Plan Review Details - Permit 15061111
Plan Review Stops For Permit 15061111
Review Stop B BUILDING (STRUCTURAL)
Rev No 4 Status P Date 2015-11-18 Cont ID  
Sent By shill Date 2015-11-18 Time 12:35 Rev Time 0.00
Received By shill Date 2015-11-18 Time 12:35 Sent To  
Notes
2015-11-18 12:41:26****PROVISO****
 ISSUED AT CONTRACTOR'S AND OWNER'S RISK
  
 SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 APPLICATION FOR INTERIOR RENOVATION AND CHANGE OF
 OCCUPANCY IS PENDING.
  
 CONDITIONAL APPROVAL OF THIS PERMIT IS SUBJECT TO
 APPROVAL OF RENOVATION / CHANGE OF OCCUPANCY PERMIT
 15110357. OWNER/CONTRACTOR IS HEREBY INFORMED THAT THE
 WORK COVERED UNDER THIS PERMIT MAY REQUIRE FUTURE
 REMOVAL OR ALTERATION PENDING OUTCOME OF THE REVIEW OF
 15110357.
  
 ISSUANCE OF PERMIT #15110357 IS REQUIRED PRIOR TO FINAL
 INSPECTION.
 FAILURE TO OBTAIN FINAL INSPECTION FOR 15110357 MAY
 RESULT IN THIS PERMIT BEING REVOKED AND A NEW VIOLATION
 TO BE ISSUED.
  
 APPLICANT ALSO AGREES THAT IT IS ACCEPTABLE FOR A
 VIOLATION FOR WORK DONE WITHOUT PERMIT AND CHANGE OF
 OCCUPANCY WITHOUT PERMIT BE ISSUED WITHOUT A SITE VISIT
 DUE TO THE URGENCY OF ISSUANCE OF THIS PERMIT. A SITE
 VISIT MAY BE DONE BY THIS DEPARTMENT AT A FUTURE DATE.
  
 THESE CONDITIONS HAVE BEEN SENT VIA EMAIL TO JOSEPH
 MORRISON (APPLICANT) AND CONTRACTOR (AUTOMATED AIR
 CONDITIONING). BOTH HAVE BEEN INFORMED THAT, IF THEY DO
 NOT AGREE WITH THESE CONDITIONS, THEY ARE NOT TO PICK
 UP THIS PERMIT.
  
  
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 3 Status F Date 2015-08-14 Cont ID  
Sent By shill Date 2015-08-14 Time 06:23 Rev Time 0.00
Received By shill Date 2015-08-14 Time 06:23 Sent To  
Notes
2015-08-14 07:00:51****CORRECTIONS****
  
 SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 1. APPLICATION IS FOR: "COMPLETE MECHANICAL
 MODIFICATIONS AS PER DRAWINGS."
  
 THE OCCUPANCY CLASSIFICATION FOR THIS STRUCTURE IS (FBC
 2001) S2, STORAGE.
  
 A SEARCH OF BUSINESS TAX RECEIPTS DOES NOT SHOW A
 BUSINESS TAX AT THIS UNIT.
  
 SEE FBC 2010 107.2.1:
  
 CONSTRUCTION DOCUMENTS SHALL BE OF SUFFICIENT CLARITY
 TO INDICATE THE LOCATION, NATURE AND EXTENT OF THE WORK
 PROPOSED AND SHOW IN DETAIL THAT IT WILL CONFORM TO THE
 PROVISIONS OF THIS CODE AND RELEVANT LAWS, ORDINANCES,
 RULES AND REGULATIONS, AS DETERMINED BY THE BUILDING
 OFFICIAL. SUCH DRAWINGS AND SPECIFICATIONS SHALL
 CONTAIN INFORMATION, IN THE FORM OF NOTES OR OTHERWISE,
 AS TO THE QUALITY OF MATERIALS, WHERE QUALITY IS
 ESSENTIAL TO CONFORMITY WITH THE TECHNICAL CODES.
  
 APPLICATION AND PLANS ARE TO MODIFY A MECHANICAL
 SYSTEM. OTHER DOCUMENTS INDICATE THAT THIS IS A CHANGE
 OF OCCUPANCY. SEE THE DEFINITION OF S2 (LOW HAZARD
 STORAGE). THIS CLASSIFICATION IS FOR THE STORAGE OF NON
 COMBUSTIBLE MATERIALS. BASED ON THE DOCUMENTS PROVIDED,
 THE PROPOSED USE IS NOT "STORAGE OF NON COMBUSTIBLE
 MATERIALS."
  
