Plan Review Details - Permit 16061102
Plan Review Stops For Permit 16061102
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2016-07-29 Cont ID  
Sent By rmcdouga Date 2016-07-29 Time 18:58 Rev Time 0.00
Received By rmcdouga Date 2016-07-29 Time 18:32 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2016-06-30 Cont ID  
Sent By rmcdouga Date 2016-06-30 Time 08:38 Rev Time 0.00
Received By rmcdouga Date 2016-06-29 Time 19:04 Sent To P
Notes
2016-06-30 08:38:25PLAN REVIEW COMMENTS FOR SOLAR DOMESTIC WATER HEATER
  
 1ST REVIEW: FBC FIFTH EDITION (2014)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) THE FLORIDA LICENSED ENGINEER IS REQUIRED TO SIGN BY
 HAND HIS HANDWRITTEN SIGNATURE (FACSIMILES ARE NOT
 ACCEPTABLE) ON THE PLANS AND OTHER CONSTRUCTION
 DOCUMENTS. FAC 61G15-23.002 DIGITAL SIGNATURES ARE ONLY
 ACCEPTABLE ON ELECTRONICALLY SUBMITTED DOCUMENTS.
 FAC61G15-23.003
  
 2) PLANS ARE REQUIRED TO BE DRAWN TO A MINIMUM 1/8 INCH
 SCALE PER 107.2.1.4.
  
 3) PROVIDE DOCUMENTATION FROM THE MANUFACTURED BUILDING
 DESIGNER OF RECORD TO SHOW THAT THE BUILDING CAN SAFELY
 SUPPORT ALL ADDITIONAL LOADING THAT MAY BE CREATED BY
 INSTALLATION OF THIS PHOTOVOLTAIC SYSTEM AND SOLAR
 WATER HEATER COLLECTOR ON THE ROOF. FBC-R 301.1 SUBMIT
 A SIGNED AND SEALED LETTER FROM THE ENGINEER CERTIFYING
 THAT HE HAS REVIEWED THE STRUCTURE AND FOUND IT TO BE
 STRUCTURALLY CAPABLE OF SAFELY SUPPORTING ALL
 ADDITIONAL LOADING THAT WILL BE CREATED BY INSTALLATION
 OF THIS PHOTOVOLTAIC SYSTEM AND SOLAR WATER HEATER
 COLLECTOR ON THE ROOF. FBCR M2301.2.2
  
 4) PROVIDE THE WIND DESIGN DATA ON THE PLANS. FBCR
 301.2.1
  
 5) PROVIDE THE MANUFACTURER'S SPECIFICATIONS, LISTING
 AND INSTALLATION DETAILS FOR THE SOLAR WATER HEATER
 SYSTEM. FBC 107.2.1 AND FBCR-M2301.3
  
 6) PROVIDE SPECIFIC MOUNTING AND ANCHORING DETAILS FOR
 THE ROOF TOP SOLAR COLLECTOR. FBCR-M2301.2.2 AND
 FBCR301.1
  
  
  

Review Stop E ELECTRICAL
Rev No 2 Status P Date 2016-08-01 Cont ID  
Sent By mvaldes Date 2016-07-28 Time 11:48 Rev Time 0.00
Received By mvaldes Date 2016-07-28 Time 11:19 Sent To  
Notes
2016-07-28 11:57:14REVIEW 2014 5TH FBC ED. NEC 2011
 MARIO VALDES
 ELECTRICAL PLAN EXAMINER
 561-805-6713
 [email protected]
  
  
  
 PASSED WITH THE FOLLOWING PROVISO :
  
 - PER FAC RULE 61G4-15.021, A SEPERATE ELECTRICAL
 PERMIT BY A LICENSED ELECTRICAL CONTRACTOR IS REQUIRED
 FOR THE CONNECTION TO THE PREMISES INTERGAL WIRING OR
 UTILITY SERVICE.
 THE CVC CONTRACTOR IS LIMITED TO THE PV SUPPLY SIDE OF
 THE POWER CONDITIONING UNIT, PV SOURCE CIRCUITS, PV
 OUTPUT CIRCUITS, AND BATTERY STORAGE SYSTEM CIRCUITS.

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2016-06-30 Cont ID  
Sent By mvaldes Date 2016-06-30 Time 10:25 Rev Time 0.00
Received By mvaldes Date 2016-06-30 Time 10:25 Sent To  
Notes
2016-06-30 10:28:38REVIEW 2014 5TH FBC ED. NEC 2011
 MARIO VALDES
 ELECTRICAL PLAN EXAMINER
 561-805-6713
 [email protected]
  
 - PLEASE CLARIFY IF SOLAR WATER HEATER SYSTEM HAS ANY
 ELECTRICAL COMPONENTS AND IF SO PROVIDE A RISER
 SCHEMATIC PLAN TO INCLUDE SPECS, WIRE AND BREAKER SIZE
 ? FBC 107 MINIMUM PLAN CRITERIA.

