Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status P Date 2016-07-13 Cont ID  
Sent By rmcdouga Date 2016-07-13 Time 10:56 Rev Time 0.00
Received By rmcdouga Date 2016-07-13 Time 10:56 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2016-06-13 Cont ID  
Sent By rmcdouga Date 2016-06-13 Time 18:08 Rev Time 0.00
Received By rmcdouga Date 2016-06-13 Time 18:08 Sent To  
Notes
2016-06-13 18:08:20PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC FIFTH EDITION (2014)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) THE SUBSTRATE IS LISTED AS CONCRETE BLOCK ON THE
 INSTALLATION SCHEDULE FOR ALL OPENINGS AND THE SPACING
 MARKED ON THE PRODUCT APPROVAL FOR SOME OF THE STORM
 PANELS AND ACCORDIONS IS FOR POURED CONCRETE. FBC
 107.2.3 THE TABLES ARE SEPARATED INTO POURED CONCRETE
 AND CONCRETE BLOCK COLUMNS ON BOTH THE ACCORDION
 SHUTTER AND PANEL PRODUCT APPROVALS. IDENTIFY THE
 SUBSTRATE THAT YOU WILL BE FASTENING TO AND SELECT THE
 FASTENER SPACING FOR THE TYPE OF MOUNT FROM THE
 APPROPRIATE COLUMN.
  
 2) THE GLASS SEPARATION DISTANCE IS MORE THAN 1" FOR
 BOTH THE PANEL AND THE ACCORDION SHUTTER PRODUCT
 APPROVALS. PLEASE CORRECT THE INSTALLATION SCHEDULE.
 FBC R301.1
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2016-05-24 Cont ID  
Sent By rmcdouga Date 2016-05-24 Time 14:53 Rev Time 0.00
Received By rmcdouga Date 2016-05-24 Time 14:53 Sent To  
Notes
2016-05-24 14:53:27PLAN
 REVIEW COMMENTS
  
 1ST REVIEW: FBC FIFTH EDITION (2014)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) THE INSTALLATION SCHEDULE IS NOT CLEAR WHICH ONES
 ARE THE STORM PANELS AND WHICH ARE THE ACCORDIONS. THE
 SUBSTRATE IS LISTED AS CONCRETE BLOCK ON THE
 INSTALLATION SCHEDULE FOR ALL OPENINGS AND THE SPACING
 MARKED ON THE PRODUCT APPROVAL FOR SOME OF THE STORM
 PANELS AND ACCORDIONS IS FOR POURED CONCRETE. FBC
 107.2.3
  
 2) FOR THE SHUTTER MOUNTING TYPE ON THE INSTALLATION
 SCHEDULE YOU NEED TO LIST THE SPECIFIC NUMBER FROM THE
 PRODUCT APPROVAL FOR THE TOP AND BOTTOM MOUNTING TYPE
 FOR EACH OPENING. FBC 107.2.3
  
 3) INDICATE WHICH OPENINGS HAVE PANELS AND WHICH HAVE
 ACCORDIONS. FBC 107.2.3
  
 4) TWO COPIES OF THE CONSTRUCTION DOCUMENTS ARE
 REQUIRED TO BE SUBMITTED AND ONLY ONE WAS SUBMITTED. I
 MADE COPIES FOR YOU THIS TIME, HOWEVER, FUTURE
 SUBMITTALS WILL BE DENIED. FBC 107.1

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2016-07-13 Cont ID  
Sent By rmcdouga Date 2016-07-13 Time 10:57 Rev Time 0.00
Received By rmcdouga Date 2016-06-30 Time 14:29 Sent To  
Notes
2016-06-30 14:29:50RESUB ROUTED TO RMCDOUGAL

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2016-06-13 Cont ID  
Sent By rmcdouga Date 2016-06-13 Time 18:08 Rev Time 0.00
Received By rmcdouga Date 2016-06-06 Time 10:04 Sent To  
Notes
2016-06-07 10:04:21RESUB ROUTED TO RMCDOUGAL

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2016-06-13 Cont ID  
Sent By rmcdouga Date 2016-05-24 Time 18:08 Rev Time 0.00
Received By rmcdouga Date 2016-05-17 Time 10:32 Sent To  
Notes
2016-05-18 10:32:58BLDG MISC 1