Plan Review Details - Permit 15060750
Plan Review Stops For Permit 15060750 |
Review Stop |
B |
BUILDING (STRUCTURAL) |
Rev No |
1 |
Status |
P |
Date |
2015-06-20 |
|
|
Cont ID |
|
Sent By |
tmoore |
Date |
2015-06-20 |
Time |
08:21 |
Rev Time |
0.00 |
Received By |
tmoore |
Date |
2015-06-20 |
Time |
08:20 |
Sent To |
ENG |
|
Notes |
2015-06-20 08:21:36 | HAVE ALL NEEDED UTILITY RELEASES. PASSING AND MOVING ON | | TO ENGINEERING AND HISTORIC. |
|
|
Review Stop |
ENG |
ENGINEERING CSD |
Rev No |
3 |
Status |
P |
Date |
2015-07-17 |
|
|
Cont ID |
|
Sent By |
cranford |
Date |
2015-07-17 |
Time |
15:32 |
Rev Time |
0.00 |
Received By |
cranford |
Date |
2015-07-17 |
Time |
15:31 |
Sent To |
|
|
Notes |
2015-07-17 15:31:54 | CHECK FOR LAND STABILIZATION BOND DEPOSITED $122.00 | | | | | | KEC |
|
|
Review Stop |
ENG |
ENGINEERING CSD |
Rev No |
2 |
Status |
F |
Date |
2015-07-07 |
|
|
Cont ID |
|
Sent By |
cranford |
Date |
2015-07-07 |
Time |
10:00 |
Rev Time |
0.00 |
Received By |
cranford |
Date |
2015-07-07 |
Time |
09:33 |
Sent To |
HIST |
|
Notes |
2015-07-07 09:34:09 | SPOKE WITH CONTRACTOR AND CLARIFIED WHICH BUILDING | | WOULD BE DEMOLISHED. STILL NEED EROSION CONTROL / LAND | | STABILIZATION BOND. | | | | KELLY CRANFORD | | 494-1098 |
|
|
Review Stop |
ENG |
ENGINEERING CSD |
Rev No |
1 |
Status |
F |
Date |
2015-06-23 |
|
|
Cont ID |
|
Sent By |
cranford |
Date |
2015-06-23 |
Time |
08:47 |
Rev Time |
0.00 |
Received By |
cranford |
Date |
2015-06-22 |
Time |
11:11 |
Sent To |
HIST |
|
Notes |
2015-06-23 08:47:34 | 1. SUBMIT A SKETCH CLEARLY INDICATING THE LIMITS OF THE | | DEMOLITION. | | | | 2. SUBMIT A STORMWATER POLLUTION PREVENTION PLAN | | (SWPPP) AS REQUIRED BY SECTION 94-450 OF THE CODE OF | | ORDINANCES. THE PLAN WILL NEED TO ADDRESS PREVENTING | | TURBID WATER, DIRT, DUST AND OTHER CONSTRUCTION DEBRIS | | FROM LEAVING THE SITE EXCEPT IN SEALED CONTAINERS. | | GUIDELINES FOR PREPARING THE SWPPP ARE UNDER: | | HTTP://WPB.ORG/WP-CONTENT/UPLOADS/SITES/7/2012/05/2011- | | 12-21-15-00-29-SWPPPGUIDE.PDF | | | | 3. PLEASE SUBMIT A BOND OR DEPOSIT IN AN AMOUNT | | COVERING THE COST ASSOCIATED WITH IMPLEMENTATION OF THE | | SWPPP AND LAND STABILIZATION OF THE SITE. THE BOND WILL | | BE RELEASED UPON APPROVED INSPECTION OF TIE-BEAMS OR | | SIMILAR VERTICAL CONSTRUCTION. (CITY CODE SECTION | | 94-450) | | | | | | KELLY CRANFORD, P.E. | | LAND DEVELOPMENT ENGINEER | | PUBLIC WORKS DEPARTMENT | | CITY OF WEST PALM BEACH | | [email protected] | | 561-494-1098 (OFFICE) | | |
|
|
Review Stop |
HIST |
HISTORICAL |
Rev No |
1 |
Status |
P |
Date |
2015-07-22 |
|
|
Cont ID |
|
Sent By |
fmittner |
Date |
2015-07-22 |
Time |
14:56 |
Rev Time |
0.00 |
Received By |
fmittner |
Date |
2015-07-22 |
Time |
14:56 |
Sent To |
|
|
Notes |
|
|
|