Plan Review Details - Permit 17061355
Plan Review Stops For Permit 17061355
Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2017-11-01 Cont ID  
Sent By tmoore Date 2017-11-01 Time 08:16 Rev Time 0.00
Received By tmoore Date 2017-11-01 Time 08:13 Sent To  
Notes
2017-11-01 08:16:11OK TO ISSUE WITH FEES PAID AND DEBRIS DISPOSAL FORM
 FILLED OUT.

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2017-10-20 Cont ID  
Sent By tmoore Date 2017-10-20 Time 15:04 Rev Time 0.00
Received By tmoore Date 2017-10-20 Time 14:54 Sent To  
Notes
2017-10-20 15:03:55APPLICATION DOES NOT INCLUDE;
  
 1) WATER DEPARTMENT CONFIRMATION OF REQUEST TO PULL
 METER, OR, BACKFLOW INSTALLATION PERMIT, OR HYDRANT
 METER ARRANGEMENT.
  
 2) SEWER LATERAL CAPPING PERMIT NUMBER #17061355 DOES
 NOT HAVE AN INSPECTION. WE STILL NEED A #703 FINAL
 PLUMBING CALLED IN AND PASSED.
  
 3) ELECTRICAL CONFIRMATION FROM FPL THAT THE LINE IN
 POWER HAS BEEN SAFED.
  
 4) DEBRIS DISPOSAL FORM COMPLETED. THIS CAN BE DONE AT
 PERMIT PICK UP.

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2017-07-01 Cont ID  
Sent By tmoore Date 2017-07-01 Time 10:20 Rev Time 0.00
Received By tmoore Date 2017-07-01 Time 09:58 Sent To ENG
Notes
2017-07-01 10:20:14VERY LITTLE INFORMATION WAS PROVIDED WITH APPLICATION.
 THE FOLLOWING WILL BE NEEDED PRIOR TO ISSUANCE OF DEMO
 PERMIT.
  
 1) COPY OF AN ASBESTOS ABATEMENT SURVEY AND REMOVAL
 RECEIPT OR SWA CONFIRMATION.
  
 2) COPY OF UTILITY RELEASE FROM FPL.
  
 3) COPY OF UTILITY RELEASE FROM FPU.
  
 4) COPY OF CITY UTILITY (WATER) DEPARTMENT REQUEST TO
 PULL METER AND/OR INSTALL HYDRANT BACKFLOW.
 IF BACKFLOW INSTALLED BY PLUMBER, SEPARATE PERMIT FOR
 THAT IS REQUIRED.UTILITIES WILL MARK LATERAL LOCATIONS
 AND CONFIRM WHEN COMPLETE.
  
 5) SEWER LATERAL CAPPING PERMIT PULLED AND #703 FINAL
 INSPECTION REQUESTED, AND PASSED.
  
 6) COPY OF RODENT LETTER INSPECTION AND TREATMENT
 CONFIRMATION.
  
 7) DEBRIS DISPOSAL FORM FILLED OUT. THIS CAN BE DONE AT
 PICK UP. A SMALL FEE MAY BE ASSOCIATED WITH THIS FORM.
  
 8) COPY OF THE N.O.C. OR NOTICE OF COMMENCEMENT.
  
 9) PASSING PLAN REVIEW RESULTS FROM HISTORIC AND
 ENGINEERING DEPARTMENTS.

Review Stop ENG ENGINEERING CSD
Rev No 1 Status P Date 2017-07-06 Cont ID  
Sent By hhall Date 2017-07-06 Time 10:06 Rev Time 0.00
Received By hhall Date 2017-07-06 Time 10:06 Sent To HIST
Notes
2017-07-06 10:07:27PASSED - NO UTILITY CONFLICTS
 ADDRESS BUILDING ISSUES

Review Stop HIST HISTORICAL
Rev No 1 Status P Date 2017-07-06 Cont ID  
Sent By destabro Date 2017-07-06 Time 15:48 Rev Time 0.00
Received By destabro Date 2017-07-06 Time 15:48 Sent To B
Notes
2017-07-06 15:49:217/6/2017 - NOT HISTORICALLY DESIGNATED, EITHER
 INDIVIDUALLY OR WITHIN A DISTRICT.DLE
2017-07-06 14:33:03ROUTED TO DESIREE ESTABROOK

Review Stop I INCOMING/PROCESSING
Rev No 2 Status   Date   Cont ID  
Sent By   Date   Time   Rev Time 0.00
Received By shill Date 2017-10-19 Time 14:24 Sent To  
Notes
2017-10-19 14:25:06TO TM DESK
 (DOCUMENTS SUBMITTED OK PER RB)
  

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2017-07-06 Cont ID  
Sent By cpuell Date 2017-07-06 Time 16:50 Rev Time 0.00
Received By cpuell Date 2017-06-29 Time 09:10 Sent To  
Notes
2017-06-30 09:10:52ROUTED TO TMOORE'S DESK


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved