2016-01-27 08:31:05 | 1.SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE |
| LENGTH OF ALL CUT SECTIONS OF PIPE PER 2014 FBC-FUEL |
| GAS, SECS. 402.4.1, 402.4.2. OR 2014 FBC-RES SEC. |
| G2413. |
| |
| 2.SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL |
| PIPE SIZES, AND THE CORRESPONDING EHD NUMBER OF THE |
| CORRUGATED STAINLESS STEEL TUBING FOR EACH PIPE SIZE. |
| WPB AMENDMENTS TO FBC SEC.107.2.1. |
| |
| 3.BTU LOAD OF EACH APPLIANCE AND THE TOTAL BTU LOAD ON |
| THE SYSTEM. REFER TO THE 2014 FBC-FUEL GAS SECS.401.8 |
| THRU 402.6.1 AND TABLES 402.4 (1) THRU 402.4 (37) OR |
| 2014 FBC-RES. SEC. G2413. |
| |
| 5.SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (METER |
| OR MP REGULATOR) TO THE MOST REMOTE OUTLET IN THE |
| BUILDING AND / OR SYSTEM PER THE 2014 FBC-FUEL GAS |
| SEC.402.4.1 OR 2014 FBC-RES. SEC. G 2413.3. |
| |
| 6.SUBMIT CALCULATIONS FOR COMBUSTION AIR PER THE 2014 |
| FBC-FUEL GAS CODE SEC.304.1 OR 2014 FBC-RES. SEC. G |
| 2407. |
| |
| 7.INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM ON |
| THE PLAN PER 2014 FBC-FUEL GAS SEC.402.2 OR FBC RES. |
| SEC. G2413.2. . |
| |
| 8.SUBMIT A DETAIL SHOWING THE TYPE, LOCATION, SIZE AND |
| TERMINATION OF THE GAS VENTS PER 2014 FBC-FUEL GAS |
| SECS. 502 THRU 505. OR 2014 FBC-RES. SEC.G2426. |
| |
| 9.SUBMIT MANUFACTURER?S SPECIFICATION SHEETS / |
| INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO VERIFY |
| COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND |
| FBC-2014 FUEL GAS CODE SEC. 402.2, AND 301.3 OR 2014 |
| FBC-RES. SEC. G2404.3. GAS APPLIANCES SHALL BE LISTED |
| AND LABELED. |
| |
| THE FUEL GAS CODE CAN BE REVIEWED AT |
| WWW.FLORIDABUILDING.ORG |
| |
| ANY QUESTIONS REGARDING THESE REQUIREMENTS MAY BE |
| REFERRED TO THE CHIEF PLUMBING INSPECTOR AT |
| 561-805-6692. |
| |
| |
| PLUMBING PLAN REVIEW |
| TIM LARGE |
| CHIEF PLUMBING INSPECTOR |
| 561-805-6692 |
| [email protected] |
| |
| |
| |
| |
| |
| |
| |
| |
| |
| |