Plan Review Details - Permit 17110403
Plan Review Stops For Permit 17110403
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2018-02-02 Cont ID  
Sent By rmcdouga Date 2018-02-02 Time 07:34 Rev Time 0.00
Received By rmcdouga Date 2018-02-02 Time 07:22 Sent To I
Notes
2018-02-02 07:35:54CONTRACT SUBMITTED HAS A VALUE OF $35,500.00 FOR THE
 POOL. PERMIT VALUE HAS BEEN ADJUSTED ACCORDINGLY.

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2017-11-27 Cont ID  
Sent By rmcdouga Date 2017-11-27 Time 07:42 Rev Time 0.00
Received By rmcdouga Date 2017-11-27 Time 06:54 Sent To E
Notes
2017-11-27 07:16:06PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC FIFTH EDITION (2014)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) THE VALUATION FOR THE POOL OF $13,500.00 IS LOW.
 SUBMIT A COPY OF THE SIGNED CONTRACT FOR THE POOL. FBC
 109.3 BUILDING PERMIT VALUATION. FOR PERMITTING
 PURPOSES, VALUATION OF BUILDINGS AND SYSTEMS SHALL BE
 TOTAL REPLACEMENT VALUE TO INCLUDE STRUCTURAL,
 ELECTRIC, PLUMBING, MECHANICAL, INTERIOR FINISH,
 RELATIVE SITE WORK, ARCHITECTURAL AND DESIGN FEES,
 MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING ONLY
 LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE LATEST
 PUBLISHED DATA OF NATIONAL CONSTRUCTION COST ANALYSIS
 SERVICES (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY
 INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT
 VALUATION SHALL BE SET BY THE BUILDING OFFICIAL.
  
 FBC-R4501.19 FINAL INSPECTION. FINAL ELECTRICAL AND
 BARRIER CODE INSPECTION SHALL BE COMPLETED PRIOR TO
 FILLING THE POOL WITH WATER.
  
  

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2017-11-27 Cont ID  
Sent By rmcdouga Date 2017-11-27 Time 07:52 Rev Time 0.00
Received By jleahy Date 2017-11-27 Time 12:09 Sent To I
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status N Date 2017-11-20 Cont ID  
Sent By tklarge Date 2017-11-20 Time 06:28 Rev Time 0.00
Received By tklarge Date 2017-11-20 Time 06:22 Sent To  
Notes
2017-11-20 06:28:36THERE IS A GAS HEATER ON THIS POOL.A GAS PLAN HAS NOT
 BEEN INCLUDED IN THIS SUBMITTAL PACKAGE. A GAS PLAN
 REVIEW HAS NOT BEEN PERFORMED AT THIS TIME. A GAS
 PERMIT IS REQUIRED FOR A CONTRACTOR TO PERFORM THE
 RELATED WORK. PROVIDE COMPLETE PLANS THAT REFLECT THE
 ENTIRE SCOPE OF GAS WORK TO BE DONE. WPB AMEND. TO FBC
 SEC.107.2.1.
 GAS APPLIANCES SHALL BE LISTED AND LABELED PER THE
 FBC-R, SEC. G2404.3.
 GAS APPLIANCES SHALL BE LISTED AND LABELED PER FBC-FUEL
 GAS SEC. 301.3.
  
 A SEPARATE PERMIT IS REQUIRED FOR THE GAS INSTALLATION.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  

Review Stop HIST HISTORICAL
Rev No 1 Status P Date 2017-11-15 Cont ID  
Sent By destabro Date 2017-11-15 Time 10:20 Rev Time 0.00
Received By destabro Date 2017-11-15 Time 10:20 Sent To B
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2018-02-02 Cont ID  
Sent By rmcdouga Date 2018-02-02 Time 07:36 Rev Time 0.00
Received By rmcdouga Date 2018-01-31 Time 13:42 Sent To  
Notes
2018-02-01 13:42:46RESUB ROUTED TO RMCDOUGAL

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2017-11-27 Cont ID  
Sent By jleahy Date 2017-11-27 Time 12:09 Rev Time 0.00
Received By jleahy Date 2017-11-09 Time 09:21 Sent To  
Notes
2017-11-13 09:21:59ROUTED TO ZONING

Review Stop P PLUMBING
Rev No 1 Status P Date 2017-11-20 Cont ID  
Sent By tklarge Date 2017-11-20 Time 06:22 Rev Time 0.00
Received By tklarge Date 2017-11-20 Time 05:57 Sent To  
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2017-11-15 Cont ID  
Sent By destabro Date 2017-11-15 Time 10:44 Rev Time 0.00
Received By destabro Date 2017-11-15 Time 10:44 Sent To B
Notes
2017-11-15 10:46:0711/15/2017 - MEETS SIDE AND REAR SETBACK REQUIREMENTS
 (LDR SEC. 94-304 ACCES. STRUCTURES, 94-305 SETBACKS).
 DLE


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved