Review Stop E ELECTRICAL
Rev No 2 Status P Date 2015-07-28 Cont ID  
Sent By albarran Date 2015-07-28 Time 15:33 Rev Time 0.00
Received By albarran Date 2015-07-28 Time 15:13 Sent To I
Notes
2015-07-28 15:34:27THOUGH THE RESUB WAS NOT AS REQUIRED, AN ENLARGED VIEW
 OF THE AREA OF WORK WAS SUBMITTED FOR BE INCLUDED WITH
 THE PERMIT DOCUMENTS.

Review Stop E ELECTRICAL
Rev No 1 Status F Date 2015-07-28 Cont ID  
Sent By albarran Date 2015-07-28 Time 11:15 Rev Time 0.00
Received By albarran Date 2015-07-28 Time 11:09 Sent To I
Notes
2015-07-28 11:19:56PLEASE NOTE THAT I, MIKE ALBARRAN, ELECTRICAL PLANS
 EXAMINER HAVE COMPLETED THE REVIEW OF THE ABOVE
 MENTIONED JOB. BELOW ARE THE COMMENTS WITH REGARDS TO
 THE REQUIRED CORRECTIONS. THE FOLLOWING ITEMS SHALL BE
 CORRECTED AND THE PLANS RESUBMITTED FOR ANOTHER REVIEW.
  
 1. FROM THE DRAWINGS SUBMITTED I CANT IDENTIFY THE
 SCOPE OF WORK. YOU SHALL INDICATE YOUR SCOPE OF WORK ON
 THE DRAWINGS.
 2. YOU SHALL DESCRIBED HOW YOU INTEND TO COMPLETE THIS
 SCOPE OF WORK, EI: DESCRIBED THE PROPOSED WIRING METHOD
 AND HOW WILL YOU BE GETTING FROM ONE DEVICE TO ANOTHER.
 3. PROVIDE LITERATURE ON THE PROPOSED EQUIPMENT, MAKING
 SURE THAT IT WILL PERFORM IN A FAIL-SAFE MANNER.
  
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT
 CORRECTED PAGES INTO TO SUBMITTAL AND LEAVE THE
 PREVIOUSLY REVIEWED SHEETS.
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status P Date 2015-07-23 Cont ID  
Sent By wjolin Date 2015-07-23 Time 10:47 Rev Time 0.00
Received By wjolin Date 2015-07-23 Time 10:42 Sent To E
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2015-07-28 Cont ID  
Sent By albarran Date 2015-07-28 Time 15:40 Rev Time 0.00
Received By albarran Date 2015-07-28 Time 14:47 Sent To  
Notes
2015-07-28 15:41:167/28/15 - PASSED ELECTRICAL REVIEW. CONTRACTOR NOTIFIED
 VIA EMAIL. SENT TO SMALL READY BIN "K". MA
2015-07-28 15:13:01RESUBMIT OF ELECTRICAL CORRECTIONS
  

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2015-07-28 Cont ID  
Sent By albarran Date 2015-07-28 Time 11:20 Rev Time 0.00
Received By albarran Date 2015-07-21 Time 11:30 Sent To  
Notes
2015-07-28 11:24:227/28/15 - FAILED ELECTRICAL REVIEW AS NOTED. CONTRACTOR
 NOTIFIED VIA EMAIL. SENT TO SMALL DENIED BIN "K". MA
2015-07-21 11:31:07ROUTED TO FIRE