Plan Review Details - Permit 18021086
Plan Review Stops For Permit 18021086
Review Stop ENG ENGINEERING CSD
Rev No 1 Status N Date 2018-03-01 Cont ID  
Sent By thunt Date 2018-03-01 Time 08:44 Rev Time 0.00
Received By thunt Date 2018-03-01 Time 08:43 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2018-03-27 Cont ID  
Sent By tklarge Date 2018-03-27 Time 06:00 Rev Time 0.00
Received By tklarge Date 2018-03-27 Time 05:47 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2018-03-19 Cont ID  
Sent By tklarge Date 2018-03-19 Time 10:02 Rev Time 0.00
Received By tklarge Date 2018-03-14 Time 13:10 Sent To  
Notes
2018-03-16 13:11:10RESUB ROUTED TO THUNT

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2018-03-01 Cont ID  
Sent By thunt Date 2018-03-01 Time 08:50 Rev Time 0.00
Received By thunt Date 2018-02-26 Time 09:21 Sent To I
Notes
2018-02-27 09:22:09PLUMB<5K

Review Stop P PLUMBING
Rev No 3 Status P Date 2018-03-27 Cont ID  
Sent By tklarge Date 2018-03-27 Time 05:59 Rev Time 0.00
Received By tklarge Date 2018-03-27 Time 05:47 Sent To I
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status F Date 2018-03-19 Cont ID  
Sent By tklarge Date 2018-03-19 Time 09:57 Rev Time 0.00
Received By tklarge Date 2018-03-19 Time 05:35 Sent To I
Notes
2018-03-19 10:02:041) SUBMIT SIZING CALCULATIONS AS TO HOW YOU ARRIVED AT
 THE SIZE OF THE UNIT TO BE INSTALLED. SUBMIT SIZING
 CALCULATIONS BASED ON THE SIZING EQUATION FOUND IN THE
 PLUMBING AND DRAINAGE INSTITUTE'S STANDARD PDI-G101.
 2ND REQUEST.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  
  

Review Stop P PLUMBING
Rev No 1 Status F Date 2018-03-01 Cont ID  
Sent By thunt Date 2018-03-01 Time 08:38 Rev Time 0.00
Received By thunt Date 2018-03-01 Time 08:38 Sent To  
Notes
2018-03-01 08:43:5103/01/2018 1ST PLUMBING REVIEW**DENIED**
  
  
 1) PROVIDE FULL MANUFACTURES INSTALLATION MANUAL. FBC
 107.2.1
  
 2) SHOW HOW YOU SIZED THE SYSTEM AND THAT THIS
 INTERCEPTOR COMPLIES WITH FBC P1003.3.4
  
 3) SHOW ON YOUR ISOMETRIC DRAWING THE PIPING SIZE AND
 DEVELOPED LENGTH OF EACH SECTION OF PIPING. FBC 107.3.5
  
 4) ADD P-TRAP AND VENT COMPLYING WITH 1002.1 AND 901.2
 TO YOUR ISOMETRIC DRAWING
  
 5) OVERALL VALUE OF JOB SEEMS LOW. PROVIDE SIGN
 CONTRACT SHOWING FULL VALUE OF JOB INCLUDING ALL
 MATERIAL, LABOR, OVERHEAD, AND PROFITS. WPB AMEND TO
 FBC 109.3
  
  
 TIM HUNT
 PLUMBING INSPECTOR / PLUMBING PLAN REVIEWER
 CITY OF WEST PALM BEACH DEVELOPMENT SERVICES DEPARTMENT