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2016-07-29 Cont ID  
Sent By rmcdouga Date 2016-07-29 Time 18:58 Rev Time 0.00
Received By rmcdouga Date 2016-07-20 Time 11:24 Sent To  
Notes
2016-07-21 11:25:34RESUB ROUTED TO NJWIRA VIA ZONING INBOX

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2016-07-05 Cont ID  
Sent By cpuell Date 2016-07-05 Time 16:16 Rev Time 0.00
Received By cpuell Date 2016-06-17 Time 07:02 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 3 Status P Date 2016-08-02 Cont ID  
Sent By gjohnson Date 2016-08-02 Time 18:11 Rev Time 0.00
Received By gjohnson Date 2016-08-02 Time 18:11 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 2 Status F Date 2016-07-27 Cont ID  
Sent By gjohnson Date 2016-07-27 Time 15:36 Rev Time 0.00
Received By gjohnson Date 2016-07-27 Time 15:36 Sent To  
Notes
2016-07-27 15:37:172ND REVIEW
  
  
  
 GEORGE JOHNSON
 PLUMBING PLANS EXAMINER LL
 CITY OF WEST PALM BEACH
 DEVELOPMENT SERVICES
 BUILDING DIVISION
 561-805-6711
 [email protected]
  
  
 PLUMBING COMMENTS: 2ND REQUEST
  
 1. PROVIDE MANUFACTURE SPECIFICATION AND INSTILLATION
 GUIDE. PER WPB AMEND. TO FBC SEC. 107.2.1 THE
 MANUFACTURE SPECIFICATION MUST SHOW COMPLIANCE WITH THE
 FSEC STANDARD 101-15
  
  
  
  
 2. PROVIDE PLUMBING RISER DIAGRAM THAT SHOWS COMPLIANCE
 WITH FBC M SEC 1402.5.1 PRESSURE AND TEMPERATURE.
 SOLAR ENERGY SYSTEM COMPONENTS CONTAINING PRESSURIZED
 FLUIDS SHALL BE PROTECTED AGAINST PRESSURES AND
 TEMPERATURES EXCEEDING DESIGN LIMITATIONS WITH A
 PRESSURE AND TEMPERATURE RELIEF VALVE. EACH SECTION OF
 THE SYSTEM IN WHICH EXCESSIVE PRESSURES ARE CAPABLE OF
 DEVELOPING SHALL HAVE A RELIEF DEVICE LOCATED SO THAT A
 SECTION CANNOT BE VALVED OFF OR OTHERWISE ISOLATED FROM
 A RELIEF DEVICE. RELIEF VALVES SHALL COMPLY WITH THE
 REQUIREMENTS OF SECTION 1006.4 AND DISCHARGE IN
 ACCORDANCE WITH SECTION 1006.6.
 1402.5.3 PROTECTION FROM FREEZING.
 SYSTEM COMPONENTS SHALL BE PROTECTED FROM DAMAGE BY
 FREEZING OF HEAT TRANSFER LIQUIDS AT THE LOWEST AMBIENT
 TEMPERATURES THAT WILL BE ENCOUNTERED DURING THE
 OPERATION OF THE SYSTEM.
  
  
  
 DUE TO THE DEFICIENCIES OF THIS PLAN A COMPLETE AND
 THOROUGH REVIEW CANNOT BE DONE AT THIS TIME. UPON
 RESUBMITTAL THERE MAYBE ADDITIONAL COMMENTS.
 WHEN RESUBMITTING PLANS, REMOVE AND REPLACE ANY PAGES
 AS NECESSARY. A NARRATIVE LISTING THE ORIGINAL REVIEW
 COMMENT NUMBER WITH A DESCRIPTION OF THE CHANGES MADE
 AND IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE
 THE CHANGE CAN BE FOUND WILL HELP EXPEDITE THE REVIEW.

