Plan Review Details - Permit 18020216
Plan Review Stops For Permit 18020216
Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2018-02-21 Cont ID  
Sent By jgomez Date 2018-02-21 Time 12:31 Rev Time 0.00
Received By jgomez Date 2018-02-21 Time 09:10 Sent To  
Notes
2018-02-21 09:37:09BUILDING REVIEW APPROVED WITH PROVISO;
 1- SEE DETAIL "H" ON SHEET 3 OF 10 AND DETAIL "J" ON
 SHEET 4 OF 10 FOR PROPOSED MOUNTING CONDITIONS. VERIFY
 MOUNTING IN FIELD.
  
 2- VERIFY TOP MOUNTING TO WOOD FRAMING MEMBERS NOT
 PLYWOOD.
  
 3- VERIFY BOTTOM MOUNTING TO FILLED CONCRETE BLOCK NOT
 WINDOW VENEER.

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2018-02-15 Cont ID  
Sent By jgomez Date 2018-02-14 Time 18:28 Rev Time 0.00
Received By jgomez Date 2018-02-14 Time 16:31 Sent To  
Notes
2018-02-14 16:32:01RESIDENTIAL (R3) ALTERATION, SECOND BUILDING REVIEW
 CHECKLIST.
 CODE: FBC 6TH EDITION (2017).
  
 1- PROPOSED INSTALLATION STILL IS NOT CLEAR. THERE ARE
 FOUR DIFFERENT MOUNTING CONDITIONS SHOWN (A, B, E AND
 J). IT IS NOT CLEAR HOW THE FOUR MOUNTING CONDITIONS
 ARE GOING TO BE MET IF THE 3 WINDOWS ARE LOCATED IN THE
 SAME WALL PLANE. IN ADDITION, CLARIFY WHY ONLY WINDOW
 #3 HAS A DIFFERENT CONNECTION TYPE AT THE BOTTOM. SEC.
 107.2.1 CITY AMENDMENTS.
  
 2- INSTALLATION SCHEDULE SPECIFIES CONCRETE AS THE
 SUBSTRATE WHERE THE STORM PANELS ARE GOING TO BE
 INSTALLED. ACCORDING TO CITY RECORDS. THESE ARE ARCHED
 WINDOWS. THERE IS WOOD FRAME AROUND TOP OF WINDOW. THIS
 IS NOT CONCRETE SUBSTRATE. CLARIFY IF PANELS ARE GOING
 TO BE INSTALLED AT THE PRECAST LINTEL OR AT THE WOOD
 FRAMED AREA. BOTTOM OF WINDOW IS CONCRETE BLOCK. REVISE
 SUBSTRATE INFORMATION SHOWN ON THE INSTALLATION
 SCHEDULE. AND, REVISE ANCHOR TYPE AND SPACING
 ACCORDINGLY. SEC. 107.2.1 CITY AMENDMENTS.
  
 3- EDGE DISTANCE NEED TO TAKE INTO CONSIDERATION THE
 THICKNESS OF THE STUCCO OR WALL FINISH. REVISE EDGE
 DISTANCE ON THE INSTALLATION SCHEDULE AS REQUIRED.
 SEC.107.2.1 CITY AMENDMENTS.
  
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 (561)805-6712
 [email protected]

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2018-02-08 Cont ID  
Sent By jgomez Date 2018-02-08 Time 09:27 Rev Time 0.00
Received By jgomez Date 2018-02-08 Time 07:50 Sent To  
Notes
2018-02-08 09:30:56RESIDENTIAL (R3) ALTERATION, BUILDING REVIEW COMMENTS.
 CODE: FBC 6TH EDITION (2017).
  
 1- PROPOSED INSTALLATION IS NOT CLEAR. DRAWING #2 OF 10
 OF FLORIDA PRODUCT APPROVAL FL12856-R6 SUBMITTED SHOWS
 AN "H" HEADER AND "F" TRACK CIRCLED AS THE PROPOSED
 INSTALLATION, WHILE DRAWING #3 OF 10 SHOWS "DIRECT
 MOUNT SECTION CIRCLED WITH NO "H" HEADER OR "F" TRACK
 INSTALLATION. REVISE AS REQUIRED TO MATCH TO VERIFY
 PROPOSED INSTALLATION. NOTE: CONNECTION TYPES ARE
 DIFFERENT FOR EACH DIFFERENT APPLICATION. THAT'S WHY IS
 IMPORTANT TO KNOW THE EXACT PROPOSED INSTALLATION. SEC.
 107.2.1 CITY AMENDMENTS.
  
 2- INSTALLATION SCHEDULE SPECIFIES CONCRETE BLOCK AS
 THE SUBSTRATE WHERE THE STORM PANELS ARE GOING TO BE
 INSTALLED. BUT, ANCHOR SCHEDULE ON SHEET #8 OF 10 OF
 FLORIDA PRODUCT APPROVAL SUBMITTED SHOWS ANCHOR
 SCHEDULE CIRCLED FOR CONCRETE SUBSTRATE. REVISE AS
 REQUIRED. NEED TO USE THE ANCHOR SCHEDULE FOR CONCRETE
 BLOCK AND REVISE ANCHOR TYPE, SPACING AND EDGE DISTANCE
 ACCORDINGLY. OR, PROVIDE PROOF THAT THE SUBSTRATE IS
 CONCRETE WITH THE STRENGTH REQUIRED BY THE CONCRETE
 ANCHOR SCHEDULE. SEC. 107.2.1 CITY AMENDMENTS.
  
 3- CLARIFY WHY THE INSTALLATION SCHEDULE SUBMITTED
 INDICATES THAT SHUTTERS ARE GOING TO BE INSTALLED
 HORIZONTALLY IF BASED ON THE SHUTTER SPAN SHOWN, IT
 LOOKS LIKE THE PANELS ARE GOING TO BE INSTALLED
 VERTICALLY NOT HORIZONTALLY. REVISE AS REQUIRED. SEC.
 107.2.1 CITY AMENDMENTS.
  
 IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT
 JULIO GOMEZ
 COMMERCIAL COMBINATION PLANS EXAMINER
 DEVELOPMENT SERVICES DEPARTMENT
 BUILDING DIVISION
 (561)805-6712
 [email protected]

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2018-02-21 Cont ID  
Sent By jgomez Date 2018-02-21 Time 12:36 Rev Time 0.00
Received By jgomez Date 2018-02-21 Time 09:10 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2018-02-15 Cont ID  
Sent By jgomez Date 2018-02-14 Time 18:28 Rev Time 0.00
Received By jgomez Date 2018-02-13 Time 09:25 Sent To  
Notes
2018-02-14 09:25:38RESUB ROUTED TO JGOMEZ

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2018-02-08 Cont ID  
Sent By jgomez Date 2018-02-08 Time 10:02 Rev Time 0.00
Received By jgomez Date 2018-02-06 Time 13:03 Sent To I
Notes
2018-02-07 13:04:02BLDG <5K