2016-02-13 06:14:42 | 1) SUBMIT TWO COPIES OF A FLOOR PLAN SHOWING THE |
| LOCATION OF THE TANKLESS WATER HEATER . 2014 FBC SEC. |
| 107.2.1. |
| 2) INDICATE ON THE PLAN IF THE TANKLESS WATER HEATER IS |
| AN INDOOR OR OUTDOOR MODEL.2014 FBC SEC. 107.2.1. |
| 3) IDENTIFY THE MODEL OF THE WATER HEATER ON BOTH SETS |
| OF SPECIFICATIONS BY CIRCLING THE UNIT MODEL NUMBER |
| .2014 FBC SEC. 107.2.1. |
| 4) INDICATE ON THE PLAN IF THE NEW UNIT IS REPLACING AN |
| EXISTING GAS TANKLESS WATER HEATER OR IF IT IS |
| REPLACING A GAS STORAGE TANK TYPE WATER HEATER. IF |
| REPLACING A STORAGE TANK TYPE, A SEPARATE PERMIT WILL |
| BE REQUIRED FOR THE REQUIRED ELECTRICAL WORK. |
| 5) SUBMIT A WATER AND GAS RISER DIAGRAM FOR CHANGES |
| THAT MAY BE MADE TO THE GAS AND PLUMBING SYSTEMS. 2014 |
| FBC SEC.107.3.5.1.3. |
| 6) A COPY OF THE INSTALLATION MANUAL SHALL BE ONSITE |
| FOR INSPECTION.2014 FGC SEC.305.1. |
| 7) IF THE NEW UNIT IS INDOORS, SUBMIT COMBUSTION AIR |
| CLACULATIONS FOR REVIEW IN ACCORDANCE WITH 2014 FGC |
| SEC.304. |
| 8) SUPPLY VENTING DETAILS FOR THE UNIT. SHOW TYPE OF |
| VENT, SIZE, LOCATION, HEIGHT ABOVE ROOF, ETC. IN |
| ACCORDANCE WITH THE MANUF.INSTALLATION MANUAL PER 2014 |
| FGC SEC.304.1 AND FGC SEC. 503.8. |
| 9) COMPLY WITH THE FOLLOWING ITEMS FOR GAS IF |
| APPLICABLE. |
| 10) SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE |
| LENGTH OF ALL CUT SECTIONS OF PIPE PER 2014 FBC-FUEL |
| GAS, SECS. 402.4.1, 402.4.2. OR 2014 FBC-RES SEC. |
| G2413. |
| 11)SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL |
| PIPE SIZES, AND THE CORRESPONDING EHD NUMBER OF THE |
| CORRUGATED STAINLESS STEEL TUBING FOR EACH PIPE SIZE. |
| WPB AMENDMENTS TO FBC SEC.107.2.1. |
| 12) TYPE OF GAS (LP OR NATURAL). |
| 13) SHOW THE BTU LOAD OF EACH APPLIANCE / EQUIPMENT AND |
| THE TOTAL BTU LOAD ON THE SYSTEM. REFER TO THE 2014 |
| FBC-FUEL GAS SECS.401.8 THRU 402.6.1 AND TABLES 402.4 |
| (1) THRU 402.4 (37) OR 2014 FBC-RES. SEC. G2413. 15. |
| 14) INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM |
| ON THE PLAN PER 2014 FBC-FUEL GAS SEC.402.2 OR FBC RES. |
| SEC. G2413.2. |
| |
| PLUMBING PLAN REVIEW |
| TIM LARGE |
| CHIEF PLUMBING INSPECTOR |
| 561-805-6692 |
| [email protected] |
| |
| |
| ANY QUESTIONS REGARDING THESE REQUIREMENTS MAY BE |
| REFERRED TO THE CHIEF PLUMBING INSPECTOR AT |
| 561-805-6692. |
| |
| REV. 7/24/15 - TKL |
| |
| |
| |
| |