Plan Review Details - Permit 16120116
Plan Review Stops For Permit 16120116
Review Stop G GAS REVIEW
Rev No 2 Status P Date 2017-01-17 Cont ID  
Sent By tklarge Date 2017-01-17 Time 06:00 Rev Time 0.00
Received By tklarge Date 2017-01-17 Time 05:53 Sent To  
Notes
***NONE***

Review Stop G GAS REVIEW
Rev No 1 Status F Date 2016-12-31 Cont ID  
Sent By tklarge Date 2016-12-31 Time 06:41 Rev Time 0.00
Received By tklarge Date 2016-12-31 Time 06:20 Sent To  
Notes
2016-12-31 06:41:151) SHOW THE SIZE OF THE LINE FROM THE LP TANK DOME TO
 THE 1ST STAGE REGULATOR.
 2) SHOW THE DISTANCE FROM THE LP DOME TO THE 1ST STAGE
 REGULATOR.
 3) SHOW THE TYPE OF PIPE MATERIAL FROM LP TANK DOME TO
 THE 1ST STAGE REGULATOR.
 4) IF THE STUB IS GALVANIZED, SHOW THE SIZE OF THE
 STUB-UP.
 5) SHOW THE ANTICIPATED BTU LOAD OF THE FUTURE
 APPLIANCE/EQUIPMENT.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2017-01-17 Cont ID  
Sent By tklarge Date 2017-01-17 Time 06:00 Rev Time 0.00
Received By tklarge Date 2017-01-10 Time 13:27 Sent To  
Notes
2017-01-10 13:27:40RESUB ROUTED TO TKLARGE

Review Stop I INCOMING/PROCESSING
Rev No 2 Status F Date 2017-01-03 Cont ID  
Sent By tklarge Date 2017-01-03 Time 10:09 Rev Time 0.00
Received By tklarge Date 2016-12-28 Time 09:10 Sent To  
Notes
2016-12-29 09:10:30RESUB ROUTED TO TKLARGE

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2016-12-12 Cont ID  
Sent By tklarge Date 2016-12-12 Time 08:53 Rev Time 0.00
Received By tklarge Date 2016-12-05 Time 11:25 Sent To  
Notes
2016-12-06 11:26:02PLUMB <5K

Review Stop P PLUMBING
Rev No 2 Status N Date 2016-12-31 Cont ID  
Sent By tklarge Date 2016-12-31 Time 06:20 Rev Time 0.00
Received By tklarge Date 2016-12-31 Time 06:08 Sent To  
Notes
2016-12-31 06:20:59THIS NEEDS TO BE CHANGED TO A GAS PERMIT.

Review Stop P PLUMBING
Rev No 1 Status F Date 2016-12-12 Cont ID  
Sent By tklarge Date 2016-12-12 Time 08:53 Rev Time 0.00
Received By tklarge Date 2016-12-12 Time 06:10 Sent To  
Notes
2016-12-12 06:57:561) SHOW THE DISTANCE FROM THE RELIEF VALVE ON THE LP
 TANK TO THE EXTERIOR WALL OF THE STRUCTURE. COMPLY WITH
 NFPA 58 SEC.6.3.4.2.
 2) SHOW THE DISTANCE OF THE LP TANK FROM THE PROPERTY
 LINE.COMPLY WITH NFPA 58 TABLE 6.3.1.
 3) YOU HAVE SUBMITTED TWO DIFFERENT SIZING TABLES WITH
 THIS PERMIT - ONE FOR A 10 PSI SYSTEM WITH DRISCOPLEX
 PIPE AND ONE FOR A 11.0 INCH W.C.( LOW PRESSURE) SYSTEM
 WITH SCH. 40 METALLIC PIPE BUT NO METALLIC PIPE IS
 SHOWN.CLARIFY. SHOW WHAT THE PSI OF THE SYSTEM IS ON
 THE PE PIPE.
 4) SHOW THE LOCATION OF THE U/G GAS LINE FROM THE TANK
 TO ITS TERMINATION POINT ABOVE GROUND ON THE SURVEY.
 WPB AMEND. TO FBC SEC. 107.2.1.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  
  