 "A" SHEETS WERE SUBMITTED BUT NOTHING ON THESE SHEETS
 INDICATE THAT THIS IS A CHANGE OF OCCUPANCY. IT IS NOT
 CLEAR HOW ENGINEER CONSIDERED THIS ISSUE ADDRESSED.
 LACK OF AN "A" SHEET AND MECHANICAL/STRUCTURAL ONLY
 WOULD HAVE EXCLUDED LIFE SAFETY / CHANGE OF OCCUPANCY
 ISSUES FROM THIS PLAN. INCLUSION OF AN "A" SHEET
 IMPLIES THAT LIFE SAFETY / CHANGE OF OCCUPANCY WAS
 ADDRESSED. IT IS NOT CLEAR WHY "A" SHEETS WERE
 SUBMITTED BUT NOTHING WHICH SHOULD HAVE BEEN SHOWN ON
 THESE SHEETS WERE INCLUDED IN THE PLAN.
  
 SEE FBC 105.1 REQUIRED. ANY CONTRACTOR, OWNER, OR AGENT
 AUTHORIZED IN ACCORDANCE WITH FLORIDA STATUTE 489 WHO
 INTENDS TO ... CHANGE THE OCCUPANCY OF A BUILDING OR
 STRUCTURE, ... , OR TO CAUSE ANY SUCH WORK TO BE DONE,
 SHALL FIRST MAKE APPLICATION TO THE BUILDING OFFICIAL
 AND OBTAIN THE REQUIRED PERMIT. (REFER TO CODE FOR FULL
 TEXT; THIS HAS BEEN SHORTENED TO INCLUDE ONLY THE
 PORTION PERTINENT TO THIS PROJECT).
  
 EITHER PROVIDE A PERMIT NUMBER FOR THE CHANGE OF
 OCCUPANCY FROM S2 (05020247) OR A QUALIFIED DESIGN
 PROFESSIONAL IS TO ADDRESS THE ISSUE OF CHANGE OF
 OCCUPANCY.
  
 SEE ALSO FBC 111.1:
  
 111.1 USE AND OCCUPANCY. NO BUILDING OR STRUCTURE SHALL
 BE USED OR OCCUPIED, AND NO CHANGE IN
 THE EXISTING OCCUPANCY CLASSIFICATION OF A BUILDING OR
 STRUCTURE OR PORTION THEREOF SHALL BE MADE, UNTIL
 THE BUILDING OFFICIAL HAS ISSUED A CERTIFICATE OF
 OCCUPANCY THEREFORE AS PROVIDED HEREIN. ISSUANCE OF A
 CERTIFICATE OF OCCUPANCY SHALL NOT BE CONSTRUED AS AN
 APPROVAL OF A VIOLATION OF THE PROVISIONS OF THIS
 CODE OR OF OTHER ORDINANCES OF THE JURISDICTION. SAID
 CERTIFICATE SHALL NOT BE ISSUED UNTIL ALL REQUIRED
 ELECTRICAL, GAS, MECHANICAL, PLUMBING AND FIRE
 PROTECTION SYSTEMS HAVE BEEN INSPECTED FOR
 COMPLIANCE WITH THE TECHNICAL CODES AND OTHER
 APPLICABLE LAWS AND ORDINANCES AND RELEASED BY THE
 BUILDING OFFICIAL.
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 2 Status F Date 2015-07-31 Cont ID  
Sent By shill Date 2015-07-31 Time 16:37 Rev Time 0.00
Received By shill Date 2015-07-31 Time 16:37 Sent To  
Notes
2015-07-31 16:39:02****CORRECTIONS****
  
 SAMANTHA HILL
 BUILDING PLANS EXAMINER
 [email protected]
 561-805-6724
  
 1. MY APOLOGIES, BUT I AM UNABLE TO LOCATE THE ORIGINAL
 SUBMITTAL. PLEASE PROVIDE A SIGNED PERMIT APPLICATION.
 THIS CAN BE A COPY IF YOU HAVE ONE AVAILABLE. (THE
 ORIGINAL WILL "TURN UP", BUT I DO NOT WANT TO CAUSE ANY
 ISSUANCE DELAYS).
  
