Plan Review Stops For Permit 17081507 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
P |
Date |
2018-01-19 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2018-01-19 |
Time |
17:01 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2018-01-19 |
Time |
17:01 |
Sent To |
|
|
Notes |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2018-01-19 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2018-01-19 |
Time |
17:01 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2018-01-19 |
Time |
14:08 |
Sent To |
|
|
Notes |
2018-01-19 14:10:35 | 1/19 CONTRACTOR CALLED FOR STATUS, FEES WERE PAID 12/7, | | ROUTED TO SH DESK | | | | |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2017-09-14 |
|
|
Cont ID |
|
Sent By |
shill |
Date |
2017-09-14 |
Time |
09:57 |
Rev Time |
0.00 |
Received By |
shill |
Date |
2017-08-31 |
Time |
13:17 |
Sent To |
|
|
Notes |
2017-09-05 13:09:33 | REVISION ROUTED TO SHILL |
|
|
|