Plan Review Details - Permit 17080065
Plan Review Stops For Permit 17080065
Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2017-08-04 Cont ID  
Sent By pleduc Date 2017-08-04 Time   Rev Time 0.00
Received By pleduc Date 2017-08-03 Time 11:16 Sent To M
Notes
2017-08-04 10:33:54THIS PLAN WAS REVIEWED AND APPROVED BY PETER LEDUC,
 FIRE MARSHAL, WITH THE FOLLOWING COMMENTS:
  
 PLEASE CONSIDER THE FOLLOWING AS PROVISO:
  
 THESE PROVISO COMMENTS WILL BE VERIFIED AND CONFIRMED
 AT THE TIME OF FIRE INSPECTION. FAILURE TO FOLLOW THESE
 PROVISO COMMENTS WILL RESULT IN A FAILED FIRE
 INSPECTION.
  
  
  
 1) TEST AT WORKING PRESSURE FOR 2 HOURS PER NFPA 13.
  
 USE FIRE PUMP TEST PRESSURE FOR WORKING PRESSURE
 CALCULATIONS.
  
 24.2.1.6 MODIFICATIONS THAT CANNOT BE ISOLATED, SUCH AS
 RELOCATED DROPS, SHALL NOT REQUIRE TESTING IN EXCESS OF
 SYSTEM WORKING PRESSURE.
 24.2.1.7 LOSS SHALL BE DETERMINED BY A DROP IN GAUGE
 PRESSURE OR VISUAL LEAKAGE.
  
  
 3.3.19 SYSTEM WORKING PRESSURE. THE MAXIMUM ANTICIPATED
 STATIC (NONFLOWING) OR FLOWING PRESSURE APPLIED TO
 SPRINKLER SYSTEM COMPONENTS EXCLUSIVE OF SURGE
 PRESSURES AND EXCLUSIVE OF PRESSURE FROM THE FIRE
 DEPARTMENT CONNECTION.
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  
  

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2017-08-11 Cont ID  
Sent By hmoser Date 2017-08-11 Time 10:39 Rev Time 0.00
Received By hmoser Date 2017-08-01 Time 11:31 Sent To  
Notes
2017-08-02 11:31:11ROUTED TO FIRE INBOX

Review Stop M MECHANICAL (A/C)
Rev No 1 Status P Date 2017-08-11 Cont ID  
Sent By hmoser Date 2017-08-11 Time 10:35 Rev Time 0.00
Received By hmoser Date 2017-08-11 Time 10:35 Sent To  
Notes
2017-08-11 10:38:40NEED CONTRACTORS SIGNATURE ON EACH PLAN
 BE FOR PERMIT IS ISSUED HM.