 2. SEE MECHANICAL COMMENTS; PROVIDE THE MECHANICAL
 STAND PRODUCT APPROVAL, FBC 1609, FAC9N-3.
  
  

Review Stop B BUILDING (STRUCTURAL)
Rev No 1 Status P Date 2015-07-06 Cont ID  
Sent By shill Date 2015-07-06 Time 17:36 Rev Time 0.00
Received By shill Date 2015-07-06 Time 17:36 Sent To  
Notes
2015-07-06 17:45:20PROVISO - GUARDRAIL REQUIRED
  

Review Stop FIRE FIRE DEPARTMENT
Rev No 3 Status P Date 2015-08-07 Cont ID  
Sent By pleduc Date 2015-08-07 Time   Rev Time 0.00
Received By pleduc Date 2015-08-07 Time 11:57 Sent To B
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 2 Status P Date 2015-07-31 Cont ID  
Sent By pleduc Date 2015-07-31 Time   Rev Time 0.00
Received By pleduc Date 2015-07-31 Time 12:15 Sent To B
Notes
***NONE***

Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status F Date 2015-06-26 Cont ID  
Sent By pleduc Date 2015-06-26 Time   Rev Time 0.00
Received By pleduc Date 2015-06-26 Time 14:26 Sent To B
Notes
2015-06-26 14:39:21THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE
 MARSHAL, WITH THE FOLLOWING COMMENTS:
  
 PER NFPA 90A SMOKE DETECTORS ARE REQUIRED FOR AIR
 CAPACITY'S GREATER THAN 2000FT3

Review Stop I INCOMING/PROCESSING
Rev No 3 Status N Date 2015-08-14 Cont ID  
Sent By shill Date 2015-08-14 Time 06:23 Rev Time 0.00
Received By shill Date 2015-08-03 Time 13:32 Sent To  
Notes
2015-08-11 10:11:288/11 TO SH DESK
  
  

Review Stop I INCOMING/PROCESSING
Rev No 2 Status N Date 2015-07-31 Cont ID  
Sent By shill Date 2015-07-31 Time 16:39 Rev Time 0.00
Received By shill Date 2015-07-20 Time 15:22 Sent To  
Notes
***NONE***

Review Stop I INCOMING/PROCESSING
Rev No 1 Status N Date 2015-07-23 Cont ID  
Sent By skennedy Date 2015-06-25 Time 15:21 Rev Time 0.00
Received By skennedy Date 2015-06-25 Time 13:46 Sent To  
Notes
2015-06-25 14:51:38ADDED BUILDING, FIRE, AND ZONING REVIEWS/PLACED IN
 C02/CCOLE 6/25/15

Review Stop M MECHANICAL (A/C)
Rev No 3 Status P Date 2015-08-04 Cont ID  
Sent By ccole Date 2015-08-04 Time 14:43 Rev Time 0.00
Received By ccole Date 2015-08-04 Time 12:11 Sent To FIRE
Notes
2016-02-02 07:51:18MECHANICAL PROVISIOS
 8/4/15
  
 1) MANUFACTURER'S SPECIFICATIONS FOR THE EXHAUST HOOD
 AND DUCT WORK SHALL BE ON-SITE AT TIME OF INSPECTION.
 2) RECIRCULATION OF CHEMICAL FUMES THROUGH THE AC
 SYSTEM IS PROHIBITED.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  
  
  

Review Stop M MECHANICAL (A/C)
Rev No 2 Status F Date 2015-07-24 Cont ID  
Sent By ccole Date 2015-07-24 Time 07:24 Rev Time 0.00
Received By ccole Date   Time   Sent To  
Notes
2015-07-24 07:42:072ND REVIEW: FBC 2010 MECHANICAL
 7/24/15
  
