Plan Review Details - Permit 15090229
Plan Review Stops For Permit 15090229
Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status P Date 2015-10-09 Cont ID  
Sent By shill Date 2015-10-09 Time 12:33 Rev Time 0.00
Received By shill Date 2015-10-09 Time 12:33 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status F Date 2015-10-06 Cont ID  
Sent By shill Date 2015-10-06 Time 14:22 Rev Time 0.00
Received By shill Date 2015-10-06 Time 14:22 Sent To  
Notes
2015-10-06 14:26:06****CORRECTIONS****
  
 SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 FROM PREVIOUS LIST:
  
 1. SEE PAGE 6. SPANS BETWEEN 6' AND 8'8" REQUIRE 6.5"
 SPACING, 12.5 PROPOSED (FOR EXAMPLE, SEE OPENINGS 2, 3,
 5). PLEASE REVISE AND CHECK ALL.
  
 SPANS HAVE BEEN REVISED AND NOW APPEAR INCORRECT.
  
 SPAN IS DISTANCE ANCHOR TO ANCHOR. DIMENSIONS SHOULD BE
 WIDTH X HEIGHT. IF A PANEL IS INSTALLED HORIZONTALLY,
 "WIDTH" IS THE FIRST DIMENSION. FOR EXAMPLE, SEE
 OPENING 2. PREVIOUS INSTALLATIN SCHEDULE GAVE A SPAN OF
 89.5. SINCE THE WIDTH OF THE OPENING IS 89.5, THE SPAN
 SHOULD BE 95.5", BUT NOW THE SPAN IS STATED AS 48".
  
 IF SPANS ARE INCORRECT, ANCHOR SPACING CANNOT BE
 REVISED.
  
 PLEASE HAVE QUALIFIER REVIEW THE COMMENT LISTS AND THE
 ANCHOR SCHEDULES SUBMITTED PRIOR TO RESUBMITTAL.
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2015-09-29 Cont ID  
Sent By shill Date 2015-09-29 Time 17:36 Rev Time 0.00
Received By shill Date 2015-09-29 Time 17:36 Sent To  
Notes
2015-09-29 17:40:08****CORRECTIONS****
  
 SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 1. SEE PAGE 6. SPANS BETWEEN 6' AND 8'8" REQUIRE 6.5"
 SPACING, 12.5 PROPOSED (FOR EXAMPLE, SEE OPENINGS 2, 3,
 5). PLEASE REVISE AND CHECK ALL.
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2015-09-16 Cont ID  
Sent By shill Date 2015-09-16 Time 17:01 Rev Time 0.00
Received By shill Date 2015-09-16 Time 17:01 Sent To  
Notes
2015-09-16 17:03:11****CORRECTIONS****
  
 SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 1. HORIZONTAL INSTALLATIONS TYPICALLY HAVE BLOCK AS A
 SUBSTRATE (FILLED CELLS RATHER THAN FORMED AND POURED
 CONCRETE). PLEASE REVISE OR PROVIDE INFORMATION AS TO
 HOW IT HAS BEEN DETERMINED THAT THE SUBSTRATE IS
 CONCRETE (WOULD REQUIRE FORMED AND POURED COLUMNS ON
 BOTH SIDES OF EACH OPENING), FBC 5TH ED. RESIDENTIAL
 301.
  

Review Stop I INCOMING/PROCESSING
Rev No 4 Status N Date 2015-10-09 Cont ID  
Sent By shill Date 2015-10-09 Time 12:33 Rev Time 0.00
Received By shill Date 2015-10-08 Time 16:10 Sent To  
Notes
2015-10-08 16:10:36RESUB ROUTED TO SHILL

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2015-10-06 Cont ID  
Sent By shill Date 2015-10-06 Time 14:26 Rev Time 0.00
Received By shill Date 2015-10-01 Time 14:39 Sent To  
Notes
2015-10-01 14:39:43RESUB ROUTED TO SHILL

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2015-09-29 Cont ID  
Sent By shill Date 2015-09-29 Time 17:40 Rev Time 0.00
Received By shill Date 2015-09-21 Time 12:43 Sent To  
Notes
2015-09-21 12:43:23RESUB ROUTED TO SHILL

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2015-09-16 Cont ID  
Sent By shill Date 2015-09-16 Time 17:03 Rev Time 0.00
Received By shill Date 2015-09-16 Time 17:03 Sent To  
Notes
***NONE***


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved