Plan Review Stops For Permit 15081167 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
2 |
Status |
P |
Date |
2016-01-25 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2016-01-25 |
Time |
16:50 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2016-01-25 |
Time |
16:20 |
Sent To |
|
|
Notes |
2016-01-25 17:12:30 | COMPLY WITH FBC R4501.17 FOR RESIDENTIAL POOL BARRIER | | REQUIREMENTS. |
|
|
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
F |
Date |
2015-09-02 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2015-09-02 |
Time |
18:45 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2015-09-02 |
Time |
17:48 |
Sent To |
|
|
Notes |
2015-09-02 18:52:26 | PLAN | | REVIEW COMMENTS | | | | 1ST REVIEW: FBC FIFTH EDITION (2014) | | ROBERT MCDOUGAL, CBO | | COMMERCIAL COMBINATION PLANS EXAMINER | | (561) 805-6714 | | [email protected] | | | | DENIED BY BUILDING | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | 1) SHOW COMPLIANCE WITH FBCR 4501.17 FOR REQUIRED | | SWIMMING POOL BARRIER. SPECIFY THE METHOD OR | | COMBINATION OF METHODS THAT WILL BE USED. | | | | 2) SECTION R403.9.2 OF THE 2014 ENERGY CONSERVATION | | CODE REQUIRES TIME SWITCHES FOR PUMPS AND HEATERS. | | | | 3) SECTION R403.9.3 OF THE 2014 ENERGY CONSERVATION | | CODE REQUIRES HEATED POOLS TO HAVE COVERS TO REDUCE | | HEAT LOSS. |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
2 |
Status |
P |
Date |
2016-01-25 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2016-01-25 |
Time |
16:50 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2016-01-25 |
Time |
16:26 |
Sent To |
|
|
Notes |
|
|
Review Stop |
E |
ELECTRICAL |
Rev No |
1 |
Status |
F |
Date |
2015-09-02 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2015-09-02 |
Time |
18:07 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2015-09-02 |
Time |
18:07 |
Sent To |
|
|
Notes |
2015-09-02 18:09:13 | PLAN | | REVIEW COMMENTS | | | | 1ST REVIEW: FBC FIFTH EDITION (2014) | | ROBERT MCDOUGAL, CBO | | COMMERCIAL COMBINATION PLANS EXAMINER | | (561) 805-6714 | | [email protected] | | | | DENIED BY ELECTRICAL | | PLEASE ADDRESS THE ITEMS NOTED BELOW: | | | | 1) THE POOL PERMIT WILL NOT BE ISSUED UNTIL A POOL | | ELECTRICAL SUB-PERMIT IS SUBMITTED. FBC 105.1 | | | | 2) SHOW COMPLIANCE WITH FBCR - E 4204.2 FOR | | EQUIPOTENTIAL BONDING. | | | | 3) SHOW COMPLIANCE WITH FBCR - E 4204.3 FOR REQUIRED | | BONDING OF POOL WATER. |
|
|
Review Stop |
G |
GAS REVIEW |
Rev No |
1 |
Status |
N |
Date |
2015-09-02 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2015-09-02 |
Time |
04:45 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2015-09-02 |
Time |
04:45 |
Sent To |
|
|
Notes |
2015-09-02 04:46:41 | THE HEATER IS AN ELECTRIC HEAT PUMP. THERE IS NO GAS ON | | THIS POOL.TKL. |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
2 |
Status |
N |
Date |
2016-01-25 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2016-01-25 |
Time |
16:50 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2016-01-15 |
Time |
15:33 |
Sent To |
|
|
Notes |
2016-01-19 15:33:48 | RESUB ROUTED TO TKLARGE |
|
|
Review Stop |
I |
INCOMING/PROCESSING |
Rev No |
1 |
Status |
N |
Date |
2015-09-02 |
|
|
Cont ID |
|
Sent By |
rmcdouga |
Date |
2015-09-02 |
Time |
18:52 |
Rev Time |
0.00 |
Received By |
rmcdouga |
Date |
2015-08-31 |
Time |
13:56 |
Sent To |
|
|
Notes |
2015-08-31 13:56:40 | ROUTED TO ZONING |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
2 |
Status |
P |
Date |
2016-01-20 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2016-01-20 |
Time |
12:36 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2016-01-20 |
Time |
11:44 |
Sent To |
|
|
Notes |
|
|
Review Stop |
P |
PLUMBING |
Rev No |
1 |
Status |
F |
Date |
2015-09-02 |
|
|
Cont ID |
|
Sent By |
tklarge |
Date |
2015-09-02 |
Time |
05:06 |
Rev Time |
0.00 |
Received By |
tklarge |
Date |
2015-09-02 |
Time |
04:27 |
Sent To |
|
|
Notes |
2015-09-02 05:04:31 | 1) POOL SPECS BOX: THE TURNOVER RATE FOR THE POOL IS | | NOTED AS 6 HR. ? MIN. FOR 21,542 GALS. I HAVE | | CALCULATED A TURNOVER RATE OF 11.58 HOURS. CLARIFY. | | 2) SUBMIT 2 COPIES OF THE MANUFACTURER'S SPECIFICATIONS | | FOR THE HEAT PUMP. THE INFORMATION SHALL CLEARLY SHOW | | COMPLIANCE WITH THE 2014 FL. ENERGY CODE SEC.R403.9.1 & | | R403.9.1.2. HEAT PUMPS SHALL HAVE A MINIMUM COP OF 4.0 | | AND SHALL BE TESTED IN ACCORDANCE WITH AHRI 1160, TABLE | | 2.A TEST REPORT FROM AN INDEPENDENT LABORATORY IS | | REQUIRED TO VERIFY PROCEDURE COMPLIANCE. | | 3) 2014 FBC- ENERGY CODE SEC. R 403.9.2 - TIME SWITCHES | | OR OTHER CONTROL METHODS THAT CAN AUTOMATICALLY TURN | | OFF AND ON HEATERS AND PUMPS ACCORDING TO A PRESET | | SCHEDULE SHALL BE INSTALLED ON ALL HEATERS AND PUMPS. | | HEATERS, PUMPS AND MOTORS THAT HAVE BUILT IN TIMERS | | SHALL BE DEEMED IN COMPLIANCE WITH THIS REQUIREMENT. | | 4) SUBMIT A COPY OF THE PUMP CURVE FOR THE POOL/SPA | | PUMP AND IDENTIFY THE TOTAL DYNAMIC HEAD CALCULATIONS | | PER FOR THIS POOL PER ANSI/APSP-7 SEC. 4.4.1. | | 5) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR BOTH | | CHANNEL DRAINS TO ENSURE COMPLIANCE WITH ANSI/APSP-7 | | SEC.5.5.1 | | | | | | | | PLUMBING PLAN REVIEW | | TIM LARGE | | CHIEF PLUMBING INSPECTOR | | 561-805-6692 | | [email protected] | | | | | | |
|
|
Review Stop |
Z |
ZONING |
Rev No |
1 |
Status |
P |
Date |
2015-09-01 |
|
|
Cont ID |
|
Sent By |
sgraham |
Date |
2015-09-01 |
Time |
10:08 |
Rev Time |
0.00 |
Received By |
sgraham |
Date |
2015-09-01 |
Time |
10:08 |
Sent To |
B |
|
Notes |
|
|