 1) IN RESPONSE TO 1ST REVIEW COMMENT #5, ORBIT LABS HAS
 SUBMITTED LETTERS INDICATING MINIMAL LEVELS OF
 FLAMMABLE VAPORS, GAS, FUMES, MIST, AND DUSTS FROM THE
 CHEMICAL PROCESSES WILL BE EXHAUSTED THROUGH THE NEW
 CAPTURE HOOD SYSTEM. IN ORDER TO VERIFY COMPLIANCE WITH
 SECTION 510.2 FBC-10 MECHANICAL (WHICH OUTLINES THE
 PARAMETERS BY WHICH A HAZARDOUS EXHAUST SYSTEM IS
 REQUIRED), AND IN ACCORDANCE WITH SECTION 502.8, PLEASE
 SUBMIT MSDS SHEETS FOR THE CHEMICAL 2-PROPANOL,
 METHANOL, AND NIOTROGEN. INDICATE ON THE PLANS THE
 QUANTITIES OF EACH CHEMICAL BEING STORED IN THE
 FACILITY, AND HOW THE CHEMICALS ARE BEING STORED- ROOM,
 CLOSET, CABINET? THE ISSUE IS FURTHER EVIDENCE IS
 REQUIRED TO DETERMINE AN ACCURATE OCCUPANCY
 CLASSIFICATION FOR THE FACILITY, AND WHICH ASSOCIATED
 CODE REQUIREMENTS MUST BE ENFORCED- REFER TO TABLE
 307.1(1) AND SECTION 414 FBC-10 BUILDING.
 2) THE PLAN INDICATES A MANUALLY OPERATED RHEOSTAT WILL
 CONTROL THE EXHAUST FAN OPERATION- REFER TO SECTION
 502.8.1.1 ITEM 3 AND PROVIDE EVIDENCE AS NOTED IN
 COMMENT #1 TO INDICATE CONTINUOUS OPERATION IS NOT
 APPLICABLE.
 3) INDICATE ON THE PLAN THE TYPE OF AND GAGE OF EXHAUST
 DUCT MATERIAL TO BE CONNECTED TO THE EXHAUST HOOD, AND
 TO THE NITROGEN GENERATOR- REFER TO SECTION 510.8
 FBC-10 MECHANICAL.
 3) AS PREVIOUSLY REQUESTED, PROVIDE AN EQUIPMENT
 SCHEDULE AND AN EQUIPMENT FLOOR PLAN LAYOUT. IDENTIFY
 ALL EQUIPMENT ON THE PLAN AS EITHER NEW, EXISTING, OR
 FUTURE.
 4) AS PREVIOUSLY REQUESTED, SUBMIT THE MIAMI-DADE NOA
 FOR THE AC ROOF STAND.
 5) THE SUBMITTED ENERGY COMPLIANCE FORM DOES NOT
 INCLUDE THE ENERGY EFFICIENCY COMPLIANCE SUMMARY PAGES:
 6) PLEASE NOTE THAT THE CITY OF WPB BUILDING DIVISION
 REQUIRES ALL COMPLIANCE DOCUMENTS, NOA'S, PRODUCT CUT
 SHEETS ETC. TO BE SUBMITTED IN DUPLICATE.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  

Review Stop M MECHANICAL (A/C)
Rev No 1 Status F Date 2015-06-25 Cont ID  
Sent By ccole Date 2015-06-25 Time 13:47 Rev Time 0.00
Received By ccole Date 2015-06-25 Time 13:47 Sent To  
Notes
2015-06-25 14:30:241ST REVIEW: FBC 2010 MECHANICAL
  
 1) THE AC SIZING LOAD CALCULATIONS INDICATE 60775
 BTU/HR FOR MISCELLANEOUS: PLEASE PROVIDE MORE SPECIFIC
 INFORMATION. IS THIS LOAD BEING GENERATED BY EQUIPMENT-
 EITHER NEW OR EXISTING?
 2) SHEET S-1 AND THE STRUCTURAL CALCULATIONS INDICATE
 TWO NEW EXHAUST FANS, HOWEVER ONLY ONE IS NOTED AND
 SHOWN IN THE MECHANICAL PLANS: PLEASE CLARIFY.
 3) CLARIFY HOW MAKE-UP AIR IS BEING PROVIDED FOR THE
 EXHAUST HOOD- EXISTING OR NEW SUPPLY? PROVIDE NOTES AND
 CALCULATIONS, AND DRAWINGS FOR ALL NEW INSTALLATIONS.
 4) PLEASE PROVIDE AN EQUIPMENT SCHEDULE ON THE PLAN
 IDENTIFYING ALL NEW AND EXISTING EQUIPMENT IN THE LAB,
 INCLUDING THE PIECE OF EQUIPMENT THAT IS REQUIRING THE
 EXHAUST HOOD.
 5) WHAT IS THE TYPE OF EXHAUST- REFERENCE SECTION
 501.2.1 FBC-10 MECH. FOR OUTLET LOCATIONS, AND 510.2
 FOR HAZARDOUS EXHAUST REQUIREMENTS.
 6) SHEET A-1 SHOWS THE NEW AC AND FAN EQUIPMENT WITHIN
 10 FT. OF THE ROOF EDGE WHICH REQUIRES EITHER A GUARD
 OR A MINIMUM 42' PARAPET WALL- SECTION 304.11.
 7) PROVIDE A SUBMITTAL PACKAGE PREPARED BY THE DESIGN
 PROFESSIONAL OF RECORD THAT INCLUDES FL. PRODUCT
 APPROVALS AND/OR MIAMI-DADE NOA'S, AND PRODUCT DATA
 SHEETS FOR ALL NEW COMPONENTS OF THE AC AND EXHAUST
 SYSTEMS.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  

Review Stop Z ZONING
Rev No 1 Status N Date 2015-07-23 Cont ID  
Sent By jroach Date 2015-07-23 Time 15:29 Rev Time 0.00
Received By skennedy Date   Time   Sent To  
Notes
2015-07-23 15:30:06PER SG


Account Summary | Usage Policy | Privacy Policy