Plan Review Details - Permit 16100697
Plan Review Stops For Permit 16100697
Review Stop ENG ENGINEERING CSD
Rev No 1 Status P Date 2016-12-19 Cont ID  
Sent By mkhan Date 2016-12-19 Time 15:29 Rev Time 4.00
Received By mkhan Date 2016-12-19 Time 15:29 Sent To FIRE
Notes
2016-12-19 16:39:57DECEMBER 19, 2016
  
 PASSED WITH THE FOLLOWING PROVISO:
  
 1. CONSTRUCTION COORDINATION WILL BE REQUIRED WITH
 CITY'S TRAFFIC GROUP FOR PROPER STRIPING, SIGNAGE AND
 SIGNALIZATION. THIS SHALL BE PERFORMED UNDER SEPARATE
 RIGHT-OF-WAY PERMIT APPLICATION. RIGHT-OF-WAY PERMIT
 APPLICATION CAN BE DOWNLOADED FROM THE FOLLOWING LINK:
  
 HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR
 MS,-PERMITS-APPLICATIONS
  
 2. UTILITY CONNECTION WORK ON CHARLOTTE AVE. SHALL
 REQUIRE SUBMISSION OF A RIGHT-OF-WAY PERMIT AND A
 PRE-CONSTRUCTION MEETING SHALL
 BE ARRANGED WITH THE CITY OF WEST PALM BEACH
 ENGINEERING SERVICES DEPARTMENT SO THAT A CONSTRUCTION
 COORDINATOR CAN BE ASSIGNED;
  
 3. WATER METER AND CONTROL VALVE SHALL BE INSTALLED IN
 THE CITY'S RIGHT-OF-WAY AS SHOWN ON THE CITY'S STANDARD
 DETAILS;
  
 4. LOCATION OF THE SANITARY SEWER CLEANOUT SHALL BE PER
 THE CITY'S STANDARD DETAI GS-6;
  
 5. CONTRACTOR SHALL IDENTIFY/VERIFY ALL UTILITY
 CROSSINGS AND IF THERE IS A CONFLICT CONTACT THE CITY
 OF WEST PALM BEACH UTILITY ENGINEER;
  
 6. WATER PIPE SHALL BE D.I.P. AND SANITARY SEWER PIPES
 SHALL BE SDR-26;
  
 7. SEPARATION REQUIREMENTS FOR WATER, SANITARY OR STORM
 SEWER SHALL BE PER 62-555.314 F.A.C. ACCORDING TO WHICH
 A HORIZONTAL DISTANCE OF TEN FEET IS PREFERRED BETWEEN
 THESE UTILITY LINES;
  
 8. AS OF DECEMBER 20, 2015 THE CITY OF WEST PALM BEACH
 CROSS-CONNECTION CONTROL MANUAL HAS BEEN REVISED,
 MAKING KNOWN THAT "ALL BACKFLOW DEVICES MUST BE LEAD
 FREE." FOR MORE INFORMATION REFER TO THE LINK BELOW:
  
 HTTP://WPB.ORG/DEPARTMENTS/PUBLIC-UTILITIES/FORMS-PUBLI
 CATIONS/BACKFLOW-CROSS-CONNECTION-CONTROL-MANUAL
  
 9. FOR SANITATION/GARBAGE PICKUP COORDINATE WITH CITY'S
 SANITATION DEPARTMENT AT: (561) 822-2075 EXT: 2076;
 EMAIL: [email protected]
  
 SENT TO FIRE FOR THEIR REVIEW.
  
 JANUARY 9, 2017
  
 FOLLOWING COMMENTS HAVE BEEN ADDRESSED:
  
 #3, #4, #6, #7.
  
 PLANS APPROVED WITH 'PROVISO' AS NOTED ON THE PLANS ON
 JANUARY 9, 2017.

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2016-12-22 Cont ID  
Sent By pleduc Date 2016-12-22 Time   Rev Time 0.00
Received By pleduc Date 2016-12-22 Time 12:51 Sent To PC
Notes
2016-12-22 12:58:25THIS PLAN WAS REVIEWED AND APPROVED BY PETER LEDUC,
 FIRE MARSHAL, WITH THE FOLLOWING COMMENTS:
  
 PLEASE CONSIDER THE FOLLOWING AS PROVISO:
  
 THESE PROVISO COMMENTS WILL BE VERIFIED AND CONFIRMED
 AT THE TIME OF FIRE INSPECTION. FAILURE TO FOLLOW THESE
 PROVISO COMMENTS WILL RESULT IN A FAILED FIRE
 INSPECTION.
  
  
 1) ALL FIRE LINE INSTALLATION SHALL COMPLY WITH NFPA
 24.
  
  
 2) PROVIDE ALL FIRE LINE PRODUCT MANUFACTURER'S SPEC
 SHEETS AT THE TIME OF INSPECTOR FOR INSPECTOR TO REVIEW
 AND CONFIRM.
  
  
 PETER LEDUC
 FIRE MARSHAL
 561-804-4709
 [email protected]
  

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2016-12-22 Cont ID  
Sent By pleduc Date 2016-12-22 Time   Rev Time 0.00
Received By pleduc Date 2016-10-24 Time 12:25 Sent To  
Notes
2016-10-25 12:25:55ROUTED TO ZONING

Review Stop Z ZONING
Rev No 1 Status P Date 2016-10-28 Cont ID  
Sent By njwira Date 2016-10-28 Time 10:37 Rev Time 0.00
Received By njwira Date 2016-10-25 Time 17:13 Sent To ENG
Notes
***NONE***