Plan Review Details - Permit 15070729
Plan Review Stops For Permit 15070729
Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status P Date 2015-09-10 Cont ID  
Sent By skennedy Date 2015-09-10 Time 10:43 Rev Time 0.00
Received By skennedy Date 2015-09-10 Time 10:43 Sent To  
Notes
***NONE***

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status F Date 2015-08-24 Cont ID  
Sent By skennedy Date 2015-08-24 Time 14:12 Rev Time 0.00
Received By skennedy Date 2015-08-24 Time 14:12 Sent To  
Notes
2015-08-24 14:21:451ST REVIEW: FBC 2014 5TH ED.
 RESIDENTIAL
  
 THE IMPROVEMENT EXCEEDS 30% OF THE ASSESSED VALUE OF
 THE STRUCTURE. PROVIDE AN ENERGY SUBMITTAL PER FBC-R
 CHAPTER 400.
  
 STEVEN KENNEDY, CBO
 CHIEF PLANS EXAMINER
 (561) 805-6710
 [email protected]
  

Review Stop E ELECTRICAL
Rev No 1 Status P Date 2015-08-24 Cont ID  
Sent By skennedy Date 2015-08-24 Time 14:13 Rev Time 0.00
Received By skennedy Date 2015-08-24 Time 14:13 Sent To  
Notes
***NONE***

Review Stop HIST HISTORICAL
Rev No 1 Status P Date 2015-08-05 Cont ID  
Sent By fmittner Date 2015-08-05 Time 15:27 Rev Time 0.00
Received By fmittner Date 2015-08-05 Time 15:27 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 2 Status P Date 2015-09-10 Cont ID  
Sent By skennedy Date 2015-09-10 Time 10:43 Rev Time 0.00
Received By skennedy Date 2015-09-08 Time 15:24 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2015-08-24 Cont ID  
Sent By skennedy Date 2015-08-24 Time 14:13 Rev Time 0.00
Received By skennedy Date 2015-07-17 Time 15:45 Sent To  
Notes
2015-07-17 15:45:33R24

Review Stop M MECHANICAL (A/C)
Rev No 2 Status P Date 2015-09-10 Cont ID  
Sent By skennedy Date 2015-09-10 Time 10:43 Rev Time 0.00
Received By skennedy Date 2015-09-10 Time 10:43 Sent To  
Notes
***NONE***

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2015-08-24 Cont ID  
Sent By skennedy Date 2015-08-24 Time 14:13 Rev Time 0.00
Received By skennedy Date 2015-08-24 Time 14:13 Sent To  
Notes
2015-08-24 14:20:591ST REVIEW: FBC 2014 5TH ED.
 RESIDENTIAL
  
 THE IMPROVEMENT EXCEEDS 30% OF THE ASSESSED VALUE OF
 THE STRUCTURE. PROVIDE AN ENERGY SUBMITTAL PER FBC-R
 CHAPTER 400 AND PROVIDE AN HVAC SIZING CALUCLATION FOR
 THE NEW SYSTEM.
  
 STEVEN KENNEDY, CBO
 CHIEF PLANS EXAMINER
 (561) 805-6710
 [email protected]
  

Review Stop P PLUMBING
Rev No 2 Status P Date 2015-09-09 Cont ID  
Sent By gjohnson Date 2015-09-09 Time 15:30 Rev Time 0.00
Received By gjohnson Date 2015-09-09 Time 15:30 Sent To  
Notes
***NONE***

Review Stop P PLUMBING
Rev No 1 Status F Date 2015-08-04 Cont ID  
Sent By gjohnson Date 2015-08-04 Time 13:49 Rev Time 0.00
Received By gjohnson Date 2015-08-03 Time 17:14 Sent To  
Notes
2015-08-04 14:02:091ST REVIEW FBC 2014
  
 COMMENTS
  
 1. PLUMBING RISER MUST COMPLY WITH FBC RES P3108.1
  
 2. PLUMBING RISER MUST MATCH FLOOR PLAN
 WPB AMENDMENTS 107.3.5.3
  
 3.SHOW CONDESNATE RUNNING OUTSIDE BUILDING CANNOT
 TERMINATE INTO SANITARY
 WPB ORD. 90-126[B].5
  
 4. NEED RISER FOR WASHING MACHINE
 WPB AMENDMENTS 107.3.5.3
  
 5. NOTE PAN DRAIN FOR WH ON PLAN
 WPB AMENDMENTS 107.3.5.3
  
 5. NOTE ON PLAN CHANGING TUB TO SHOWER AND RELOCATION
 OF LAVS IN MASTER BATH
 WPB AMENDMENTS 107.2.1
  
  
  
 GEORGE JOHNSON
 PLUMBING PLANS EXAMINER LL
 CITY OF WEST PALM BEACH
 EX. 561-805-6711
 [email protected]
  
  
  
  