROVIDED |
| BY THE BUILDING?S MECHANICAL VENTILATION SYSTEM, THE |
| SYSTEM SHALL PROVIDE THE SPECIFIED COMBUSTION AIR RATE |
| IN ADDITION TO THE REQUIRED VENTILATION AIR. FGC |
| SEC.304.9.3 OR FBCR G2407.9.3. |
| |
| |
| 5) SUBMIT MANUFACTURER?S SPECIFICATION SHEETS / |
| INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO VERIFY |
| COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND |
| FBC-2014 FUEL GAS CODE SEC. 402.2, AND 301.3 OR 2014 |
| FBC-RES. SEC. G2404.3. GAS APPLIANCES SHALL BE LISTED |
| AND LABELED. THE INSTALLATION MANUALS FOR ALL GAS |
| APPLIANCES / EQUIPMENT SHALL BE ONSITE AT THE TIME OF |
| INSPECTION. FGC SEC.305.1, FBC-RES. SEC.G2408.1 |
| |
| 6) SUBMIT TWO COPIES OF A HOUSE PLAN SHOWING THE |
| LOCATION OF THE TANKLESS WATER HEATER AND THE LOCATION |
| AND DISTANCE OF ANY OPERABLE DOORS OR WINDOWS IN |
| RELATION TO THE WATER HEATER. THE LOCATION OF THE WATER |
| HEATER SHALL COMPLY WITH THE MANUFACTURER'S |
| INSTALLATION INSTRUCTIONS. THE HOUSE PLAN CAN BE HAND |
| DRAWN. WPB AMEND. TO FBC SEC. 107.2.1. |
| |
| 7) SHOW THE LOCATION OF ALL MP (STEP-DOWN) REGULATORS. |
| A LISTED SHUTOFF VALVE SHALL BE INSTALLED IMMEDIATELY |
| AHEAD OF EACH MP REGULATOR. FBC-FUEL GAS SEC.409.4, |
| FBC-RESIDENTIAL SEC. G 2420.4. I |
| |
| 8) SUBMIT MANUFACTURER?S SPECIFICATIONS FOR THE |
| PRESSURE REGULATORS. REGULATORS INSTALLED ON THE |
| EXTERIOR OF THE BUILDING SHALL BE APPROVED FOR OUTDOOR |
| INSTALLATION. 2014 FGC SEC.410.1. |
| |
| 9) SHOW THE DISTANCE FROM THE 2 PSI REGULATOR TO THE |
| APPLIANCE. COMPLY WITH 2014 FBC-FUEL GAS TABLE 402.4 |
| (28) FOR THE PROPER PIPE SIZE AND BTU LOAD. |
| |