Review Stop P PLUMBING
Rev No 1 Status F Date 2016-07-01 Cont ID  
Sent By gjohnson Date 2016-07-01 Time 16:28 Rev Time 0.00
Received By gjohnson Date 2016-07-01 Time 16:28 Sent To  
Notes
2016-07-27 15:35:562ND REVIEW
  
  
  
 GEORGE JOHNSON
 PLUMBING PLANS EXAMINER LL
 CITY OF WEST PALM BEACH
 DEVELOPMENT SERVICES
 BUILDING DIVISION
 561-805-6711
 [email protected]
  
  
 PLUMBING COMMENTS: 2ND REQUEST
  
 1. PROVIDE MANUFACTURE SPECIFICATION AND INSTILLATION
 GUIDE. PER WPB AMEND. TO FBC SEC. 107.2.1 THE
 MANUFACTURE SPECIFICATION MUST SHOW COMPLIANCE WITH THE
 FSEC STANDARD 101-15
  
  
  
  
 2. PROVIDE PLUMBING RISER DIAGRAM THAT SHOWS COMPLIANCE
 WITH FBC M SEC 1402.5.1 PRESSURE AND TEMPERATURE.
 SOLAR ENERGY SYSTEM COMPONENTS CONTAINING PRESSURIZED
 FLUIDS SHALL BE PROTECTED AGAINST PRESSURES AND
 TEMPERATURES EXCEEDING DESIGN LIMITATIONS WITH A
 PRESSURE AND TEMPERATURE RELIEF VALVE. EACH SECTION OF
 THE SYSTEM IN WHICH EXCESSIVE PRESSURES ARE CAPABLE OF
 DEVELOPING SHALL HAVE A RELIEF DEVICE LOCATED SO THAT A
 SECTION CANNOT BE VALVED OFF OR OTHERWISE ISOLATED FROM
 A RELIEF DEVICE. RELIEF VALVES SHALL COMPLY WITH THE
 REQUIREMENTS OF SECTION 1006.4 AND DISCHARGE IN
 ACCORDANCE WITH SECTION 1006.6.
 1402.5.3 PROTECTION FROM FREEZING.
 SYSTEM COMPONENTS SHALL BE PROTECTED FROM DAMAGE BY
 FREEZING OF HEAT TRANSFER LIQUIDS AT THE LOWEST AMBIENT
 TEMPERATURES THAT WILL BE ENCOUNTERED DURING THE
 OPERATION OF THE SYSTEM.
  
  
  
 DUE TO THE DEFICIENCIES OF THIS PLAN A COMPLETE AND
 THOROUGH REVIEW CANNOT BE DONE AT THIS TIME. UPON
 RESUBMITTAL THERE MAYBE ADDITIONAL COMMENTS.
 WHEN RESUBMITTING PLANS, REMOVE AND REPLACE ANY PAGES
 AS NECESSARY. A NARRATIVE LISTING THE ORIGINAL REVIEW
 COMMENT NUMBER WITH A DESCRIPTION OF THE CHANGES MADE
 AND IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE
 THE CHANGE CAN BE FOUND WILL HELP EXPEDITE THE REVIEW.
2016-07-01 16:43:091ST REVIEW
  
  
  
 GEORGE JOHNSON
 PLUMBING PLANS EXAMINER LL
 CITY OF WEST PALM BEACH
 DEVELOPMENT SERVICES
 BUILDING DIVISION
 561-805-6711
 [email protected]
  
  
 PLUMBING COMMENTS:
  
 1. PROVIDE MANUFACTURE SPECIFICATION AND INSTILLATION
 GUIDE. PER WPB AMEND. TO FBC SEC. 107.2.1
  
 2. PROVIDE PLUMBING RISER DIAGRAM. PER WPB AMEND. TO
 FBC SEC. 107.3.5.3(13)
  
  
  
 DUE TO THE DEFICIENCIES OF THIS PLAN A COMPLETE AND
 THOROUGH REVIEW CANNOT BE DONE AT THIS TIME. UPON
 RESUBMITTAL THERE MAYBE ADDITIONAL COMMENTS.
 WHEN RESUBMITTING PLANS, REMOVE AND REPLACE ANY PAGES
 AS NECESSARY. A NARRATIVE LISTING THE ORIGINAL REVIEW
 COMMENT NUMBER WITH A DESCRIPTION OF THE CHANGES MADE
 AND IDENTIFYING THE SHEET OR SPECIFICATION PAGE WHERE
 THE CHANGE CAN BE FOUND WILL HELP EXPEDITE THE REVIEW.

Review Stop Z ZONING
Rev No 2 Status P Date 2016-07-22 Cont ID  
Sent By njwira Date 2016-07-22 Time 15:53 Rev Time 0.00
Received By njwira Date 2016-07-21 Time 13:16 Sent To P
Notes
***NONE***

Review Stop Z ZONING
Rev No 1 Status P Date 2016-07-05 Cont ID  
Sent By njwira Date 2016-07-05 Time 16:09 Rev Time 0.00
Received By njwira Date 2016-07-05 Time 16:09 Sent To I
Notes
2016-07-05 16:10:227/5/16- PASSED
  
 1. SOLAR PANELS DO NOT EXCEED 33FT. FROM THE GROUND.
  
 PLEASE CONTACT:
 NATHAN WIRA
 (561)822-1442
 [email protected]
  