Plan Review Details - Permit 17090100
Plan Review Stops For Permit 17090100 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
P |
Date |
2017-09-13 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2017-09-13 |
Time |
17:21 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2017-09-13 |
Time |
17:15 |
Sent To |
|
|
Notes |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
P |
Date |
2017-09-18 |
|
|
Cont ID |
|
Sent By |
jleahy |
Date |
2017-09-18 |
Time |
17:20 |
Rev Time |
0.00 |
Received By |
jleahy |
Date |
2017-09-18 |
Time |
17:20 |
Sent To |
|
|
Notes |
|
|
Review Stop |
G |
GAS REVIEW |
Rev No |
1 |
Status |
N |
Date |
2017-09-13 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2017-09-13 |
Time |
17:21 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2017-09-13 |
Time |
17:21 |
Sent To |
|
|
Notes |
2017-09-13 17:22:16 | NO GAS SHOWN ON THE PLANS. A SEPARATE PERMIT, | | APPLICATION AND REVIEW IS REQUIRED. |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2017-09-28 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2017-09-28 |
Time |
05:49 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2017-09-26 |
Time |
13:14 |
Sent To |
|
|
Notes |
2017-09-27 13:14:33 | REVISION ROUTED TO TKLARGE |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2017-09-18 |
|
|
Cont ID |
|
Sent By |
jleahy |
Date |
2017-09-18 |
Time |
17:20 |
Rev Time |
0.00 |
Received By |
jleahy |
Date |
2017-09-05 |
Time |
14:44 |
Sent To |
|
|
Notes |
2017-09-06 14:44:18 | ROUTED TO ZONING |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
2 |
Status |
P |
Date |
2017-09-28 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2017-09-28 |
Time |
05:48 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2017-09-28 |
Time |
05:28 |
Sent To |
|
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
F |
Date |
2017-09-18 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2017-09-18 |
Time |
09:48 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2017-09-14 |
Time |
08:45 |
Sent To |
|
|
Notes |
2017-09-18 09:48:36 | 1) SHT. 2 OF 3 - PIPING DIAGRAM - SHOWS A 2 INCH MAIN | | DRAIN TO THE EXISTING POOL PUMP AND ALSO SHOWS A 3 INCH | | MAIN DRAIN CONNECTED TO THE PUMP, FILTER AND HEATER. | | CLARIFY. | | 2) SHT.2 OF 3 - THE PIPING DIAGRAM SHOWS A 3 INCH | | RETURN TO THE SPA CONNECTED TO THE 2 HP BLOWER AND THE | | PIPING DIAGRAM ALSO SHOWS A 2 INCH RETURN TO THE SPA | | FROM THE EXISTING POOL PUMP. CLARIFY. | | 3) SHT. 2 OF 3 - THE SKIMMER AND VAC DETAIL SHOWS A 3 | | INCH RETURN TO THE SPA AND THE PIPING DIAGRAM SHOWS A 3 | | INCH AND ALSO A 2 INCH RETURN TO THE SPA. CLARIFY. | | 4) SHT. 3 OF 3 - THERE IS A AREA ON THE PLAN LABELED AS | | " ASPS-15" BUT ALL THE ITEMS IN THIS AREA ARE BLANK. | | CLARIFY. | | 5) THE PLAN SHOWS AN EXISTING PUMP BUT SPECS HAVE BEEN | | SUBMITTED FOR A NEW PUMP. CLARIFY. | | | | I AM CONFUSED AS TO THIS PIPING ARRANGEMENT .PLEASE | | SUBMIT A NARRATIVE THAT EXPLAINS THIS PIPING | | ARRANGEMENT. | | | | TIM LARGE | | CHIEF PLUMBING INSPECTOR | | PLUMBING PLAN REVIEW | | 561-805-6692 | | [email protected] | | | | |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
P |
Date |
2017-09-07 |
|
|
Cont ID |
|
Sent By |
njwira |
Date |
2017-09-07 |
Time |
16:56 |
Rev Time |
0.00 |
Received By |
njwira |
Date |
2017-09-07 |
Time |
15:59 |
Sent To |
|
|
Notes |
|
|
|