Plan Review Details - Permit 16051252
Plan Review Stops For Permit 16051252
Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2016-06-23 Cont ID  
Sent By shill Date 2016-06-23 Time 12:36 Rev Time 0.00
Received By shill Date 2016-06-23 Time 12:36 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2016-06-01 Cont ID  
Sent By shill Date 2016-06-01 Time 15:24 Rev Time 0.00
Received By shill Date 2016-06-01 Time 15:24 Sent To  
Notes
2016-06-01 15:24:46SEE 16051111

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2016-05-31 Cont ID  
Sent By shill Date 2016-05-31 Time 12:06 Rev Time 0.00
Received By shill Date 2016-05-31 Time 12:06 Sent To  
Notes
2016-05-31 12:07:23****CORRECTIONS****
 (SAME COMMENTS AS 16051111)
  
 SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 1. EVIDENCE OF DELEGATED ENGINEERING REVIEW IS TO BE
 ACCOMPLISHED IN THE FOLLOWING WAYS (FBC 107):
  
 A. A SHOP DRAWING REVIEW STAMP DIRECTLY ON THE
 DELEGATED ENGINEERING BY THE EOR (OR BY ANOTHER
 LICENSED ENGINEER IN THE EOR'S OFFICE, PLEASE INCLUDE
 NAME & LICENSE NUMBER). THE SIGNATURE/INITIALS SHOULD
 BE IN INK, OR
  
 B. A REVIEW LETTER, SIGNED AND SEALED IN ACCORDANCE
 WITH FAC61G15-23.002/FS471. THE LETTER IS TO BE VERY
 SPECIFIC - ENGINEER NAME AND FIRM, DRAWINGS REVIEWED
 (SHEET NUMBERS, DATES, NAME OF DRAWINGS). THE LETTER
 SUBMITTED HAS A DIGITALLY CREATED SIGNATURE, REFERS TO
 DRAWINGS PREPARED BY CECO, BUT CECO DELEGATED TO
 ANOTHER ENGINEER AND FIRM OR,
  
 C. THE DELEGATED ENGINEERING COULD BE SUBMITTED
 DIGITALLY. IF THIS ENGINEER (RAFAEL E. PUERTA, PE OF
 DPS INC) DOES NOT HAVE A DIGITAL SIGNATURE, THE PAPER
 ORIGINAL CAN BE PROVIDED AT THE BUILDING DIVISION AS A
 "SIGNATURE DOCUMENT." THE ENGINEER CAN SIGN AND SEAL
 HIS REVIEW LETTER DIGITALLY.
  
 2. FOR DELEGATED ENGINEERING REVIEW PREVIOUSLY REVIEWED
 WITH A DIGITAL IMAGE OF A SIGNATURE, PLEASE PROVIDE
 SIGNED AND SEALED ORIGINALS TO PROPERLY DOCUMENT THE
 FILE.
  
  
  
  

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2016-06-23 Cont ID  
Sent By shill Date 2016-06-23 Time 12:36 Rev Time 0.00
Received By shill Date 2016-06-23 Time 12:36 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2016-06-01 Cont ID  
Sent By shill Date 2016-06-01 Time 15:24 Rev Time 0.00
Received By shill Date 2016-06-01 Time 10:28 Sent To  
Notes
2016-06-01 10:28:42RESUB ROUTED TO SHILL

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2016-05-31 Cont ID  
Sent By shill Date 2016-05-31 Time 12:07 Rev Time 0.00
Received By shill Date 2016-05-27 Time 08:15 Sent To  
Notes
2016-05-31 08:15:32SHILL'S DESK